NEW MIXED-USED, 100% AFFORDABLE HOUSING APARTMENT BUILDING PER SECTION 12.22 A25 OF THE LAMC. 1 OF 2
Permit Issued
Issued on 7/27/2021
Issuing Office
Metro
Current Status
CofO Issued on 4/11/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/12/2021 APPLICANT
Assigned to Plan Check Engineer 2/1/2021 EUGENE BARBEAU
Corrections Issued 2/1/2021 EUGENE BARBEAU
Plan Check Approved 7/15/2021 EUGENE BARBEAU
Issued 7/27/2021 APPLICANT
TCO Issued (Expire Date: 06-25-2024) 12/28/2023 ERNESTO CORRAL
CofO in Progress 4/10/2024 RAFAEL ESPINOZA
Permit Finaled 4/11/2024 ADAM BURGESS
CofO Issued 4/11/2024 ADAM BURGESS
Permit Finaled 4/11/2024 ADAM BURGESS

Permit Application Clearance Information

Address approval Cleared 9/16/2020 THOMAS LANG
City Hist. Cultural Monument Cleared 1/25/2021 MICAELA TORRES-GIL
Historic monument Cleared 1/25/2021 MICAELA TORRES-GIL
Eng Process Fee Ord 176,300 Cleared 1/26/2021 ELAINE LEI
Sewer availability Cleared 1/26/2021 ELAINE LEI
Metro Rail approval Cleared 3/5/2021 EUGENE BARBEAU
Redevelopment Project Area Cleared 3/16/2021 GRACIELA ACOSTA
Highway dedication Cleared 3/23/2021 CECILIO NAVARRO
Trees in Parkway Cleared 3/31/2021 JOHN KIM
Green Code Cleared 4/5/2021 EUGENE BARBEAU
Building over 36-ft Cleared 5/10/2021 CALOSHA APPROVED
Permit Cleared 5/11/2021 CECILIO NAVARRO
Hydrant and Access approval Cleared 6/9/2021 MATTHEW CRAIG
Fire Marshall Fire Life Safety Cleared 6/11/2021 VIDAL GARCIA
Low Impact Development Cleared 6/18/2021 ANDRES COVARRUBIAS
DAS Clearance Cleared 6/22/2021 EUGENE BARBEAU
Public Housing Cleared 6/22/2021 LUIS ALVAREZ
CPC Cleared 6/23/2021 DANG NGUYEN
Clean Up Green Up Cleared 6/23/2021 DANG NGUYEN
Clean Up Green Up Cleared 6/23/2021 DANG NGUYEN
Frnt yard landscape/Water mgmt Cleared 6/23/2021 DANG NGUYEN
Opn space landscape/Water mgmt Cleared 6/23/2021 DANG NGUYEN
Prkng lot landscape/Water mgmt Cleared 6/23/2021 DANG NGUYEN
Site Plan review Cleared 6/23/2021 DANG NGUYEN
ZA Case Cleared 6/23/2021 DANG NGUYEN
ZA Case Cleared 6/23/2021 DANG NGUYEN
Density Bonus 12.22.A.25 Cleared 6/24/2021 LOUIE MILLER
Roof/Waste drainage to street Cleared 6/24/2021 THAN WIN

Contact Information

Architect Aliano,, Giuseppe; Lic. No.: C26571 3408 BUENA VISTA AVE      GLENDALE, CA 91208
Contractor Walton Construction Inc; Lic. No.: 1034491-B 358 E FOOTHILL BLVD STE 100      SAN DIMAS, CA 91773
Engineer Adams,, Jelisa Thomas; Lic. No.: GE3092 26632 EL TOBOSO      MISSION VIEJO, CA 92691
Engineer Arriola,, Kirby Norman; Lic. No.: C31416 PO BOX 5566      OXNARD, CA 93031
Engineer Curran,, Sarah Kathryn; Lic. No.: C69620 759 TEMPLE ST      SAN DIEGO, CA 92106
Engineer Yeh,, Ming-Yang; Lic. No.: S2587 131 WEST GREEN ST      PASADENA, CA 911059886
Landscape Architect Mather,, Evan Richard; Lic. No.: LA4805 1007 DOLORES DRIVE      ALTADENA, CA 91001

