1863 S BARRY AVE 90025

Certificate Information: 1863 S BARRY AVE 90025

Application / Permit
20010-10000-01671
Plan Check / Job No.
B20LA08774
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 4-STORY S.F.D. W/ ATT. GARAGE AND ROOF DECK. SMALL LOT SUBDIVISION PURSUANT TO VTT-82467-SL LOT 7
Permit Issued
Issued on 8/29/2022
Issuing Office
Metro
Current Status
CofO Issued on 12/31/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/30/2020 APPLICANT
Assigned to Plan Check Engineer 8/20/2020 SAM CHANG
Corrections Issued 8/31/2020 SAM CHANG
Quality Review Completed 9/3/2020 TIEN JEN WANG
Applicant returned to address corrections 1/27/2021 SAM CHANG
Applicant returned to address corrections 2/10/2021 SAM CHANG
Applicant returned to address corrections 10/15/2021 SAM CHANG
Building Plans Picked Up 10/22/2021 APPLICANT
Applicant returned to address corrections 5/17/2022 SAM CHANG
Plan Check Approved 7/15/2022 SAM CHANG
Issued 8/29/2022 APPLICANT
CofO in Progress 12/29/2025 ANDREW NAVE
Permit Finaled 12/31/2025 RICHARD STEINBACH
CofO Issued 12/31/2025 RICHARD STEINBACH
Permit Finaled 12/31/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/12/2021 NIKTA MOUSAVI
Address approval Cleared 3/16/2021 NIKTA MOUSAVI
Highway dedication Cleared 5/26/2021 RAYMOND MUGAMBWA
Miscellaneous Cleared 5/26/2021 RAYMOND MUGAMBWA
Permit Cleared 7/9/2021 NIKTA MOUSAVI
Hydrant and Access approval Cleared 8/9/2021 MATTHEW CRAIG
Trees in Parkway Cleared 9/29/2021 ADRIAN SANCHEZ
Green Code Cleared 10/15/2021 SAM CHANG
CPC Cleared 2/18/2022 MAXFIELD VERMY
Frnt yard landscape/Water mgmt Cleared 2/18/2022 MAXFIELD VERMY
Opn space landscape/Water mgmt Cleared 2/18/2022 MAXFIELD VERMY
Tract Map conditions Cleared 2/18/2022 MAXFIELD VERMY
Specific Plan Cleared 2/22/2022 DYLAN SITTIG
Sewer availability Cleared 3/10/2022 NIKTA MOUSAVI
Specific Plan Cleared 4/5/2022 PEDRO AYALA
Low Impact Development Cleared 4/14/2022 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 4/25/2022 NIKTA MOUSAVI
Building over 36-ft Cleared 7/15/2022 CALOSHA APPROVED

