341 N MATHEWS ST 90033

Certificate Information: 341 N MATHEWS ST 90033

Application / Permit
20010-10000-01639
Plan Check / Job No.
B20LA08600
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 100% AFFORDABLE HOUSING 50 UNITS, 4 STORY APARTMENT BUILDING TO INCLUDIE 3 STORY TYPE VA APARTMENT OVER 1 STORY TYPE IA / VA MIXED USED RECREATION ROOM PER SECTION 12.22 A25 OF THE LAMC. 2 OF 2
Permit Issued
Issued on 7/27/2021
Issuing Office
Metro
Current Status
CofO Issued on 4/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/12/2021 APPLICANT
Assigned to Plan Check Engineer 2/1/2021 EUGENE BARBEAU
Corrections Issued 2/1/2021 EUGENE BARBEAU
Plan Check Approved 7/15/2021 EUGENE BARBEAU
Issued 7/27/2021 APPLICANT
TCO Issued (Expire Date: 04-28-2024) 10/31/2023 TED RIES
CofO in Progress 3/1/2024 RAFAEL ESPINOZA
CofO Issued 4/3/2024 ERNESTO CORRAL
Permit Finaled 4/3/2024 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 9/16/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 2/9/2021 THOMAS LANG
Highway dedication Cleared 2/26/2021 THOMAS LANG
Metro Rail approval Cleared 3/5/2021 EUGENE BARBEAU
Redevelopment Project Area Cleared 3/16/2021 GRACIELA ACOSTA
Trees in Parkway Cleared 3/31/2021 JOHN KIM
Green Code Cleared 4/5/2021 EUGENE BARBEAU
Building over 36-ft Cleared 5/10/2021 CALOSHA APPROVED
Permit Cleared 5/11/2021 CECILIO NAVARRO
Hydrant and Access approval Cleared 6/9/2021 MATTHEW CRAIG
Work Adjacent to Public Way Cleared 6/10/2021 JOSE RODRIGUEZ
Low Impact Development Cleared 6/18/2021 ANDRES COVARRUBIAS
DAS Clearance Cleared 6/22/2021 EUGENE BARBEAU
Public Housing Cleared 6/22/2021 LUIS ALVAREZ
CPC Cleared 6/23/2021 DANG NGUYEN
Clean Up Green Up Cleared 6/23/2021 DANG NGUYEN
Frnt yard landscape/Water mgmt Cleared 6/23/2021 DANG NGUYEN
Historic monument Cleared 6/23/2021 LAMBERT GIESSINGER
Opn space landscape/Water mgmt Cleared 6/23/2021 DANG NGUYEN
Prkng lot landscape/Water mgmt Cleared 6/23/2021 DANG NGUYEN
Sewer availability Cleared 6/23/2021 THOMAS LANG
ZA Case Cleared 6/23/2021 DANG NGUYEN
ZA Case Cleared 6/23/2021 DANG NGUYEN
Density Bonus 12.22.A.25 Cleared 6/24/2021 LOUIE MILLER
Fire Marshall Fire Life Safety Cleared 6/24/2021 OSCAR SALGADO JR
Roof/Waste drainage to street Cleared 6/24/2021 THAN WIN

Contact Information

Architect Aliano,, Giuseppe; Lic. No.: C26571 3408 BUENA VISTA AVE      GLENDALE, CA 91208
Contractor Walton Construction Inc; Lic. No.: 1034491-B 358 E FOOTHILL BLVD STE 100      SAN DIMAS, CA 91773
Engineer Adams,, Jelisa Thomas; Lic. No.: GE3092 26632 EL TOBOSO      MISSION VIEJO, CA 92691
Engineer Arriola,, Kirby Norman; Lic. No.: C31416 PO BOX 5566      OXNARD, CA 93031
Engineer Curran,, Sarah Kathryn; Lic. No.: C69620 759 TEMPLE ST      SAN DIEGO, CA 92106
Engineer Yeh,, Ming-Yang; Lic. No.: S2587 131 WEST GREEN ST      PASADENA, CA 911059886
Landscape Architect Mather,, Evan Richard; Lic. No.: LA4805 1007 DOLORES DRIVE      ALTADENA, CA 91001