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/10/2021 Approved RAFAEL ESPINOZA
Footing/Foundation/Slab 12/10/2021 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 1/21/2022 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 2/14/2022 Not Ready for Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 4/21/2022 Approved RAFAEL ESPINOZA
Deputy Reinf. Concrete 4/25/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 5/3/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 5/13/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/18/2022 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 5/19/2022 Approved RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 6/21/2022 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 7/6/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 7/12/2022 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 7/21/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 7/25/2022 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 8/2/2022 Partial Approval TED RIES
Deputy Steel/Welding 8/5/2022 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 8/9/2022 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 8/16/2022 Partial Approval RAFAEL ESPINOZA
Green Building Rough 8/31/2022 Approved RAFAEL ESPINOZA
Insulation 8/31/2022 Partial Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 8/31/2022 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 8/31/2022 Partial Approval RAFAEL ESPINOZA
Insulation 9/6/2022 Partial Approval RAFAEL ESPINOZA
Insulation 9/8/2022 Partial Approval RAFAEL ESPINOZA
Wood Frame 9/16/2022 Partial Approval RAFAEL ESPINOZA
Insulation 9/22/2022 Partial Approval RAFAEL ESPINOZA
Wood Frame 9/22/2022 Partial Approval RAFAEL ESPINOZA
Insulation 9/29/2022 Partial Approval BRUCE CAMPBELL
Floor/Roof Diaphrgm/Shear Wall 10/4/2022 Partial Inspection RAFAEL ESPINOZA
Insulation 10/6/2022 Partial Approval RAFAEL ESPINOZA
Wood Frame 10/6/2022 Partial Approval RAFAEL ESPINOZA
Insulation 10/13/2022 Partial Approval RAFAEL ESPINOZA
Wood Frame 10/13/2022 Partial Approval RAFAEL ESPINOZA
Insulation 10/24/2022 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 10/24/2022 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 10/24/2022 Partial Approval RAFAEL ESPINOZA
Deputy Other (see comments) 10/26/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Other (see comments) 10/28/2022 Conditional Approval MICHAEL ROSENBERG
Insulation 10/31/2022 Partial Inspection RAFAEL ESPINOZA
Insulation 11/18/2022 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 11/18/2022 Partial Approval RAFAEL ESPINOZA
Insulation 11/22/2022 Partial Inspection RAFAEL ESPINOZA
Light Gage Steel Frame 11/22/2022 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 11/29/2022 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 12/5/2022 Partial Approval RAFAEL ESPINOZA
Insulation 12/8/2022 Partial Approval JEROME BLACKWOOD
Light Gage Steel Frame 2/7/2023 Partial Approval RAFAEL ESPINOZA
Insulation 2/14/2023 Not Ready for Inspection RAFAEL ESPINOZA
Insulation 2/21/2023 Partial Approval JULIAN CAPUCETTI
Light Gage Steel Frame 4/24/2023 Not Ready for Inspection RAFAEL ESPINOZA
Light Gage Steel Frame 4/25/2023 Approved RAFAEL ESPINOZA
Light Gage Steel Frame 8/4/2023 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 8/7/2023 Approved RAFAEL ESPINOZA
Drywall Nailing 8/10/2023 Partial Approval RAFAEL ESPINOZA
Green Building Final 8/10/2023 Not Ready for Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 8/10/2023 SGSOV Not Ready RAFAEL ESPINOZA
Smoke Detectors 8/10/2023 Not Ready for Inspection RAFAEL ESPINOZA
Special/Order Compliance 8/10/2023 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 8/10/2023 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 8/10/2023 Not Ready for Inspection RAFAEL ESPINOZA
Final 11/15/2023 Partial Inspection RAFAEL ESPINOZA
Green Building Final 11/15/2023 Approved RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 11/15/2023 SGSOV Not Ready RAFAEL ESPINOZA
Smoke Detectors 11/15/2023 Not Ready for Inspection RAFAEL ESPINOZA
Special/Order Compliance 11/15/2023 Approved RAFAEL ESPINOZA
Verify Sprinkler Sign Off 11/15/2023 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 11/15/2023 Not Ready for Inspection RAFAEL ESPINOZA
Final 11/27/2023 Partial Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 11/27/2023 SGSOV Not Ready RAFAEL ESPINOZA
Smoke Detectors 11/27/2023 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 11/27/2023 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 11/27/2023 Not Ready for Inspection RAFAEL ESPINOZA
Final 4/10/2024 OK to Issue CofO RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 4/10/2024 SGSOV Approved RAFAEL ESPINOZA
Smoke Detectors 4/10/2024 Approved RAFAEL ESPINOZA
Verify Sprinkler Sign Off 4/10/2024 Approved RAFAEL ESPINOZA
Wood Frame 4/10/2024 Approved RAFAEL ESPINOZA