451 E 84TH PL 90003

Certificate Information: 451 E 84TH PL 90003

Application / Permit
20010-10000-01548
Plan Check / Job No.
B20LA08396
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY ADU PER GCS 65852.2(E)(1)(B) 2 BEDROOM AND 2 BATHROOMS.
Permit Issued
Issued on 5/27/2021
Issuing Office
Valley
Current Status
CofO Issued on 4/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/8/2020 APPLICANT
Assigned to Plan Check Engineer 5/11/2020 JESSE JIMENEZ
Corrections Issued 5/12/2020 JESSE JIMENEZ
Applicant returned to address corrections 10/26/2020 STARR CHEN
Applicant returned to address corrections 3/18/2021 AUNG SOE
Building Plans Picked Up 3/22/2021 APPLICANT
Plan Check Approved 5/12/2021 JESSE JIMENEZ
Issued 5/27/2021 APPLICANT
CofO in Progress 3/31/2022 LILIANA PORTILLO
Permit Finaled 4/13/2022 DEROLD HAUFF
CofO Issued 4/13/2022 DEROLD HAUFF
Permit Finaled 4/13/2022 DEROLD HAUFF

Permit Application Clearance Information

Certificate of Compliance Cleared 5/22/2020 MAXFIELD VERMY
"Q" conditions Cleared 5/28/2020 MAXFIELD VERMY
Address approval Cleared 5/28/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 5/28/2020 JEANIE LAM
Sewer availability Cleared 5/28/2020 JEANIE LAM
Hydrant and Access approval Cleared 9/30/2020 KURT CORRAL
Low Impact Development Cleared 10/6/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 10/16/2020 JEANIE LAM
Highway dedication Cleared 2/16/2021 JEANIE LAM
Trees in Parkway Cleared 4/27/2021 JOHN KIM
Permit Cleared 5/4/2021 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Truong,, Phong Lap; Lic. No.: C70784 20754 TIMBERLINE LN      WALNUT, CA 91789

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/11/2021 Approved ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 8/11/2021 Corrections Issued JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 8/18/2021 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 9/24/2021 Partial Approval JOAQUIN GREENOUGH
Gas Test 10/1/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Green Building Rough 10/1/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Insulation 10/1/2021 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Rough 10/1/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Sewer 10/1/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Underground Mechanical 10/1/2021 Corrections Issued JOAQUIN GREENOUGH
Insulation 10/4/2021 Partial Approval EUGENE CASSIDY
Underground Mechanical 10/4/2021 Partial Approval EUGENE CASSIDY
Insulation 10/6/2021 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 10/6/2021 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/8/2021 Partial Approval ADAM ESCOTO
Insulation 10/8/2021 Partial Approval ADAM ESCOTO
Footing/Foundation/Slab 10/12/2021 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 10/15/2021 Partial Approval CRAIG DAVIS
Footing/Foundation/Slab 10/22/2021 Approved DANIEL GONZALEZ
BUILDING-Rough-Frame 12/17/2021 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 12/17/2021 Approved ANTHONY EGSON
Green Building Rough 12/17/2021 Corrections Issued ANTHONY EGSON
Verify Sprinkler Sign Off 12/17/2021 Corrections Issued ANTHONY EGSON
Wood Frame 12/17/2021 Corrections Issued ANTHONY EGSON
Interior/Exterior Lathing 1/6/2022 Approved ANTHONY EGSON
BUILDING-Rough-Frame 1/11/2022 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 1/11/2022 Approved FREDDIE RIVERA
Green Building Rough 1/11/2022 Not Ready for Inspection FREDDIE RIVERA
HVAC-Rough 1/11/2022 Approved FREDDIE RIVERA
PLUMBING-Rough 1/11/2022 Approved FREDDIE RIVERA
Rough-Elec/Plmb/HVAC 1/11/2022 Not Ready for Inspection FREDDIE RIVERA
Shower Pan 1/11/2022 Not Ready for Inspection FREDDIE RIVERA
Verify Sprinkler Sign Off 1/11/2022 Approved FREDDIE RIVERA
Wood Frame 1/11/2022 Not Ready for Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 1/12/2022 Approved FREDDIE RIVERA
Green Building Rough 1/12/2022 Approved FREDDIE RIVERA
Insulation 1/19/2022 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 1/24/2022 Approved LILIANA PORTILLO
Shower Pan 1/24/2022 Approved LILIANA PORTILLO
Drywall Nailing 1/26/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 3/1/2022 Approved LILIANA PORTILLO
HVAC-Final 3/1/2022 Approved LILIANA PORTILLO
PLUMBING-Final 3/1/2022 Approved LILIANA PORTILLO
Final 3/4/2022 Corrections Issued LILIANA PORTILLO
Green Building Final 3/4/2022 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 3/4/2022 SGSOV Not Ready LILIANA PORTILLO
Smoke Detectors 3/4/2022 Approved LILIANA PORTILLO
Gas Test 3/10/2022 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 3/10/2022 SGSOV Approved LILIANA PORTILLO
Gas Test 3/17/2022 Approved LILIANA PORTILLO
Final 3/30/2022 OK to Issue CofO LILIANA PORTILLO
Service/Power Release 3/30/2022 Approved LILIANA PORTILLO