229 E 56TH ST 90011

Certificate Information: 229 E 56TH ST 90011

Application / Permit
20010-10000-01732
Plan Check / Job No.
B20LA09062
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) DETACHED ONE-STORY ADU . PER STATE LAW GCS 65852.2(e)(1)(B)
Permit Issued
Issued on 9/20/2021
Issuing Office
Current Status
CofO Issued on 2/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/26/2020 APPLICANT
Assigned to Plan Check Engineer 6/18/2020 CARLOS MONTES
Corrections Issued 6/19/2020 CARLOS MONTES
Quality Review Completed 7/3/2020 PRANITA SHAH
Building Plans Picked Up 7/8/2020 APPLICANT
Applicant returned to address corrections 8/28/2020 CARLOS MONTES
Plan Check Approved 4/1/2021 CARLOS MONTES
Issued 9/20/2021 APPLICANT
CofO in Progress 2/16/2023 BRENDAN MORELLI
Permit Finaled 2/21/2023 DEROLD HAUFF
CofO Issued 2/21/2023 DEROLD HAUFF
Permit Finaled 2/21/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/29/2020 CECILIO NAVARRO
Sewer availability Cleared 9/29/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 10/22/2020 CECILIO NAVARRO
Hydrant and Access approval Cleared 11/3/2020 MATTHEW CRAIG
Low Impact Development Cleared 3/9/2021 MITESH PATEL
Community Plan Implem. Overlay Cleared 3/16/2021 HELEN JADALI
Roof/Waste drainage to street Cleared 3/24/2021 THAN WIN

Contact Information

Contractor Colossus Energy; Lic. No.: 962278-B 1701 S GROVE AVE STE E      ONTARIO, CA 91761
Engineer Wu,, Harold Ping-Hung; Lic. No.: C35693 1168 SAN GABRIEL BLVD NO N      ROSEMEAD, CA 91770

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/20/2021 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 10/28/2021 Approved JOAQUIN GREENOUGH
Underground Mechanical 10/28/2021 Partial Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 11/30/2021 Corrections Issued JOAQUIN GREENOUGH
Green Building Rough 11/30/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 11/30/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 12/3/2021 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 12/15/2021 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Rough 12/15/2021 Corrections Issued JOAQUIN GREENOUGH
Green Building Rough 12/15/2021 Corrections Issued JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 12/15/2021 Approved JOAQUIN GREENOUGH
ELECTRICAL-Rough 2/9/2022 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 2/23/2022 Approved STUART CHAPMAN
Green Building Rough 2/23/2022 Approved STUART CHAPMAN
HVAC-Rough 2/23/2022 Approved STUART CHAPMAN
Insulation 2/23/2022 Corrections Issued STUART CHAPMAN
PLUMBING-Rough 2/23/2022 Approved STUART CHAPMAN
Rough-Elec/Plmb/HVAC 2/23/2022 Approved STUART CHAPMAN
Underground Mechanical 2/23/2022 Partial Approval STUART CHAPMAN
Insulation 3/1/2022 Conditional Approval JOAQUIN GREENOUGH
Drywall Nailing 3/30/2022 Conditional Approval JOAQUIN GREENOUGH
Shower Pan 3/30/2022 Corrections Issued JOAQUIN GREENOUGH
Drywall Nailing 6/3/2022 Approved JOAQUIN GREENOUGH
Final 6/3/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Green Building Final 6/3/2022 Not Ready for Inspection JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 6/3/2022 SGSOV Not Ready JOAQUIN GREENOUGH
Service/Power Release 6/3/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Shower Pan 6/3/2022 Approved JOAQUIN GREENOUGH
Smoke Detectors 6/3/2022 Corrections Issued JOAQUIN GREENOUGH
Final 7/12/2022 Corrections Issued JOAQUIN GREENOUGH
Green Building Final 7/12/2022 Not Ready for Inspection JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 7/12/2022 SGSOV Not Ready JOAQUIN GREENOUGH
Service/Power Release 7/12/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Smoke Detectors 7/12/2022 Approved JOAQUIN GREENOUGH
Pre-Inspection 7/28/2022 Not Ready for Inspection JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 8/8/2022 SGSOV Not Ready ENRIQUE MIRELES
Final 8/17/2022 Corrections Issued JOAQUIN GREENOUGH
Green Building Final 8/17/2022 Not Ready for Inspection JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 8/17/2022 SGSOV Not Ready JOAQUIN GREENOUGH
Service/Power Release 8/17/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Final 8/29/2022 Corrections Issued ENRIQUE MIRELES
Green Building Final 8/29/2022 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 8/29/2022 SGSOV Approved ENRIQUE MIRELES
Final 9/14/2022 Corrections Issued SHAVONNE ESPINOZA
Service/Power Release 9/14/2022 Not Ready for Inspection SHAVONNE ESPINOZA
ELECTRICAL-Final 9/19/2022 Corrections Issued SHAVONNE ESPINOZA
PLUMBING-Final 9/19/2022 Corrections Issued SHAVONNE ESPINOZA
ELECTRICAL-Final 9/23/2022 Partial Inspection SHAVONNE ESPINOZA
HVAC-Final 9/23/2022 Corrections Issued SHAVONNE ESPINOZA
PLUMBING-Final 9/23/2022 Approved SHAVONNE ESPINOZA
ELECTRICAL-Final 10/3/2022 Approved SHAVONNE ESPINOZA
HVAC-Final 10/3/2022 Approved SHAVONNE ESPINOZA
PLUMBING-Final 10/3/2022 Approved SHAVONNE ESPINOZA
Final 10/7/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Service/Power Release 10/7/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Pre-Inspection 10/31/2022 Corrections Issued ANTHONY EGSON
Final 1/3/2023 Partial Inspection BRENDAN MORELLI
Service/Power Release 1/3/2023 Corrections Issued BRENDAN MORELLI
Final 1/4/2023 Conditional Approval BRENDAN MORELLI
Service/Power Release 1/4/2023 Approved BRENDAN MORELLI
Final 1/26/2023 Corrections Issued BRENDAN MORELLI
Final 1/27/2023 OK to Issue CofO BRENDAN MORELLI