Footing/Foundation/Slab
|
10/6/2021
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
10/18/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Excavation/Setback/Form/Re-Bar
|
10/18/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
10/20/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
10/21/2021
|
Approved
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
10/22/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
11/2/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
11/2/2021
|
Corrections Issued
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
11/3/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
11/3/2021
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Green Building Rough
|
11/9/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
11/9/2021
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
11/16/2021
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
11/19/2021
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
11/29/2021
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Green Building Rough
|
11/30/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
11/30/2021
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Verify Sprinkler Sign Off
|
11/30/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
12/1/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
12/1/2021
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
12/2/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Wall Anchors
|
12/2/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
12/3/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
12/6/2021
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
12/7/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
12/8/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
12/13/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
12/23/2021
|
Conditional Approval
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
1/21/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
1/25/2022
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
2/14/2022
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Wood Construction
|
2/16/2022
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Wood Construction
|
2/18/2022
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Wood Construction
|
2/22/2022
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/23/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
3/2/2022
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
3/4/2022
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/7/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Wood Construction
|
3/8/2022
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
3/15/2022
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Wood Construction
|
3/17/2022
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/17/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Green Building Rough
|
3/18/2022
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
3/18/2022
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Verify Sprinkler Sign Off
|
3/18/2022
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
3/21/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
3/25/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
3/30/2022
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/30/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Wood Construction
|
3/31/2022
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Wood Construction
|
4/7/2022
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/8/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Wood Construction
|
4/13/2022
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/14/2022
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
4/20/2022
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/20/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Drywall Nailing
|
4/27/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Drywall Nailing
|
5/2/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
5/2/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Wood Construction
|
5/3/2022
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Wood Construction
|
5/4/2022
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/4/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
5/9/2022
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/10/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
5/10/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
5/10/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Wood Construction
|
5/11/2022
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/12/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
5/12/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
5/12/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
5/17/2022
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/19/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Wood Construction
|
5/24/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Drywall Nailing
|
5/24/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/24/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
5/24/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
5/24/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Wood Construction
|
6/2/2022
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/2/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
6/2/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
6/9/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
6/9/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
6/9/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Wood Construction
|
6/15/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Light Gage Steel Frame
|
6/15/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
6/15/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
6/21/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
6/23/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
6/23/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
6/23/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
6/29/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Wood Construction
|
7/5/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Insulation
|
7/6/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Wood Construction
|
7/7/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Drywall Nailing
|
7/21/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Interior/Exterior Lathing
|
7/21/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Drywall Nailing
|
8/3/2022
|
Partial Approval
|
TED RIES
|
|
Structural Steel Frame
|
8/3/2022
|
Partial Approval
|
TED RIES
|
|
Insulation
|
8/8/2022
|
Partial Approval
|
TED RIES
|
|
Deputy Wood Construction
|
8/9/2022
|
Conditional Approval
|
WINSTON DUNNING
|
|
Light Gage Steel Frame
|
8/11/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Wood Construction
|
8/12/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Light Gage Steel Frame
|
8/17/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Interior/Exterior Lathing
|
8/22/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
9/6/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
9/29/2022
|
Approved
|
BRUCE CAMPBELL
|
|
Deputy Wood Construction
|
10/13/2022
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Fireproofing
|
11/2/2022
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Masonry
|
2/17/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Masonry
|
2/27/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Light Gage Steel Frame
|
3/9/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Pre-Inspection
|
3/14/2023
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
3/28/2023
|
Partial Approval
|
ALAN MORELOS
|
|
Interior/Exterior Lathing
|
4/4/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Special/Order Compliance
|
4/4/2023
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
4/24/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
5/2/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
5/11/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
5/19/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Masonry
|
5/30/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Masonry
|
5/31/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Masonry
|
6/1/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Masonry
|
6/2/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Masonry
|
6/5/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Light Gage Steel Frame
|
6/27/2023
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Special/Order Compliance
|
6/30/2023
|
Corrections Issued
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
7/11/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Special/Order Compliance
|
7/11/2023
|
Partial Inspection
|
TED RIES
|
|
Insulation
|
7/13/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Drywall Nailing
|
7/17/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
8/24/2023
|
Corrections Issued
|
LARRY ARNICK
|
|
Special/Order Compliance
|
9/7/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Final
|
10/18/2023
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
10/18/2023
|
Approved
|
RAFAEL ESPINOZA
|
|
Green Building Final
|
10/18/2023
|
Approved
|
RAFAEL ESPINOZA
|
|
Green Building Rough
|
10/18/2023
|
Approved
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
10/18/2023
|
Approved
|
RAFAEL ESPINOZA
|
|
SGSOV-Seismic Gas S/O Valve
|
10/18/2023
|
SGSOV Approved
|
RAFAEL ESPINOZA
|
|
Smoke Detectors
|
10/18/2023
|
Approved
|
RAFAEL ESPINOZA
|
|
Verify Sprinkler Sign Off
|
10/18/2023
|
Approved
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
10/18/2023
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Final
|
3/1/2024
|
OK to Issue CofO
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
3/1/2024
|
Approved
|
RAFAEL ESPINOZA
|
|
Special/Order Compliance
|
4/2/2024
|
Approved
|
RAFAEL ESPINOZA
|