Contact Information

Contractor H R Development Inc; Lic. No.: 991772-B 7700 DENSMORE AVE      VAN NUYS, CA 91406
Engineer Minas,, Caro Jolfaie; Lic. No.: GE601 4742 SAN FERNANDO RD      GLENDALE, CA 91204
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/16/2023 Partial Approval CLAYTON GRAHAM
PLUMBING-Rough 5/18/2023 Partial Approval CLAYTON GRAHAM
Underground Mechanical 5/25/2023 Partial Approval CLAYTON GRAHAM
Underground Mechanical 5/31/2023 Partial Approval CLAYTON GRAHAM
ELECTRICAL-Rough 6/6/2023 Corrections Issued MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 6/6/2023 Approved MICHAEL PELHAM
Footing/Foundation/Slab 6/6/2023 Approved MICHAEL PELHAM
PLUMBING-Rough 6/6/2023 Corrections Issued MICHAEL PELHAM
Sewer 6/6/2023 Approved MICHAEL PELHAM
Deputy Reinf. Concrete 6/7/2023 Conditional Approval CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 6/21/2023 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 7/11/2023 Partial Approval CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 7/24/2023 Partial Approval RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 8/4/2023 Partial Approval STEPHANIE SWANSON
Interior/Exterior Lathing 8/11/2023 Partial Approval CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 9/7/2023 Not Ready for Inspection CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 9/15/2023 Partial Approval BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 9/27/2023 Partial Approval ARAM AVEDISIAN
Interior/Exterior Lathing 10/2/2023 Partial Approval BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 10/17/2023 Partial Approval CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 11/28/2023 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 1/10/2024 Partial Approval TEMISTOCLES CAAL
HVAC-Rough 1/10/2024 Approved TEMISTOCLES CAAL
Special/Order Compliance 1/10/2024 Corrections Issued TEMISTOCLES CAAL
Gas Test 1/12/2024 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 1/12/2024 Partial Approval OGANES TARAKHCHYAN
Wood Frame 1/22/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Wood Frame 1/23/2024 Corrections Issued OGANES TARAKHCHYAN
HVAC-Rough 4/1/2024 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 4/3/2024 Corrections Issued ASHLEY THOMPSON
PLUMBING-Rough 4/3/2024 Approved ASHLEY THOMPSON
Shower Pan 4/5/2024 Not Ready for Inspection ASHLEY THOMPSON
Shower Pan 4/8/2024 Approved OGANES TARAKHCHYAN
Wood Frame 4/10/2024 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 4/15/2024 Approved OGANES TARAKHCHYAN
Green Building Rough 4/17/2024 Approved OGANES TARAKHCHYAN
Insulation 4/17/2024 Approved OGANES TARAKHCHYAN
Drywall Nailing 5/6/2024 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 5/6/2024 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 7/16/2024 Corrections Issued CARLOS MATAMOROS
Underground Mechanical 10/18/2024 Approved REGINA MENDEZ
Sewer 10/30/2024 Partial Approval REGINA MENDEZ
Underground Mechanical 11/1/2024 Approved KIRK SANDERS
Underground Mechanical 12/23/2024 Approved REGINA MENDEZ
ELECTRICAL-Final 2/10/2025 Corrections Issued KIRK SANDERS
PLUMBING-Final 2/10/2025 Corrections Issued KIRK SANDERS
Special/Order Compliance 2/10/2025 Corrections Issued KIRK SANDERS
Special/Order Compliance 2/11/2025 Corrections Issued MICHAEL PELHAM
ELECTRICAL-Final 2/13/2025 Corrections Issued CARLOS MATAMOROS
Gas Test 2/13/2025 Approved CARLOS MATAMOROS
PLUMBING-Final 2/13/2025 Approved CARLOS MATAMOROS
Special/Order Compliance 2/13/2025 Corrections Issued CARLOS MATAMOROS
PLUMBING-Final 2/26/2025 Approved JESUS RODRIGUEZ
HVAC-Final 3/5/2025 Corrections Issued KIRK SANDERS
Underground Mechanical 4/1/2025 Partial Approval BOBBY KEY
ELECTRICAL-Final 4/9/2025 Conditional Approval STEPHANIE SWANSON
HVAC-Final 4/23/2025 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 5/22/2025 Approved KIRK SANDERS
Final 5/22/2025 Corrections Issued KIRK SANDERS
Green Building Final 5/22/2025 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 5/22/2025 SGSOV Approved KIRK SANDERS
Service/Power Release 5/22/2025 Not Ready for Inspection KIRK SANDERS
Smoke Detectors 5/22/2025 Approved KIRK SANDERS
Verify Sprinkler Sign Off 5/22/2025 Approved KIRK SANDERS
Service/Power Release 6/18/2025 Approved MICHAEL PELHAM
Special/Order Compliance 8/20/2025 Corrections Issued MICHAEL PELHAM
Final 12/26/2025 Corrections Issued ANDREW NAVE
ELECTRICAL-Final 12/29/2025 Approved ANDREW NAVE
Final 12/29/2025 OK to Issue CofO ANDREW NAVE