2926 E FUTURE ST 90065

Certificate Information: 2926 E FUTURE ST 90065

Application / Permit
20010-10000-01683
Plan Check / Job No.
B20LA08882
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
A NEW 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED TWO-CARE GARAGE
Permit Issued
Issued on 7/18/2022
Issuing Office
Metro
Current Status
CofO Issued on 10/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/15/2020 APPLICANT
Assigned to Plan Check Engineer 6/4/2020 JESSE ARELLANO
Corrections Issued 6/24/2020 JESSE ARELLANO
Quality Review Completed 7/16/2020 ALLEN MANALANSAN
Applicant returned to address corrections 9/26/2020 JESSE ARELLANO
Applicant returned to address corrections 11/29/2020 JESSE ARELLANO
Plan Check Approved 1/13/2021 JESSE ARELLANO
Building Plans Picked Up 10/8/2021 APPLICANT
Issued 7/18/2022 APPLICANT
CofO in Progress 9/19/2024 ALIZAH MAYAGOITIA
CofO Issued 10/3/2024 RUBEN SALAS
Permit Finaled 10/3/2024 RUBEN SALAS

Permit Application Clearance Information

Hydrant and Access approval Cleared 9/24/2020 KURT CORRAL
Low Impact Development Cleared 9/24/2020 ROBIN YAMADA
Eng Process Fee Ord 176,300 Cleared 9/25/2020 WALLIE JONG
Roof/Waste drainage to street Cleared 9/25/2020 WALLIE JONG
Sewer availability Cleared 9/25/2020 WALLIE JONG
Grading Pre-Inspection Cleared 9/27/2020 JESSE ARELLANO
Green Code Cleared 9/27/2020 JESSE ARELLANO
Specific Plan Cleared 10/27/2020 RUBEN VASQUEZ
Specific Plan Cleared 10/27/2020 RUBEN VASQUEZ
ZI Cleared 10/27/2020 RUBEN VASQUEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Lau,, David Harkwong; Lic. No.: C34961 12467 W WASHINGTON BLVD      LOS ANGELES, CA 90066

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/25/2022 Corrections Issued HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 12/13/2022 Corrections Issued OSVALDO PARAMO
Pre-Inspection 12/13/2022 Not Ready for Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 1/6/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 1/11/2023 Corrections Issued OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 1/17/2023 Partial Inspection OSVALDO PARAMO
PLUMBING-Rough 1/17/2023 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 1/19/2023 Approved KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 2/3/2023 Corrections Issued OSVALDO PARAMO
Deputy Drilled-In Anchors 2/6/2023 Approved OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 2/6/2023 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 2/17/2023 Partial Approval OSVALDO PARAMO
Green Building Rough 2/17/2023 Not Ready for Inspection OSVALDO PARAMO
Underground Mechanical 2/17/2023 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 3/2/2023 Partial Approval JOSEPH MCGARRY
Deputy Steel/Welding 4/4/2023 Conditional Approval OSVALDO PARAMO
Deputy Wood Construction 6/20/2023 Conditional Approval OSVALDO PARAMO
BUILDING-Rough-Frame 6/22/2023 Corrections Issued OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 6/22/2023 Partial Approval OSVALDO PARAMO
Green Building Rough 6/22/2023 Not Ready for Inspection OSVALDO PARAMO
Verify Sprinkler Sign Off 6/22/2023 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 11/29/2023 Conditional Approval OSVALDO PARAMO
PLUMBING-Rough 12/11/2023 Corrections Issued OSVALDO PARAMO
HVAC-Rough 12/14/2023 Approved OSVALDO PARAMO
PLUMBING-Rough 12/14/2023 Approved OSVALDO PARAMO
ELECTRICAL-Rough 12/18/2023 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Rough 12/27/2023 Approved JEFFREY MEAD
BUILDING-Rough-Frame 1/17/2024 Corrections Issued OSVALDO PARAMO
Green Building Rough 1/17/2024 Approved OSVALDO PARAMO
Verify Sprinkler Sign Off 1/17/2024 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 1/22/2024 Approved OSVALDO PARAMO
Interior/Exterior Lathing 1/23/2024 Partial Approval OSVALDO PARAMO
Insulation 1/29/2024 Approved ALIZAH MAYAGOITIA
Drywall Nailing 2/22/2024 Approved OSVALDO PARAMO
Shower Pan 2/27/2024 Corrections Issued JOSH MEISTER
Shower Pan 3/4/2024 Approved OSVALDO PARAMO
Interior/Exterior Lathing 3/6/2024 Approved OSVALDO PARAMO
HVAC-Final 4/30/2024 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Final 5/29/2024 Corrections Issued ALIZAH MAYAGOITIA
HVAC-Final 5/29/2024 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Final 5/29/2024 Corrections Issued ALIZAH MAYAGOITIA
ELECTRICAL-Final 6/18/2024 Approved ALIZAH MAYAGOITIA
HVAC-Final 6/18/2024 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 6/18/2024 Approved ALIZAH MAYAGOITIA
Final 8/23/2024 Not Ready for Inspection OSVALDO PARAMO
Green Building Final 8/23/2024 Not Ready for Inspection OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 8/23/2024 SGSOV Not Ready OSVALDO PARAMO
Service/Power Release 8/23/2024 Not Ready for Inspection OSVALDO PARAMO
Smoke Detectors 8/23/2024 Not Ready for Inspection OSVALDO PARAMO
Final 9/10/2024 Corrections Issued OSVALDO PARAMO
Green Building Final 9/10/2024 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 9/10/2024 SGSOV Approved OSVALDO PARAMO
Service/Power Release 9/10/2024 Approved OSVALDO PARAMO
Smoke Detectors 9/10/2024 Approved OSVALDO PARAMO
Final 9/16/2024 Partial Approval ALIZAH MAYAGOITIA
Gas Test 9/16/2024 Approved ALIZAH MAYAGOITIA
Final 9/19/2024 OK to Issue CofO ALIZAH MAYAGOITIA