217 N ST ANDREWS PL 90004
Certificate Information: 217 N ST ANDREWS PL 90004
- Application / Permit
- 20010-10000-01550
- Plan Check / Job No.
- B20LA08395
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 25'X14'-2" 2-STORY ADU IN REAR YARD PER LAMC 12.22 A.33 (c) AND (d). See application comment for the conditional clearance approval of the encroachment application by LADWP. 2 OF 2
- Permit Issued
- Issued on 11/13/2020
- Issuing Office
- Current Status
- CofO Issued on 8/14/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/28/2020 | CHUNG-WEN CHUANG |
| Corrections Issued | 6/15/2020 | CHUNG-WEN CHUANG |
| Quality Review Completed | 6/23/2020 | KESETE HAREGOT |
| Applicant returned to address corrections | 8/25/2020 | CHUNG-WEN CHUANG |
| Plan Check Approved | 11/6/2020 | CHUNG-WEN CHUANG |
| Issued | 11/13/2020 | APPLICANT |
| Building Plans Picked Up | 11/16/2020 | APPLICANT |
| CofO in Progress | 8/4/2021 | CHRIS CHRISTENSEN |
| CofO Issued | 8/14/2021 | DEROLD HAUFF |
| Permit Finaled | 8/14/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/21/2020 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 7/21/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 7/21/2020 | RENZ SORIANO |
| Hydrant and Access approval | Cleared | 9/3/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 10/5/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 10/5/2020 | RENZ SORIANO |
| Construction near power lines | Cleared | 11/6/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 11/6/2020 | RIDWAN HARDY |
Contact Information
| Architect | Thompson,, Richard William; Lic. No.: C9821 | 1850 INDUSTRIAL AVENUE # 412 LOS ANGELES, CA 90021 |
| Contractor | Brunswick Builders Inc; Lic. No.: 785137-B | 7190 W SUNSET BLVD #513 LOS ANGELES, CA 90046 |
| Engineer | Cox,, Steven Jeffrey; Lic. No.: C48940 | 130 MAGELLAN ST THOUSAND OAKS, CA 91360 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/23/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Underground Mechanical | 11/23/2020 | Approved | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 12/2/2020 | Approved | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 12/2/2020 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 12/10/2020 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 1/13/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Sewer | 1/21/2021 | Approved | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 2/5/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 2/5/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Rough-Elec/Plmb/HVAC | 2/5/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 2/16/2021 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 2/16/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 2/16/2021 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 2/16/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 2/16/2021 | Approved | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 2/16/2021 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 2/16/2021 | Approved | CHRIS CHRISTENSEN |
| Insulation | 2/24/2021 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 3/5/2021 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 3/5/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Shower Pan | 3/5/2021 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 3/8/2021 | Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 4/16/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Underground Mechanical | 4/16/2021 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 4/27/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 4/27/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 4/27/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Final | 4/27/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| PLUMBING-Final | 4/27/2021 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 4/27/2021 | SGSOV Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 4/27/2021 | Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 4/27/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 7/14/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 7/14/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Final | 8/4/2021 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 8/4/2021 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 8/4/2021 | Approved | CHRIS CHRISTENSEN |