1863 S BARRY AVE 90025
Certificate Information: 1863 S BARRY AVE 90025
- Application / Permit
- 20010-10000-01671
- Plan Check / Job No.
- B20LA08774
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 4-STORY S.F.D. W/ ATT. GARAGE AND ROOF DECK. SMALL LOT SUBDIVISION PURSUANT TO VTT-82467-SL LOT 7
- Permit Issued
- Issued on 8/29/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/31/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2020 | SAM CHANG |
| Corrections Issued | 8/31/2020 | SAM CHANG |
| Quality Review Completed | 9/3/2020 | TIEN JEN WANG |
| Applicant returned to address corrections | 1/27/2021 | SAM CHANG |
| Applicant returned to address corrections | 2/10/2021 | SAM CHANG |
| Applicant returned to address corrections | 10/15/2021 | SAM CHANG |
| Building Plans Picked Up | 10/22/2021 | APPLICANT |
| Applicant returned to address corrections | 5/17/2022 | SAM CHANG |
| Plan Check Approved | 7/15/2022 | SAM CHANG |
| Issued | 8/29/2022 | APPLICANT |
| CofO in Progress | 12/29/2025 | ANDREW NAVE |
| Permit Finaled | 12/31/2025 | RICHARD STEINBACH |
| CofO Issued | 12/31/2025 | RICHARD STEINBACH |
| Permit Finaled | 12/31/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/12/2021 | NIKTA MOUSAVI |
| Address approval | Cleared | 3/16/2021 | NIKTA MOUSAVI |
| Highway dedication | Cleared | 5/26/2021 | RAYMOND MUGAMBWA |
| Miscellaneous | Cleared | 5/26/2021 | RAYMOND MUGAMBWA |
| Permit | Cleared | 7/9/2021 | NIKTA MOUSAVI |
| Hydrant and Access approval | Cleared | 8/9/2021 | MATTHEW CRAIG |
| Trees in Parkway | Cleared | 9/29/2021 | ADRIAN SANCHEZ |
| Green Code | Cleared | 10/15/2021 | SAM CHANG |
| CPC | Cleared | 2/18/2022 | MAXFIELD VERMY |
| Frnt yard landscape/Water mgmt | Cleared | 2/18/2022 | MAXFIELD VERMY |
| Opn space landscape/Water mgmt | Cleared | 2/18/2022 | MAXFIELD VERMY |
| Tract Map conditions | Cleared | 2/18/2022 | MAXFIELD VERMY |
| Specific Plan | Cleared | 2/22/2022 | DYLAN SITTIG |
| Sewer availability | Cleared | 3/10/2022 | NIKTA MOUSAVI |
| Specific Plan | Cleared | 4/5/2022 | PEDRO AYALA |
| Low Impact Development | Cleared | 4/14/2022 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 4/25/2022 | NIKTA MOUSAVI |
| Building over 36-ft | Cleared | 7/15/2022 | CALOSHA APPROVED |
Contact Information
| Contractor | H R Development Inc; Lic. No.: 991772-B | 7700 DENSMORE AVE VAN NUYS, CA 91406 |
| Engineer | Minas,, Caro Jolfaie; Lic. No.: GE601 | 4742 SAN FERNANDO RD GLENDALE, CA 91204 |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/16/2023 | Partial Approval | CLAYTON GRAHAM |
| PLUMBING-Rough | 5/18/2023 | Partial Approval | CLAYTON GRAHAM |
| Underground Mechanical | 5/25/2023 | Partial Approval | CLAYTON GRAHAM |
| Underground Mechanical | 5/31/2023 | Partial Approval | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 6/6/2023 | Corrections Issued | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 6/6/2023 | Approved | MICHAEL PELHAM |
| Footing/Foundation/Slab | 6/6/2023 | Approved | MICHAEL PELHAM |
| PLUMBING-Rough | 6/6/2023 | Corrections Issued | MICHAEL PELHAM |
| Sewer | 6/6/2023 | Approved | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 6/7/2023 | Conditional Approval | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2023 | Partial Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2023 | Partial Approval | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2023 | Partial Approval | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2023 | Partial Approval | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 8/11/2023 | Partial Approval | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2023 | Partial Approval | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2023 | Partial Approval | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 10/2/2023 | Partial Approval | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2023 | Partial Approval | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 11/28/2023 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 1/10/2024 | Partial Approval | TEMISTOCLES CAAL |
| HVAC-Rough | 1/10/2024 | Approved | TEMISTOCLES CAAL |
| Special/Order Compliance | 1/10/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Gas Test | 1/12/2024 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 1/12/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Wood Frame | 1/22/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Wood Frame | 1/23/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| HVAC-Rough | 4/1/2024 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 4/3/2024 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Rough | 4/3/2024 | Approved | ASHLEY THOMPSON |
| Shower Pan | 4/5/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| Shower Pan | 4/8/2024 | Approved | OGANES TARAKHCHYAN |
| Wood Frame | 4/10/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 4/15/2024 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 4/17/2024 | Approved | OGANES TARAKHCHYAN |
| Insulation | 4/17/2024 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 5/6/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 5/6/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2024 | Corrections Issued | CARLOS MATAMOROS |
| Underground Mechanical | 10/18/2024 | Approved | REGINA MENDEZ |
| Sewer | 10/30/2024 | Partial Approval | REGINA MENDEZ |
| Underground Mechanical | 11/1/2024 | Approved | KIRK SANDERS |
| Underground Mechanical | 12/23/2024 | Approved | REGINA MENDEZ |
| ELECTRICAL-Final | 2/10/2025 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 2/10/2025 | Corrections Issued | KIRK SANDERS |
| Special/Order Compliance | 2/10/2025 | Corrections Issued | KIRK SANDERS |
| Special/Order Compliance | 2/11/2025 | Corrections Issued | MICHAEL PELHAM |
| ELECTRICAL-Final | 2/13/2025 | Corrections Issued | CARLOS MATAMOROS |
| Gas Test | 2/13/2025 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 2/13/2025 | Approved | CARLOS MATAMOROS |
| Special/Order Compliance | 2/13/2025 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Final | 2/26/2025 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 3/5/2025 | Corrections Issued | KIRK SANDERS |
| Underground Mechanical | 4/1/2025 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Final | 4/9/2025 | Conditional Approval | STEPHANIE SWANSON |
| HVAC-Final | 4/23/2025 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 5/22/2025 | Approved | KIRK SANDERS |
| Final | 5/22/2025 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 5/22/2025 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 5/22/2025 | SGSOV Approved | KIRK SANDERS |
| Service/Power Release | 5/22/2025 | Not Ready for Inspection | KIRK SANDERS |
| Smoke Detectors | 5/22/2025 | Approved | KIRK SANDERS |
| Verify Sprinkler Sign Off | 5/22/2025 | Approved | KIRK SANDERS |
| Service/Power Release | 6/18/2025 | Approved | MICHAEL PELHAM |
| Special/Order Compliance | 8/20/2025 | Corrections Issued | MICHAEL PELHAM |
| Final | 12/26/2025 | Corrections Issued | ANDREW NAVE |
| ELECTRICAL-Final | 12/29/2025 | Approved | ANDREW NAVE |
| Final | 12/29/2025 | OK to Issue CofO | ANDREW NAVE |