685 W 4TH ST 1-28 90731
Certificate Information: 685 W 4TH ST 1-28 90731
- Application / Permit
- 20010-10000-01655
- Plan Check / Job No.
- B20LA08709
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (5) Apartment
- Work Description
- NEW 28 UNIT 100% SENIOR PERMANENT SUPPORTIVE HOUSING APARTMENT TO INCLUDE 4 STORY TYPE IIIA APARTMENT OVER 1 LEVEL TYPE IIIA GARAGE AND ACCESSORY USES.
- Permit Issued
- Issued on 5/11/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Plan Check Approved | 5/7/2021 | ARMEN JIVALAGIAN |
| Issued | 5/11/2021 | APPLICANT |
| TCO Issued (Expire Date: 06-26-2024) | 12/29/2023 | DAVID TSAU |
| TCO Issued (Expire Date: 12-28-2024) | 7/1/2024 | HENRY BAGHDASSARIAN |
| Permit Finaled | 9/19/2024 | HENRY BAGHDASSARIAN |
| CofO Issued | 9/19/2024 | HENRY BAGHDASSARIAN |
| Permit Finaled | 9/19/2024 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| Address approval | Cleared | 6/30/2020 | ERIK BEASLEY |
| Community Plan Implem. Overlay | Cleared | 6/30/2020 | ERIK BEASLEY |
| Permit | Cleared | 6/30/2020 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 7/1/2020 | ERIK BEASLEY |
| Sewer availability | Cleared | 7/1/2020 | ERIK BEASLEY |
| ZA Case | Cleared | 11/19/2020 | MAXFIELD VERMY |
| Building over 36-ft | Cleared | 11/25/2020 | CALOSHA APPROVED |
| Hydrant and Access approval | Cleared | 12/7/2020 | MATTHEW CRAIG |
| Historic Resource Verification | Cleared | 12/10/2020 | MICAELA TORRES-GIL |
| Redevelopment Project Area | Cleared | 12/10/2020 | GISELLE CORELLA |
| Community Plan Implem. Overlay | Cleared | 1/4/2021 | JOHN KIM |
| Trees in Parkway | Cleared | 1/4/2021 | JOHN KIM |
| GPI Written Notices | Cleared | 1/15/2021 | ARMEN JIVALAGIAN |
| Grading Pre-Inspection | Cleared | 1/15/2021 | ARMEN JIVALAGIAN |
| Community Plan Implem. Overlay | Cleared | 2/2/2021 | JEANALEE OBERGFELL |
| Community Plan Implem. Overlay | Cleared | 2/7/2021 | PEDRO AYALA |
| Low Impact Development | Cleared | 3/4/2021 | MARTIN FRAGOSO |
| Frnt yard landscape/Water mgmt | Cleared | 3/9/2021 | AIDA KARAPETIAN |
| Highway dedication | Cleared | 3/9/2021 | ERIK BEASLEY |
| Opn space landscape/Water mgmt | Cleared | 3/9/2021 | AIDA KARAPETIAN |
| Permanent Supportive Housing | Cleared | 3/9/2021 | AIDA KARAPETIAN |
| Roof/Waste drainage to street | Cleared | 3/9/2021 | ERIK BEASLEY |
| Fire Marshall Fire Life Safety | Cleared | 3/15/2021 | ANDREW KO |
| Bicycle Parking | Cleared | 3/16/2021 | CHINH DINH |
| Community Plan Implem. Overlay | Cleared | 3/29/2021 | RIDWAN HARDY |
| Construction near power lines | Cleared | 3/29/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 3/29/2021 | RIDWAN HARDY |
| DAS Clearance | Cleared | 3/30/2021 | ARMEN JIVALAGIAN |
| DCP conditions approval | Cleared | 4/1/2021 | LOUIE MILLER |
| Density Bonus 14.00.A.13 | Cleared | 4/1/2021 | LOUIE MILLER |
| Green Code | Cleared | 4/13/2021 | ARMEN JIVALAGIAN |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Ap Contractor; Lic. No.: 643672-B | 10242 MONACO DRIVE RANCHO CUCAMONGA, CA 91737 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/17/2021 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 10/13/2021 | Partial Approval | JOEY BUCHANAN |
| Footing/Foundation/Slab | 11/8/2021 | Corrections Issued | JOEY BUCHANAN |
| Pre-Inspection | 11/10/2021 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 11/12/2021 | Partial Approval | JOEY BUCHANAN |
| Structural Steel Frame | 1/4/2022 | Partial Inspection | NICK LAROCCA |
| Floor/Roof Diaphrgm/Shear Wall | 2/17/2022 | Partial Approval | JOEY BUCHANAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2022 | Partial Approval | JOEY BUCHANAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2022 | Partial Approval | JOEY BUCHANAN |
| Pre-Inspection | 4/27/2022 | Corrections Issued | JOEY BUCHANAN |
| Wood Frame | 4/27/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| Deputy Drilled-In Anchors | 5/19/2022 | Approved | JOEY BUCHANAN |
