3040 S BUCKINGHAM ROAD 90016

Certificate Information: 3040 S BUCKINGHAM ROAD 90016

Application / Permit
20010-10000-01797
Plan Check / Job No.
B20LA09383
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADU PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g) ATTACHED TO EXISTING GARAGE
Permit Issued
Issued on 3/12/2021
Issuing Office
Current Status
CofO Issued on 9/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/27/2020 APPLICANT
Assigned to Plan Check Engineer 6/18/2020 JESSE ARELLANO
Corrections Issued 6/30/2020 JESSE ARELLANO
Quality Review Completed 7/16/2020 ALLEN MANALANSAN
Building Plans Picked Up 7/20/2020 APPLICANT
Applicant returned to address corrections 9/26/2020 JESSE ARELLANO
Applicant returned to address corrections 12/16/2020 JESSE ARELLANO
Plan Check Approved 2/26/2021 JESSE ARELLANO
Issued 3/12/2021 APPLICANT
CofO in Progress 9/9/2022 STUART CHAPMAN
Permit Finaled 9/11/2022 DEROLD HAUFF
CofO Issued 9/11/2022 DEROLD HAUFF
Permit Finaled 9/11/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/11/2020 CECILIO NAVARRO
Sewer availability Cleared 9/11/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 9/15/2020 CECILIO NAVARRO
Hydrant and Access approval Cleared 9/29/2020 MATTHEW CRAIG
Green Code Cleared 12/16/2020 JESSE ARELLANO
Construction near power lines Cleared 1/23/2021 RIDWAN HARDY
Roof/Waste drainage to street Cleared 2/23/2021 THOMAS LANG

Contact Information

Contractor Carmichael Maintenance & Construction; Lic. No.: 983154-B P O BOX 451627      LOS ANGELES, CA 90045
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/30/2021 Approved ROBERT MCDOWELL
Sewer 5/25/2021 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 6/15/2021 Partial Approval KATHRYN BUTTERWORTH
FLOOD-Elevation Certificate 6/29/2021 Approved STUART CHAPMAN
Footing/Foundation/Slab 6/29/2021 Corrections Issued STUART CHAPMAN
METHANE-Barrier 6/29/2021 Approved STUART CHAPMAN
METHANE-Subgrade 6/29/2021 Approved STUART CHAPMAN
Footing/Foundation/Slab 8/2/2021 Approved RICHARD STEINBACH
ELECTRICAL-Rough 9/24/2021 Partial Approval CALEB MEISTER
PLUMBING-Rough 9/24/2021 Corrections Issued CALEB MEISTER
ELECTRICAL-Rough 10/7/2021 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 10/7/2021 Partial Approval STUART CHAPMAN
PLUMBING-Rough 10/7/2021 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 10/25/2021 Corrections Issued KATHRYN BUTTERWORTH
FLOOD-Proofing Certificate 10/25/2021 Approved KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 10/25/2021 Partial Approval KATHRYN BUTTERWORTH
Green Building Rough 10/25/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
METHANE-Rough 10/25/2021 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 10/25/2021 Corrections Issued KATHRYN BUTTERWORTH
ELECTRICAL-Rough 10/29/2021 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 10/29/2021 Partial Approval STUART CHAPMAN
PLUMBING-Rough 10/29/2021 Approved STUART CHAPMAN
BUILDING-Rough-Frame 11/24/2021 Approved STUART CHAPMAN
Green Building Rough 11/24/2021 Approved STUART CHAPMAN
Insulation 11/24/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 11/24/2021 Partial Approval STUART CHAPMAN
Drywall Nailing 12/7/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 12/7/2021 Approved STUART CHAPMAN
ELECTRICAL-Final 1/21/2022 Not Ready for Inspection ALFREDO BALANDRA
ELECTRICAL-Final 1/27/2022 Corrections Issued STUART CHAPMAN
Final 3/1/2022 Corrections Issued STUART CHAPMAN
Green Building Final 3/1/2022 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 3/1/2022 SGSOV Not Ready STUART CHAPMAN
Smoke Detectors 3/1/2022 Approved STUART CHAPMAN
ELECTRICAL-Final 3/4/2022 Approved HORACE FULTZ
Final 3/4/2022 Conditional Approval HORACE FULTZ
HVAC-Final 3/4/2022 Approved HORACE FULTZ
PLUMBING-Final 3/4/2022 Approved HORACE FULTZ
SGSOV-Seismic Gas S/O Valve 3/4/2022 SGSOV Approved HORACE FULTZ
Final 9/8/2022 OK to Issue CofO STUART CHAPMAN