11518 W PICO BLVD 90064
Certificate Information: 11518 W PICO BLVD 90064
- Application / Permit
- 20010-10000-01654
- Plan Check / Job No.
- B20LA08704
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (18) Charter School - elementary
- Work Description
- New 3-Story School Building for 1st to 8th Grade, including 9 Classrooms, outdoor play area, lunch area and support spaces.
- Permit Issued
- Issued on 3/24/2021
- Issuing Office
- Current Status
- CofO Issued on 3/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/5/2020 | WING SUEN |
| Disabled Access Plans Picked Up | 6/22/2020 | APPLICANT |
| Corrections Issued | 6/29/2020 | WING SUEN |
| Quality Review Completed | 7/2/2020 | CHARLES CHANG |
| Building Plans Picked Up | 7/7/2020 | APPLICANT |
| Applicant returned to address corrections | 9/8/2020 | WING SUEN |
| Applicant returned to address corrections | 9/11/2020 | WING SUEN |
| Applicant returned to address corrections | 9/16/2020 | WING SUEN |
| Applicant returned to address corrections | 9/22/2020 | WING SUEN |
| Applicant returned to address corrections | 9/24/2020 | WING SUEN |
| Applicant returned to address corrections | 10/20/2020 | WING SUEN |
| Applicant returned to address corrections | 10/23/2020 | WING SUEN |
| Applicant returned to address corrections | 10/29/2020 | WING SUEN |
| Applicant returned to address corrections | 11/5/2020 | WING SUEN |
| Green Plans Picked Up | 11/10/2020 | APPLICANT |
| Applicant returned to address corrections | 11/17/2020 | WING SUEN |
| Applicant returned to address corrections | 11/20/2020 | WING SUEN |
| Applicant returned to address corrections | 11/24/2020 | WING SUEN |
| Applicant returned to address corrections | 2/17/2021 | WING SUEN |
| Applicant returned to address corrections | 3/17/2021 | WING SUEN |
| Applicant returned to address corrections | 3/18/2021 | WING SUEN |
| Plan Check Approved | 3/22/2021 | WING SUEN |
| Issued | 3/24/2021 | APPLICANT |
| TCO Issued (Expire Date: 12-02-2024) | 6/5/2024 | DAVID TSAU |
| TCO Issued (Expire Date: 05-31-2025) | 12/2/2024 | HENRY BAGHDASSARIAN |
| Permit Finaled | 3/10/2025 | HENRY BAGHDASSARIAN |
| CofO Issued | 3/10/2025 | HENRY BAGHDASSARIAN |
| Permit Finaled | 3/10/2025 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| Address approval | Cleared | 7/8/2020 | DINAH GARIN |
| Sewer availability | Cleared | 7/8/2020 | DINAH GARIN |
| CPC | Cleared | 8/13/2020 | NOAH MCCOY |
| CPC | Cleared | 8/13/2020 | NOAH MCCOY |
| Comm Cor/Mini-Mall | Cleared | 8/13/2020 | NOAH MCCOY |
| Comm Cor/Mini-Mall | Cleared | 8/13/2020 | NOAH MCCOY |
| Comm Cor/Mini-Mall | Cleared | 8/13/2020 | NOAH MCCOY |
| Highway dedication | Cleared | 8/13/2020 | RAYMOND MUGAMBWA |
| ZA Case | Cleared | 8/13/2020 | NOAH MCCOY |
| ZA Case | Cleared | 8/13/2020 | NOAH MCCOY |
| Eng Process Fee Ord 176,300 | Cleared | 8/14/2020 | DINAH GARIN |
| Work Adjacent to Public Way | Cleared | 8/19/2020 | SAUL GARCIA |
| Miscellaneous | Cleared | 9/8/2020 | DYLAN SITTIG |
| Specific Plan | Cleared | 9/8/2020 | DYLAN SITTIG |
| Supp. Use District POD/CDO/TDO | Cleared | 9/8/2020 | DYLAN SITTIG |
| ZI | Cleared | 9/8/2020 | DYLAN SITTIG |
| ZI | Cleared | 9/8/2020 | DYLAN SITTIG |
| ZI | Cleared | 9/8/2020 | DYLAN SITTIG |
| Fire Marshall Fire Life Safety | Cleared | 9/9/2020 | VIDAL GARCIA |
| Building over 36-ft | Cleared | 9/11/2020 | CALOSHA APPROVED |
| Specific Plan | Cleared | 9/24/2020 | VALERIA CEJA |
| Construction near power lines | Cleared | 9/27/2020 | RIDWAN HARDY |
| Miscellaneous | Cleared | 9/30/2020 | DINAH GARIN |
| DAS Clearance | Cleared | 10/1/2020 | WING SUEN |
| Green Code | Cleared | 10/2/2020 | VIVIAN LAO |
| Low Impact Development | Cleared | 10/5/2020 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 10/8/2020 | DINAH GARIN |
Contact Information
| Architect | Sander,, Whitney Fairbanks; Lic. No.: C20158 | 13274 FIJI WAY #150 MARINA DEL REY, CA 90292 |
| Contractor | Consolidated Contracting Services Inc; Lic. No.: 475813-B | 181 AVENIDA LA PATA SUITE 200 SAN CLEMENTE, CA 92673 |
| Engineer | Judd,, Shane Dennis; Lic. No.: C70991 | 17 E HIGH ST STE A MOORPARK, CA 93021 |
| Engineer | Perez,, Christian J; Lic. No.: C80680 | 1976 W 234TH STREET TORRANCE, CA 90501 |
Inspector Information
| PAUL DAVIDSON, (310) 914-3914 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/19/2021 | Approved | JEFF BYTHEWAY |
