1859 S BARRY AVE 90025

Certificate Information: 1859 S BARRY AVE 90025

Application / Permit
20010-10000-01667
Plan Check / Job No.
B20LA08774
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 4-STORY S.F.D. W/ ATT. GARAGE AND ROOF DECK. SMALL LOT SUBDIVISION PURSUANT TO VTT-82467-SL lot 3
Permit Issued
Issued on 8/29/2022
Issuing Office
Metro
Current Status
CofO Issued on 12/31/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/30/2020 APPLICANT
Assigned to Plan Check Engineer 8/20/2020 SAM CHANG
Corrections Issued 8/31/2020 SAM CHANG
Quality Review Completed 9/3/2020 TIEN JEN WANG
Applicant returned to address corrections 1/27/2021 SAM CHANG
Applicant returned to address corrections 2/10/2021 SAM CHANG
Applicant returned to address corrections 10/15/2021 SAM CHANG
Building Plans Picked Up 10/22/2021 APPLICANT
Applicant returned to address corrections 5/17/2022 SAM CHANG
Plan Check Approved 7/15/2022 SAM CHANG
Issued 8/29/2022 APPLICANT
CofO in Progress 12/29/2025 ANDREW NAVE
Permit Finaled 12/31/2025 RICHARD STEINBACH
CofO Issued 12/31/2025 RICHARD STEINBACH
Permit Finaled 12/31/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/12/2021 NIKTA MOUSAVI
Address approval Cleared 3/16/2021 NIKTA MOUSAVI
Highway dedication Cleared 5/26/2021 RAYMOND MUGAMBWA
Miscellaneous Cleared 5/26/2021 RAYMOND MUGAMBWA
Permit Cleared 7/9/2021 NIKTA MOUSAVI
Hydrant and Access approval Cleared 8/9/2021 MATTHEW CRAIG
Trees in Parkway Cleared 9/29/2021 ADRIAN SANCHEZ
Green Code Cleared 10/15/2021 SAM CHANG
CPC Cleared 2/18/2022 MAXFIELD VERMY
Frnt yard landscape/Water mgmt Cleared 2/18/2022 MAXFIELD VERMY
Opn space landscape/Water mgmt Cleared 2/18/2022 MAXFIELD VERMY
Tract Map conditions Cleared 2/18/2022 MAXFIELD VERMY
Specific Plan Cleared 2/22/2022 DYLAN SITTIG
Sewer availability Cleared 3/10/2022 NIKTA MOUSAVI
Specific Plan Cleared 4/5/2022 PEDRO AYALA
Low Impact Development Cleared 4/14/2022 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 4/25/2022 NIKTA MOUSAVI
Building over 36-ft Cleared 5/19/2022 CALOSHA APPROVED

Contact Information

Architect Vanos,, Vincent Jay; Lic. No.: C22269 2747 MARQUETTE DR      TOPANGA, CA 90290
Contractor H R Development Inc; Lic. No.: 991772-B 7700 DENSMORE AVE      VAN NUYS, CA 91406
Engineer Martirosian,, Hayk Sam; Lic. No.: C52563 537 NOLAN AVE      GLENDALE, CA 91202
Engineer Minas,, Caro Jolfaie; Lic. No.: GE601 4742 SAN FERNANDO RD      GLENDALE, CA 91204
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010
Landscape Architect Lewis,, Paul Adam; Lic. No.: LA3620 13351-D RIVERSIDE DR #445      SHERMAN OAKS, CA 91423

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 7/6/2023 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 7/6/2023 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 7/18/2023 Conditional Approval ARAM AVEDISIAN
Deputy Other (see comments) 8/4/2023 Conditional Approval DAVID FEILER
Footing/Foundation/Slab 8/4/2023 Approved STEPHANIE SWANSON
Deputy Reinf. Concrete 8/8/2023 Conditional Approval CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 9/7/2023 Partial Approval CLAYTON GRAHAM
Interior/Exterior Lathing 9/11/2023 Partial Approval CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 9/18/2023 Approved BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 9/27/2023 Partial Approval ARAM AVEDISIAN
Interior/Exterior Lathing 9/29/2023 Approved BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 10/10/2023 Partial Approval CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 10/17/2023 Partial Approval CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 11/9/2023 Partial Approval STEPHANIE SWANSON
Interior/Exterior Lathing 11/15/2023 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 12/7/2023 Partial Approval BEN MOLSTAD
Deputy Wood Construction 12/13/2023 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 12/13/2023 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 3/7/2024 Partial Approval ARAM AVEDISIAN
HVAC-Rough 4/22/2024 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 4/23/2024 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 4/29/2024 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 5/14/2024 Approved ASHLEY THOMPSON
BUILDING-Rough-Frame 5/15/2024 Approved ASHLEY THOMPSON
Green Building Rough 5/15/2024 Approved ASHLEY THOMPSON
Verify Sprinkler Sign Off 5/15/2024 Approved ASHLEY THOMPSON
Insulation 5/24/2024 Approved KIRK SANDERS
Drywall Nailing 6/3/2024 Approved HERBERT GIRON
Shower Pan 6/5/2024 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 6/18/2024 Approved ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 7/16/2024 Corrections Issued CARLOS MATAMOROS
Underground Mechanical 10/18/2024 Approved REGINA MENDEZ
Sewer 10/30/2024 Partial Approval REGINA MENDEZ
Underground Mechanical 11/1/2024 Corrections Issued KIRK SANDERS
Underground Mechanical 12/23/2024 Approved REGINA MENDEZ
Special/Order Compliance 2/11/2025 Corrections Issued MICHAEL PELHAM
Gas Test 2/20/2025 Approved DANIEL VERA
PLUMBING-Final 2/20/2025 Corrections Issued DANIEL VERA
PLUMBING-Final 2/26/2025 Approved JESUS RODRIGUEZ
HVAC-Final 3/10/2025 Corrections Issued KIRK SANDERS
Underground Mechanical 4/1/2025 Partial Approval BOBBY KEY
ELECTRICAL-Final 4/11/2025 Corrections Issued ARAM AVEDISIAN
Smoke Detectors 4/11/2025 Approved ARAM AVEDISIAN
ELECTRICAL-Final 4/18/2025 Approved MEL KHACHATOURIAN
HVAC-Final 4/23/2025 Approved TEMISTOCLES CAAL
Final 5/1/2025 Corrections Issued ASHLEY THOMPSON
Green Building Final 5/1/2025 Corrections Issued ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 5/1/2025 SGSOV Not Ready ASHLEY THOMPSON
Service/Power Release 5/1/2025 Approved ASHLEY THOMPSON
Final 5/20/2025 Not Ready for Inspection KIRK SANDERS
Green Building Final 5/20/2025 Not Ready for Inspection KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 5/20/2025 SGSOV Approved KIRK SANDERS
Service/Power Release 6/18/2025 Approved MICHAEL PELHAM
Special/Order Compliance 8/20/2025 Corrections Issued MICHAEL PELHAM
Final 12/26/2025 Corrections Issued ANDREW NAVE
Green Building Final 12/26/2025 Approved ANDREW NAVE
Final 12/29/2025 OK to Issue CofO ANDREW NAVE