2220-2220 1/2 S CARMONA AVE 90016
Certificate Information: 2220-2220 1/2 S CARMONA AVE 90016
- Application / Permit
- 20010-10000-01751
- Plan Check / Job No.
- B20LA09170
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- 3-STORY DUPLEX WITH ATTACHED GARAGE ( REAR BUIDLING) )2 OF 2
- Permit Issued
- Issued on 6/1/2021
- Issuing Office
- Current Status
- CofO Issued on 11/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/18/2020 | ARSALAN SHABESTARI |
| Corrections Issued | 7/2/2020 | ARSALAN SHABESTARI |
| Quality Review Completed | 7/20/2020 | HERNAN ARREOLA |
| Green Plans Picked Up | 12/15/2020 | APPLICANT |
| Applicant returned to address corrections | 5/4/2021 | ARSALAN SHABESTARI |
| Plan Check Approved | 5/11/2021 | ARSALAN SHABESTARI |
| Issued | 6/1/2021 | APPLICANT |
| Building Plans Picked Up | 6/7/2021 | APPLICANT |
| CofO in Progress | 10/27/2022 | JOSE AVILA |
| Permit Finaled | 11/5/2022 | DEROLD HAUFF |
| CofO Issued | 11/5/2022 | DEROLD HAUFF |
| Permit Finaled | 11/5/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/25/2020 | ELENA LOPEZ |
| Highway dedication | Cleared | 8/25/2020 | ELENA LOPEZ |
| Permit | Cleared | 8/25/2020 | ELENA LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2020 | ELENA LOPEZ |
| Sewer availability | Cleared | 8/31/2020 | ELENA LOPEZ |
| Hydrant and Access approval | Cleared | 10/23/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 11/6/2020 | ANDRES COVARRUBIAS |
| Green Code | Cleared | 12/4/2020 | ARSALAN SHABESTARI |
| Green Code | Cleared | 12/4/2020 | KHEDER ALRAZAA |
| Roof/Waste drainage to street | Cleared | 2/2/2021 | ROSA SILVA |
Contact Information
| Contractor | On Point Builders Inc; Lic. No.: 928105-B | 2371 GRAND AVE #90902 LONG BEACH, CA 90809 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/7/2021 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 7/7/2021 | Partial Approval | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 7/16/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 7/16/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Special/Order Compliance | 7/16/2021 | Approved | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2021 | Not Ready for Inspection | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2021 | Partial Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2021 | Approved | JOSE AVILA |
| PLUMBING-Rough | 11/8/2021 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 11/16/2021 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 11/16/2021 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 11/18/2021 | Conditional Approval | JOSE AVILA |
| ELECTRICAL-Rough | 11/18/2021 | Partial Approval | JOSE AVILA |
| Green Building Rough | 11/18/2021 | Approved | JOSE AVILA |
| MERV13>=Rough | 11/18/2021 | Not Ready for Inspection | JOSE AVILA |
| Verify Sprinkler Sign Off | 11/18/2021 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Rough | 11/24/2021 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 11/24/2021 | Approved | JOSE AVILA |
| Insulation | 12/8/2021 | Corrections Issued | JOSE AVILA |
| Interior/Exterior Lathing | 12/8/2021 | Not Ready for Inspection | JOSE AVILA |
| Insulation | 12/15/2021 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 12/15/2021 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 12/17/2021 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 12/17/2021 | Approved | JOSE AVILA |
| MERV13>=Rough | 12/17/2021 | Approved | JOSE AVILA |
| Verify Sprinkler Sign Off | 12/17/2021 | Approved | JOSE AVILA |
| Drywall Nailing | 12/22/2021 | Corrections Issued | JOSE AVILA |
| Drywall Nailing | 12/27/2021 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 12/27/2021 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 6/17/2022 | Corrections Issued | JOSE AVILA |
| Final | 6/17/2022 | Corrections Issued | JOSE AVILA |
| Green Building Final | 6/17/2022 | Corrections Issued | JOSE AVILA |
| HVAC-Final | 6/17/2022 | Corrections Issued | JOSE AVILA |
| MERV13>=Final | 6/17/2022 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 6/17/2022 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 6/17/2022 | SGSOV Not Ready | JOSE AVILA |
| Service/Power Release | 6/17/2022 | Approved | JOSE AVILA |
| Smoke Detectors | 6/17/2022 | Approved | JOSE AVILA |
| Service/Power Release | 7/7/2022 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 9/12/2022 | Approved | JOSE AVILA |
| Final | 9/12/2022 | Corrections Issued | JOSE AVILA |
| Green Building Final | 9/12/2022 | Approved | JOSE AVILA |
| HVAC-Final | 9/12/2022 | Approved | JOSE AVILA |
| MERV13>=Final | 9/12/2022 | Approved | JOSE AVILA |
| PLUMBING-Final | 9/12/2022 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 9/12/2022 | SGSOV Approved | JOSE AVILA |
| Final | 10/27/2022 | OK to Issue CofO | JOSE AVILA |