2017-2017 1/2 E IMPERIAL HWY 90059

Certificate Information: 2017-2017 1/2 E IMPERIAL HWY 90059

Application / Permit
20010-10000-01753
Plan Check / Job No.
B20LA09200
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION OF TWO NEW ADUS WITH LAUNDRY TO BE DONE PER TYPE WPFF SHEET.
Permit Issued
Issued on 2/4/2021
Issuing Office
Current Status
CofO Issued on 8/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/8/2020 APPLICANT
Assigned to Plan Check Engineer 6/26/2020 DANIEL YIP
Corrections Issued 6/26/2020 DANIEL YIP
Quality Review Completed 6/30/2020 QUAN NGHIEM
Applicant returned to address corrections 11/6/2020 DANIEL YIP
Plan Check Approved 2/4/2021 DANIEL YIP
Issued 2/4/2021 APPLICANT
Building Plans Picked Up 2/5/2021 APPLICANT
CofO in Progress 5/13/2022 ALIZAH MAYAGOITIA
Permit Finaled 8/20/2022 DEROLD HAUFF
CofO Issued 8/20/2022 DEROLD HAUFF
Permit Finaled 8/20/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/23/2020 THOMAS LANG
Sewer availability Cleared 7/24/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 7/31/2020 THOMAS LANG
Community Plan Implem. Overlay Cleared 8/24/2020 HELEN JADALI
Low Impact Development Cleared 10/22/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 10/30/2020 CECILIO NAVARRO
Green Code Cleared 11/6/2020 DANIEL YIP

Contact Information

Contractor Jerahian Araz; Lic. No.: 1045340-B 250 N COLLEGE PARK DR F36      UPLAND, CA 91786

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/31/2021 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 3/31/2021 Conditional Approval EUGENE CASSIDY
Footing/Foundation/Slab 4/12/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 5/4/2021 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 7/19/2021 Partial Approval EUGENE CASSIDY
Green Building Rough 7/19/2021 Approved EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 7/19/2021 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 7/19/2021 Approved EUGENE CASSIDY
Insulation 8/3/2021 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 9/13/2021 Approved EUGENE CASSIDY
Insulation 9/13/2021 Approved EUGENE CASSIDY
Drywall Nailing 9/28/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 9/28/2021 Partial Approval EUGENE CASSIDY
Shower Pan 9/28/2021 Not Ready for Inspection EUGENE CASSIDY
Interior/Exterior Lathing 10/5/2021 Approved EUGENE CASSIDY
Shower Pan 10/5/2021 Approved EUGENE CASSIDY
ELECTRICAL-Final 3/4/2022 Corrections Issued JOHN KLARIN
Final 3/4/2022 Corrections Issued JOHN KLARIN
Green Building Final 3/4/2022 Corrections Issued JOHN KLARIN
HVAC-Final 3/4/2022 Corrections Issued JOHN KLARIN
PLUMBING-Final 3/4/2022 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 3/4/2022 SGSOV Approved JOHN KLARIN
Service/Power Release 3/4/2022 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 3/4/2022 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Final 5/12/2022 Approved ALIZAH MAYAGOITIA
Final 5/12/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Final 5/12/2022 Approved ALIZAH MAYAGOITIA
HVAC-Final 5/12/2022 Approved ALIZAH MAYAGOITIA
Service/Power Release 5/12/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 5/12/2022 Approved ALIZAH MAYAGOITIA
Final 5/13/2022 OK to Issue CofO ALIZAH MAYAGOITIA
Service/Power Release 5/13/2022 Approved ALIZAH MAYAGOITIA
Service/Power Release 5/16/2022 Approved ALIZAH MAYAGOITIA