5275 N ELLENWOOD DR 90041
Certificate Information: 5275 N ELLENWOOD DR 90041
- Application / Permit
- 20010-10000-01618
- Plan Check / Job No.
- B20LA08567
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- BUILD NEW 1 STORY DETACHED ADU 384 SF
- Permit Issued
- Issued on 9/25/2020
- Issuing Office
- Current Status
- CofO Issued on 9/25/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/18/2020 | CARLOS MONTES |
| Corrections Issued | 5/22/2020 | CARLOS MONTES |
| Quality Review Completed | 5/22/2020 | JASON HEALEY |
| Building Plans Picked Up | 6/15/2020 | APPLICANT |
| Plan Check Approved | 9/25/2020 | CARLOS MONTES |
| Issued | 9/25/2020 | APPLICANT |
| CofO in Progress | 7/2/2021 | CRAIG VAUGHAN |
| Permit Finaled | 9/25/2021 | DEROLD HAUFF |
| CofO Issued | 9/25/2021 | DEROLD HAUFF |
| Permit Finaled | 9/25/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/6/2020 | THOMAS LANG |
| Roof/Waste drainage to street | Cleared | 7/6/2020 | THOMAS LANG |
| Grading Pre-Inspection | Cleared | 7/29/2020 | KIRK LINKLATER |
| Hydrant and Access approval | Cleared | 8/4/2020 | KURT CORRAL |
| Eng Process Fee Ord 176,300 | Cleared | 8/5/2020 | THOMAS LANG |
| Sewer availability | Cleared | 8/5/2020 | THOMAS LANG |
| Green Code | Cleared | 9/16/2020 | KHEDER ALRAZAA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 | 2160 PARNELL WY ALTADENA, CA 91001 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/19/2020 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 12/16/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 12/16/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2020 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 12/16/2020 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 12/16/2020 | Approved | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 12/16/2020 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 12/21/2020 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 1/11/2021 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 1/11/2021 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Rough | 1/11/2021 | Corrections Issued | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 2/9/2021 | Approved | CRAIG VAUGHAN |
| Insulation | 2/11/2021 | Conditional Approval | SCOTT FINNILA |
| Drywall Nailing | 2/16/2021 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 2/16/2021 | Approved | CRAIG VAUGHAN |
| Shower Pan | 2/16/2021 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 4/7/2021 | Approved | BRIAN SULLIVAN |
| Final | 4/7/2021 | Corrections Issued | BRIAN SULLIVAN |
| Green Building Final | 4/7/2021 | Approved | BRIAN SULLIVAN |
| HVAC-Final | 4/7/2021 | Approved | BRIAN SULLIVAN |
| PLUMBING-Final | 4/7/2021 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 4/7/2021 | SGSOV Not Ready | BRIAN SULLIVAN |
| Service/Power Release | 4/7/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Smoke Detectors | 4/7/2021 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 4/16/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Final | 4/16/2021 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 4/16/2021 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Final | 4/28/2021 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 4/28/2021 | Corrections Issued | CRAIG VAUGHAN |
| Gas Test | 5/27/2021 | Approved | COREY HUPP |
| Final | 6/30/2021 | OK to Issue CofO | CRAIG VAUGHAN |
| PLUMBING-Final | 6/30/2021 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 6/30/2021 | SGSOV Approved | CRAIG VAUGHAN |
| Service/Power Release | 6/30/2021 | Approved | CRAIG VAUGHAN |