| Excavation/Setback/Form/Re-Bar | 5/20/2021 | Approved | JEFF BYTHEWAY |
| Deputy Grading | 5/21/2021 | Approved | JEFF BYTHEWAY |
| Deputy Grading | 5/25/2021 | Approved | JEFF BYTHEWAY |
| Deputy Grading | 5/26/2021 | Approved | JEFF BYTHEWAY |
| Footing/Foundation/Slab | 7/29/2021 | Not Ready for Inspection | JEFF BYTHEWAY |
| Pre-Inspection | 8/13/2021 | Approved | JEFF BYTHEWAY |
| Footing/Foundation/Slab | 9/2/2021 | Not Ready for Inspection | JEFF BYTHEWAY |
| Footing/Foundation/Slab | 9/9/2021 | Partial Approval | TED RIES |
| Pre-Inspection | 9/28/2021 | Not Ready for Inspection | JEFF BYTHEWAY |
| Pre-Inspection | 9/29/2021 | Partial Inspection | JEFF BYTHEWAY |
| Green Building Rough | 11/1/2021 | Not Ready for Inspection | JEFF BYTHEWAY |
| Structural Steel Frame | 11/1/2021 | Partial Approval | JEFF BYTHEWAY |
| Verify Sprinkler Sign Off | 11/1/2021 | Approved | JEFF BYTHEWAY |
| Excavation/Setback/Form/Re-Bar | 11/17/2021 | Partial Approval | JEFF BYTHEWAY |
| Footing/Foundation/Slab | 12/17/2021 | Not Ready for Inspection | NICK LAROCCA |
| Footing/Foundation/Slab | 1/11/2022 | Partial Approval | JEFF BYTHEWAY |
| Masonry Wall/Backfill | 1/24/2022 | Partial Approval | JEFF BYTHEWAY |
| Footing/Foundation/Slab | 2/1/2022 | Partial Approval | JEFF BYTHEWAY |
| Masonry Wall/Backfill | 2/1/2022 | Partial Approval | JEFF BYTHEWAY |
| Masonry Wall/Backfill | 2/14/2022 | Partial Approval | JEFF BYTHEWAY |
| Green Building Rough | 5/16/2022 | Approved | JOHN DODGE |
| Structural Steel Frame | 5/16/2022 | Conditional Approval | JOHN DODGE |
| Pre-Inspection | 5/24/2022 | Partial Approval | JEFF BYTHEWAY |
| Pre-Inspection | 6/24/2022 | Partial Approval | JEFF BYTHEWAY |
| Reinforced Concrete Frame | 6/28/2022 | Partial Approval | JEFF BYTHEWAY |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2022 | Not Ready for Inspection | JEFF BYTHEWAY |
| Wood Frame | 8/1/2022 | Corrections Issued | JEFF BYTHEWAY |
| Wood Frame | 8/5/2022 | Corrections Issued | JEFF BYTHEWAY |
| Floor/Roof Diaphrgm/Shear Wall | 8/17/2022 | Partial Approval | JEFF BYTHEWAY |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2022 | Partial Approval | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2022 | Partial Approval | JEFF BYTHEWAY |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2022 | Corrections Issued | JEFF BYTHEWAY |
| Pre-Inspection | 11/15/2022 | Approved | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2023 | Not Ready for Inspection | GRANT WOODS |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2023 | Approved | DERRICK SPENCER |
| Wood Frame | 1/30/2023 | Partial Approval | DERRICK SPENCER |
| Drywall Nailing | 2/7/2023 | Partial Approval | DERRICK SPENCER |
| Interior/Exterior Lathing | 2/9/2023 | Approved | DERRICK SPENCER |
| Drywall Nailing | 3/7/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 3/7/2023 | Partial Approval | DERRICK SPENCER |
| Pre-Inspection | 4/19/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 5/23/2023 | Partial Approval | DERRICK SPENCER |
| Final | 6/6/2023 | Not Ready for Inspection | DERRICK SPENCER |
| Footing/Foundation/Slab | 6/6/2023 | Approved | DERRICK SPENCER |
| Green Building Final | 6/6/2023 | Not Ready for Inspection | DERRICK SPENCER |
| Reinforced Masonry Frame | 6/6/2023 | Approved | DERRICK SPENCER |
| SGSOV-Seismic Gas S/O Valve | 6/6/2023 | SGSOV Approved | DERRICK SPENCER |
| Smoke Detectors | 6/6/2023 | Approved | DERRICK SPENCER |
| Structural Steel Frame | 6/6/2023 | Approved | DERRICK SPENCER |
| Wood Frame | 6/6/2023 | Approved | DERRICK SPENCER |
| Pre-Inspection | 7/6/2023 | Approved | DERRICK SPENCER |
| Pre-Inspection | 7/13/2023 | Approved | DERRICK SPENCER |
| Pre-Inspection | 9/7/2023 | Approved | DERRICK SPENCER |
| Final | 4/23/2024 | Not Ready for Inspection | PAUL DAVIDSON |
| Green Building Final | 4/23/2024 | Not Ready for Inspection | PAUL DAVIDSON |
| Final | 5/20/2024 | Not Ready for Inspection | PAUL DAVIDSON |
| Green Building Final | 5/20/2024 | Approved | PAUL DAVIDSON |
| Final | 5/30/2024 | Partial Inspection | PAUL DAVIDSON |
| Final | 6/6/2024 | OK for TCO | PAUL DAVIDSON |
| Special/Order Compliance | 11/5/2024 | Conditional Approval | PAUL DAVIDSON |
| Special/Order Compliance | 11/26/2024 | Corrections Issued | PAUL DAVIDSON |
| Special/Order Compliance | 3/5/2025 | Partial Inspection | PAUL DAVIDSON |