2211 S MARIAN PL 90291
Certificate Information: 2211 S MARIAN PL 90291
- Application / Permit
- 20010-10000-01791
- Plan Check / Job No.
- B20LA09322
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached single-story ADU.
- Permit Issued
- Issued on 12/6/2021
- Issuing Office
- Current Status
- CofO Issued on 7/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Plan Check Approved | 11/23/2021 | RODOLFO ARIAS |
| Issued | 12/6/2021 | APPLICANT |
| CofO in Progress | 7/30/2024 | HERBERT GIRON |
| Permit Finaled | 7/30/2024 | DANIEL ORRANTE |
| CofO Issued | 7/30/2024 | DANIEL ORRANTE |
| Permit Finaled | 7/30/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/22/2021 | ANTHONY MAINEZ |
| Specific Plan | Cleared | 7/14/2021 | IRA BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2021 | CATHERINE ADROVER |
| Permit | Cleared | 7/27/2021 | CATHERINE ADROVER |
| Sewer availability | Cleared | 7/29/2021 | ANTHONY MAINEZ |
| ZA Case | Cleared | 8/5/2021 | TERRI OSBORNE |
| ZA Case | Cleared | 8/5/2021 | TERRI OSBORNE |
| Coastal Zone | Cleared | 8/25/2021 | ERIC CLAROS |
| ZA Case | Cleared | 8/25/2021 | ERIC CLAROS |
| Specific Plan | Cleared | 8/26/2021 | VALERIA CEJA |
| Work Adjacent to Public Way | Cleared | 9/3/2021 | SAUL GARCIA |
| Hydrant and Access approval | Cleared | 9/13/2021 | MATTHEW CRAIG |
| Miscellaneous | Cleared | 9/23/2021 | TERRI OSBORNE |
| Low Impact Development | Cleared | 10/22/2021 | ANDRES COVARRUBIAS |
| Green Code | Cleared | 10/28/2021 | RODOLFO ARIAS |
| Roof/Waste drainage to street | Cleared | 11/4/2021 | ANTHONY MAINEZ |
Contact Information
| Architect | Daly,, Kevin Michael; Lic. No.: C19005 | 3617 W EXPOSITION BLVD LOS ANGELES, CA 90016 |
| Contractor | Perea Construction Services Inc; Lic. No.: 979151-B | 19197 GOLDEN VALLEY RD #548 SANTA CLARITA, CA 91387 |
| Engineer | Adams,, Jelisa Thomas; Lic. No.: GE3092 | 26632 EL TOBOSO MISSION VIEJO, CA 92691 |
| Engineer | Obando,, Gaspar Eduardo; Lic. No.: C71382 | 1453 14TH ST STE A SANTA MONICA, CA 90404 |
| Engineer | Varela, Olivas, Benjamin; Lic. No.: S5714 | 6007 WASHINGTON BLVD CULVER CITY, CA 90232 |
| Geologist | Kirkgard,, Susan Franzen; Lic. No.: EG1754 | 1481 STONEBROOK STREET AZUSA, CA 91702 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/30/2022 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 9/6/2022 | Partial Approval | DAVID FEILER |
| Sewer | 9/12/2022 | Approved | DAVID FEILER |
| Underground Mechanical | 9/12/2022 | Partial Approval | DAVID FEILER |
| Footing/Foundation/Slab | 9/14/2022 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 9/26/2022 | Approved | DAVID FEILER |
| Pre-Inspection | 11/28/2022 | Partial Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 12/9/2022 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2022 | Partial Approval | EVAN COOPER |
| Green Building Rough | 12/9/2022 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 12/9/2022 | Not Ready for Inspection | EVAN COOPER |
| Verify Sprinkler Sign Off | 12/9/2022 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 12/22/2022 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 12/22/2022 | Corrections Issued | EVAN COOPER |
| HVAC-Rough | 1/19/2023 | Approved | EVAN COOPER |
| Underground Mechanical | 2/15/2023 | Partial Approval | EVAN COOPER |
| Interior/Exterior Lathing | 4/10/2023 | Not Ready for Inspection | HERBERT GIRON |
| Wood Frame | 4/10/2023 | Not Ready for Inspection | HERBERT GIRON |
| Interior/Exterior Lathing | 4/24/2023 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 6/6/2023 | Approved | EVAN COOPER |
| Green Building Rough | 6/6/2023 | Approved | EVAN COOPER |
| Insulation | 6/6/2023 | Approved | EVAN COOPER |
| Drywall Nailing | 6/15/2023 | Approved | JESUS RODRIGUEZ |
| Final | 6/15/2023 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Rough | 6/15/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 7/27/2023 | Approved | EVAN COOPER |
| Shower Pan | 7/27/2023 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 8/2/2023 | Approved | DAVID FEILER |
| Service/Power Release | 8/9/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 9/26/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 9/26/2023 | Corrections Issued | HERBERT GIRON |
| Final | 10/4/2023 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 10/4/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 10/4/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 10/4/2023 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 10/4/2023 | SGSOV Not Ready | HERBERT GIRON |
| Smoke Detectors | 10/4/2023 | Corrections Issued | HERBERT GIRON |
| Pre-Inspection | 11/9/2023 | No Access for Inspection | HERBERT GIRON |
| Pre-Inspection | 11/15/2023 | Partial Inspection | HERBERT GIRON |
| Final | 11/30/2023 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 11/30/2023 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 11/30/2023 | SGSOV Not Required | HERBERT GIRON |
| Smoke Detectors | 11/30/2023 | Not Ready for Inspection | HERBERT GIRON |
| Final | 12/19/2023 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Final | 2/7/2024 | Approved | HERBERT GIRON |
| Final | 2/7/2024 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 2/7/2024 | Approved | HERBERT GIRON |
| HVAC-Final | 2/7/2024 | Approved | HERBERT GIRON |
| Smoke Detectors | 2/7/2024 | Not Ready for Inspection | HERBERT GIRON |
| Final | 3/4/2024 | Corrections Issued | HERBERT GIRON |
| Smoke Detectors | 3/4/2024 | Approved | HERBERT GIRON |
| Final | 7/29/2024 | OK to Issue CofO | HERBERT GIRON |