1731 W 43RD ST 90062
Certificate Information: 1731 W 43RD ST 90062
- Application / Permit
- 20010-10000-01714
- Plan Check / Job No.
- B20LA08985
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) ACCESSORY DWELLING UNIT AT THE REAR OF THE LOT PER GCS 65852.2 and 65852.22
- Permit Issued
- Issued on 11/10/2020
- Issuing Office
- Current Status
- Issued on 11/10/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/28/2020 | DANIEL YIP |
| Corrections Issued | 6/1/2020 | DANIEL YIP |
| Quality Review Completed | 6/30/2020 | QUAN NGHIEM |
| Building Plans Picked Up | 7/8/2020 | APPLICANT |
| Green Plans Picked Up | 9/28/2020 | APPLICANT |
| Plan Check Approved | 11/4/2020 | DANIEL YIP |
| Issued | 11/10/2020 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/5/2020 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 8/5/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 8/18/2020 | CECILIO NAVARRO |
| Green Code | Cleared | 9/25/2020 | DANIEL YIP |
| Hold | Cleared | 12/24/2020 | JEREMY CORONEL |
Contact Information
| Contractor | C G S Home Improvement Inc; Lic. No.: 1037939-B | 7189 N FIGUEROA ST LOS ANGELES, CA 90042 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/7/2021 | Conditional Approval | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 3/31/2021 | Conditional Approval | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 3/31/2021 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2021 | Approved | ROBERT MCDOWELL |
| Gas Test | 3/31/2021 | Partial Approval | ROBERT MCDOWELL |
| Green Building Rough | 3/31/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| PLUMBING-Rough | 3/31/2021 | Approved | ROBERT MCDOWELL |
| Rough-Elec/Plmb/HVAC | 3/31/2021 | Approved | ROBERT MCDOWELL |
| Sewer | 3/31/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 3/31/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| Green Building Rough | 4/19/2021 | Approved | ROBERT MCDOWELL |
| Insulation | 4/19/2021 | Approved | ROBERT MCDOWELL |
| Interior/Exterior Lathing | 4/19/2021 | Approved | ROBERT MCDOWELL |
| Sewer | 4/19/2021 | Approved | ROBERT MCDOWELL |
| Drywall Nailing | 5/5/2021 | Approved | SABAS ALONSO |
| Shower Pan | 6/17/2021 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/7/2021 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 9/7/2021 | Approved | SABAS ALONSO |
| Final | 9/7/2021 | Conditional Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 9/7/2021 | Approved | SABAS ALONSO |
| Green Building Final | 9/7/2021 | Approved | SABAS ALONSO |
| HVAC-Final | 9/7/2021 | Approved | SABAS ALONSO |
| PLUMBING-Final | 9/7/2021 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 9/7/2021 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 9/7/2021 | Approved | SABAS ALONSO |
| Smoke Detectors | 9/7/2021 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 9/7/2021 | Approved | SABAS ALONSO |