2220-2220 1/2 S CARMONA AVE 90016

Certificate Information: 2220-2220 1/2 S CARMONA AVE 90016

Application / Permit
20010-10000-01751
Plan Check / Job No.
B20LA09170
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
3-STORY DUPLEX WITH ATTACHED GARAGE ( REAR BUIDLING) )2 OF 2
Permit Issued
Issued on 6/1/2021
Issuing Office
Current Status
CofO Issued on 11/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/28/2020 APPLICANT
Assigned to Plan Check Engineer 6/18/2020 ARSALAN SHABESTARI
Corrections Issued 7/2/2020 ARSALAN SHABESTARI
Quality Review Completed 7/20/2020 HERNAN ARREOLA
Green Plans Picked Up 12/15/2020 APPLICANT
Applicant returned to address corrections 5/4/2021 ARSALAN SHABESTARI
Plan Check Approved 5/11/2021 ARSALAN SHABESTARI
Issued 6/1/2021 APPLICANT
Building Plans Picked Up 6/7/2021 APPLICANT
CofO in Progress 10/27/2022 JOSE AVILA
Permit Finaled 11/5/2022 DEROLD HAUFF
CofO Issued 11/5/2022 DEROLD HAUFF
Permit Finaled 11/5/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/25/2020 ELENA LOPEZ
Highway dedication Cleared 8/25/2020 ELENA LOPEZ
Permit Cleared 8/25/2020 ELENA LOPEZ
Eng Process Fee Ord 176,300 Cleared 8/31/2020 ELENA LOPEZ
Sewer availability Cleared 8/31/2020 ELENA LOPEZ
Hydrant and Access approval Cleared 10/23/2020 MATTHEW CRAIG
Low Impact Development Cleared 11/6/2020 ANDRES COVARRUBIAS
Green Code Cleared 12/4/2020 ARSALAN SHABESTARI
Green Code Cleared 12/4/2020 KHEDER ALRAZAA
Roof/Waste drainage to street Cleared 2/2/2021 ROSA SILVA

Contact Information

Contractor On Point Builders Inc; Lic. No.: 928105-B 2371 GRAND AVE #90902      LONG BEACH, CA 90809

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/7/2021 Approved STUART CHAPMAN
PLUMBING-Rough 7/7/2021 Partial Approval STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 7/16/2021 Approved CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 7/16/2021 Approved CHRISTOPHER DELLEFIELD
Special/Order Compliance 7/16/2021 Approved RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 8/6/2021 Not Ready for Inspection JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 8/10/2021 Partial Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 8/20/2021 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 11/8/2021 Approved JOSE AVILA
PLUMBING-Rough 11/8/2021 Corrections Issued JOSE AVILA
HVAC-Rough 11/16/2021 Corrections Issued JOSE AVILA
PLUMBING-Rough 11/16/2021 Approved JOSE AVILA
BUILDING-Rough-Frame 11/18/2021 Conditional Approval JOSE AVILA
ELECTRICAL-Rough 11/18/2021 Partial Approval JOSE AVILA
Green Building Rough 11/18/2021 Approved JOSE AVILA
MERV13>=Rough 11/18/2021 Not Ready for Inspection JOSE AVILA
Verify Sprinkler Sign Off 11/18/2021 Partial Approval JOSE AVILA
ELECTRICAL-Rough 11/24/2021 Corrections Issued JOSE AVILA
HVAC-Rough 11/24/2021 Approved JOSE AVILA
Insulation 12/8/2021 Corrections Issued JOSE AVILA
Interior/Exterior Lathing 12/8/2021 Not Ready for Inspection JOSE AVILA
Insulation 12/15/2021 Approved JOSE AVILA
Interior/Exterior Lathing 12/15/2021 Approved JOSE AVILA
BUILDING-Rough-Frame 12/17/2021 Approved JOSE AVILA
ELECTRICAL-Rough 12/17/2021 Approved JOSE AVILA
MERV13>=Rough 12/17/2021 Approved JOSE AVILA
Verify Sprinkler Sign Off 12/17/2021 Approved JOSE AVILA
Drywall Nailing 12/22/2021 Corrections Issued JOSE AVILA
Drywall Nailing 12/27/2021 Approved JOSE AVILA
Interior/Exterior Lathing 12/27/2021 Approved JOSE AVILA
ELECTRICAL-Final 6/17/2022 Corrections Issued JOSE AVILA
Final 6/17/2022 Corrections Issued JOSE AVILA
Green Building Final 6/17/2022 Corrections Issued JOSE AVILA
HVAC-Final 6/17/2022 Corrections Issued JOSE AVILA
MERV13>=Final 6/17/2022 Corrections Issued JOSE AVILA
PLUMBING-Final 6/17/2022 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 6/17/2022 SGSOV Not Ready JOSE AVILA
Service/Power Release 6/17/2022 Approved JOSE AVILA
Smoke Detectors 6/17/2022 Approved JOSE AVILA
Service/Power Release 7/7/2022 Approved JOSE AVILA
ELECTRICAL-Final 9/12/2022 Approved JOSE AVILA
Final 9/12/2022 Corrections Issued JOSE AVILA
Green Building Final 9/12/2022 Approved JOSE AVILA
HVAC-Final 9/12/2022 Approved JOSE AVILA
MERV13>=Final 9/12/2022 Approved JOSE AVILA
PLUMBING-Final 9/12/2022 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 9/12/2022 SGSOV Approved JOSE AVILA
Final 10/27/2022 OK to Issue CofO JOSE AVILA