516-518 W 51ST ST 90037

Certificate Information: 516-518 W 51ST ST 90037

Application / Permit
20010-10000-01776
Plan Check / Job No.
B20LA09306
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2-STORY DUPLEX WITH ATTACHED 2-CAR GARAGE
Permit Issued
Issued on 1/13/2021
Issuing Office
Current Status
CofO Issued on 9/2/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/23/2020 APPLICANT
Assigned to Plan Check Engineer 6/15/2020 CARLOS MONTES
Corrections Issued 6/17/2020 CARLOS MONTES
Quality Review Completed 7/3/2020 PRANITA SHAH
Building Plans Picked Up 7/9/2020 APPLICANT
Applicant returned to address corrections 8/28/2020 CARLOS MONTES
Plan Check Approved 11/2/2020 CARLOS MONTES
Issued 1/13/2021 APPLICANT
CofO in Progress 8/16/2021 JOAQUIN GREENOUGH
CofO Issued 9/2/2021 DEROLD HAUFF
Permit Finaled 9/2/2021 DEROLD HAUFF

Permit Application Clearance Information

Frnt yard landscape/Water mgmt Cleared 7/20/2020 TERRI OSBORNE
Low Impact Development Cleared 8/14/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 8/19/2020 RENZ SORIANO
Sewer availability Cleared 8/28/2020 ELAINE LEI
Hydrant and Access approval Cleared 9/4/2020 KURT CORRAL
Eng Process Fee Ord 176,300 Cleared 9/11/2020 ELAINE LEI
Highway dedication Cleared 9/16/2020 CELINA MORENO

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/19/2021 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 3/1/2021 Partial Approval ROBERT MCDOWELL
Underground Mechanical 3/1/2021 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 3/2/2021 Partial Approval DAVID FEILER
Insulation 3/2/2021 Partial Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 3/11/2021 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/23/2021 Approved ROBERT MCDOWELL
BUILDING-Rough-Frame 3/26/2021 Approved ROBERT MCDOWELL
Deputy Wood Construction 3/26/2021 Conditional Approval SABAS ALONSO
Green Building Rough 3/26/2021 Approved ROBERT MCDOWELL
MERV13>=Rough 3/26/2021 Approved ROBERT MCDOWELL
Rough-Elec/Plmb/HVAC 3/26/2021 Approved ROBERT MCDOWELL
Verify Sprinkler Sign Off 3/26/2021 Approved ROBERT MCDOWELL
Insulation 3/30/2021 Approved FREDDIE RIVERA
Drywall Nailing 4/8/2021 Approved SABAS ALONSO
Interior/Exterior Lathing 4/8/2021 Approved SABAS ALONSO
ELECTRICAL-Final 8/4/2021 Approved JOAQUIN GREENOUGH
Final 8/4/2021 Corrections Issued JOAQUIN GREENOUGH
Green Building Final 8/4/2021 Approved JOAQUIN GREENOUGH
HVAC-Final 8/4/2021 Approved JOAQUIN GREENOUGH
MERV13>=Final 8/4/2021 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Final 8/4/2021 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 8/4/2021 SGSOV Approved JOAQUIN GREENOUGH
Service/Power Release 8/4/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Smoke Detectors 8/4/2021 Approved JOAQUIN GREENOUGH
Final 8/13/2021 OK to Issue CofO JOAQUIN GREENOUGH
MERV13>=Final 8/13/2021 Approved JOAQUIN GREENOUGH
Service/Power Release 8/13/2021 Approved JOAQUIN GREENOUGH