| Deputy Wood Construction | 5/26/2022 | Approved | JOEY BUCHANAN |
| Wood Frame | 6/1/2022 | Partial Approval | JOEY BUCHANAN |
| Deputy Wood Construction | 6/2/2022 | Approved | JOEY BUCHANAN |
| Wood Frame | 6/2/2022 | Partial Approval | JOEY BUCHANAN |
| Deputy Wood Construction | 6/10/2022 | Approved | JOEY BUCHANAN |
| Wood Frame | 6/10/2022 | Corrections Issued | JOEY BUCHANAN |
| Special/Order Compliance | 7/6/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| Special/Order Compliance | 7/13/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| Deputy Wood Construction | 7/21/2022 | Approved | JOEY BUCHANAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| Deputy Wood Construction | 7/26/2022 | Approved | JOEY BUCHANAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2022 | Partial Approval | JOEY BUCHANAN |
| Deputy Wood Construction | 7/29/2022 | Conditional Approval | DAVID TSAU |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2022 | Partial Approval | DAVID TSAU |
| Deputy Wood Construction | 8/22/2022 | Approved | JOEY BUCHANAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2022 | Partial Approval | JOEY BUCHANAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2022 | Corrections Issued | JOEY BUCHANAN |
| Drywall Nailing | 10/5/2022 | Not Ready for Inspection | DAVID TSAU |
| Wood Frame | 10/5/2022 | Partial Approval | DAVID TSAU |
| Wood Frame | 10/19/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| Pre-Inspection | 10/21/2022 | Approved | JOEY BUCHANAN |
| Interior/Exterior Lathing | 11/29/2022 | Approved | JOEY BUCHANAN |
| Interior/Exterior Lathing | 12/6/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| Interior/Exterior Lathing | 12/9/2022 | Approved | JOEY BUCHANAN |
| Wood Frame | 12/12/2022 | Partial Approval | JOEY BUCHANAN |
| Wood Frame | 12/13/2022 | Partial Approval | JOEY BUCHANAN |
| Wood Frame | 12/14/2022 | Partial Approval | JOEY BUCHANAN |
| Insulation | 12/27/2022 | Partial Approval | JOEY BUCHANAN |
| Interior/Exterior Lathing | 1/10/2023 | Partial Approval | JOEY BUCHANAN |
| Drywall Nailing | 1/17/2023 | Partial Approval | JOEY BUCHANAN |
| Wood Frame | 1/17/2023 | Partial Approval | JOEY BUCHANAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2023 | Not Ready for Inspection | JOEY BUCHANAN |
| Wood Frame | 2/15/2023 | Partial Approval | JOEY BUCHANAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2023 | Partial Approval | JOEY BUCHANAN |
| Insulation | 4/5/2023 | Approved | JOEY BUCHANAN |
| Interior/Exterior Lathing | 4/24/2023 | Partial Approval | JOEY BUCHANAN |
| Drywall Nailing | 5/3/2023 | Not Ready for Inspection | JOEY BUCHANAN |
| Masonry Wall/Backfill | 5/19/2023 | Partial Approval | JOEY BUCHANAN |
| Deputy Drilled-In Anchors | 6/1/2023 | Approved | JOEY BUCHANAN |
| Insulation | 6/7/2023 | Approved | JOEY BUCHANAN |
| T-Bar Ceiling | 6/7/2023 | Approved | JOEY BUCHANAN |
| Wood Frame | 7/17/2023 | Not Ready for Inspection | JOEY BUCHANAN |
| Green Building Rough | 8/15/2023 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 10/3/2023 | Corrections Issued | JOEY BUCHANAN |
| Final | 12/12/2023 | Corrections Issued | JOEY BUCHANAN |
| Footing/Foundation/Slab | 12/12/2023 | Approved | JOEY BUCHANAN |
| Green Building Final | 12/12/2023 | Approved | JOEY BUCHANAN |
| Reinforced Masonry Frame | 12/12/2023 | Approved | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 12/12/2023 | SGSOV Approved | JOEY BUCHANAN |
| Smoke Detectors | 12/12/2023 | Approved | JOEY BUCHANAN |
| Verify Sprinkler Sign Off | 12/12/2023 | Approved | JOEY BUCHANAN |
| Final | 12/14/2023 | Not Ready for Inspection | JOEY BUCHANAN |
| Final | 12/20/2023 | OK for TCO | JOEY BUCHANAN |
| Final | 3/13/2024 | Not Ready for Inspection | JOEY BUCHANAN |
| Special/Order Compliance | 5/29/2024 | Approved | JOEY BUCHANAN |
| Final | 6/11/2024 | Conditional Approval | JOEY BUCHANAN |
| Final | 8/23/2024 | Conditional Approval | JOEY BUCHANAN |