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/6/2021 Partial Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 10/18/2021 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 10/18/2021 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 10/20/2021 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 10/21/2021 Approved RAFAEL ESPINOZA
Deputy Reinf. Concrete 10/22/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 11/2/2021 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 11/2/2021 Corrections Issued RAFAEL ESPINOZA
Deputy Reinf. Concrete 11/3/2021 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 11/3/2021 Partial Approval RAFAEL ESPINOZA
Green Building Rough 11/9/2021 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 11/9/2021 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 11/16/2021 Partial Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 11/19/2021 Partial Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 11/29/2021 Conditional Approval ERNESTO CORRAL
Green Building Rough 11/30/2021 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 11/30/2021 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 11/30/2021 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 12/1/2021 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 12/1/2021 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 12/2/2021 Not Ready for Inspection RAFAEL ESPINOZA
Wall Anchors 12/2/2021 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 12/3/2021 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 12/6/2021 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 12/7/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 12/8/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 12/13/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 12/23/2021 Conditional Approval NICK DANERI
Footing/Foundation/Slab 1/21/2022 Partial Approval RAFAEL ESPINOZA
Deputy Steel/Welding 1/25/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 2/14/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Wood Construction 2/16/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Wood Construction 2/18/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Wood Construction 2/22/2022 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 2/23/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 3/2/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 3/4/2022 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/7/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 3/8/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 3/15/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Wood Construction 3/17/2022 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/17/2022 Partial Approval RAFAEL ESPINOZA
Green Building Rough 3/18/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 3/18/2022 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 3/18/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 3/21/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 3/25/2022 Conditional Approval ERNESTO CORRAL
Deputy Wood Construction 3/30/2022 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/30/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 3/31/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Wood Construction 4/7/2022 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 4/8/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 4/13/2022 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 4/14/2022 Partial Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 4/20/2022 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 4/20/2022 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 4/27/2022 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 5/2/2022 Partial Approval RAFAEL ESPINOZA
Wood Frame 5/2/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 5/3/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Wood Construction 5/4/2022 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 5/4/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/9/2022 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 5/10/2022 Partial Approval RAFAEL ESPINOZA
Insulation 5/10/2022 Partial Approval RAFAEL ESPINOZA
Wood Frame 5/10/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 5/11/2022 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 5/12/2022 Partial Approval RAFAEL ESPINOZA
Insulation 5/12/2022 Partial Approval RAFAEL ESPINOZA
Wood Frame 5/12/2022 Partial Approval RAFAEL ESPINOZA
Insulation 5/17/2022 Partial Inspection ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 5/19/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 5/24/2022 Conditional Approval ERNESTO CORRAL
Drywall Nailing 5/24/2022 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 5/24/2022 Partial Approval RAFAEL ESPINOZA
Insulation 5/24/2022 Partial Approval RAFAEL ESPINOZA
Wood Frame 5/24/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 6/2/2022 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 6/2/2022 Partial Approval RAFAEL ESPINOZA
Wood Frame 6/2/2022 Partial Approval RAFAEL ESPINOZA
Insulation 6/9/2022 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 6/9/2022 Partial Approval RAFAEL ESPINOZA
Wood Frame 6/9/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 6/15/2022 Conditional Approval ERNESTO CORRAL
Light Gage Steel Frame 6/15/2022 Partial Approval RAFAEL ESPINOZA
Wood Frame 6/15/2022 Partial Approval RAFAEL ESPINOZA
Insulation 6/21/2022 Partial Approval RAFAEL ESPINOZA
Insulation 6/23/2022 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 6/23/2022 Partial Approval RAFAEL ESPINOZA
Wood Frame 6/23/2022 Partial Approval RAFAEL ESPINOZA
Insulation 6/29/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 7/5/2022 Conditional Approval ERNESTO CORRAL
Insulation 7/6/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 7/7/2022 Conditional Approval ERNESTO CORRAL
Drywall Nailing 7/21/2022 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 7/21/2022 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 8/3/2022 Partial Approval TED RIES
Structural Steel Frame 8/3/2022 Partial Approval TED RIES
Insulation 8/8/2022 Partial Approval TED RIES
Deputy Wood Construction 8/9/2022 Conditional Approval WINSTON DUNNING
Light Gage Steel Frame 8/11/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 8/12/2022 Conditional Approval ERNESTO CORRAL
Light Gage Steel Frame 8/17/2022 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 8/22/2022 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 9/6/2022 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 9/29/2022 Approved BRUCE CAMPBELL
Deputy Wood Construction 10/13/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Fireproofing 11/2/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 2/17/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 2/27/2023 Conditional Approval MICHAEL ROSENBERG
Light Gage Steel Frame 3/9/2023 Partial Approval RAFAEL ESPINOZA
Pre-Inspection 3/14/2023 Partial Inspection RAFAEL ESPINOZA
Light Gage Steel Frame 3/28/2023 Partial Approval ALAN MORELOS
Interior/Exterior Lathing 4/4/2023 Partial Approval RAFAEL ESPINOZA
Special/Order Compliance 4/4/2023 Partial Inspection RAFAEL ESPINOZA
Light Gage Steel Frame 4/24/2023 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/2/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 5/11/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 5/19/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 5/30/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 5/31/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 6/1/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 6/2/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 6/5/2023 Conditional Approval MICHAEL ROSENBERG
Light Gage Steel Frame 6/27/2023 Not Ready for Inspection RAFAEL ESPINOZA
Special/Order Compliance 6/30/2023 Corrections Issued RAFAEL ESPINOZA
Light Gage Steel Frame 7/11/2023 Partial Approval RAFAEL ESPINOZA
Special/Order Compliance 7/11/2023 Partial Inspection TED RIES
Insulation 7/13/2023 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 7/17/2023 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 8/24/2023 Corrections Issued LARRY ARNICK
Special/Order Compliance 9/7/2023 Partial Approval RAFAEL ESPINOZA
Final 10/18/2023 Partial Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 10/18/2023 Approved RAFAEL ESPINOZA
Green Building Final 10/18/2023 Approved RAFAEL ESPINOZA
Green Building Rough 10/18/2023 Approved RAFAEL ESPINOZA
Reinforced Concrete Frame 10/18/2023 Approved RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 10/18/2023 SGSOV Approved RAFAEL ESPINOZA
Smoke Detectors 10/18/2023 Approved RAFAEL ESPINOZA
Verify Sprinkler Sign Off 10/18/2023 Approved RAFAEL ESPINOZA
Wood Frame 10/18/2023 Not Ready for Inspection RAFAEL ESPINOZA
Final 3/1/2024 OK to Issue CofO RAFAEL ESPINOZA
Wood Frame 3/1/2024 Approved RAFAEL ESPINOZA
Special/Order Compliance 4/2/2024 Approved RAFAEL ESPINOZA