451 E 84TH PL 90003
Certificate Information: 451 E 84TH PL 90003
- Application / Permit
- 20010-10000-01548
- Plan Check / Job No.
- B20LA08396
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1-STORY ADU PER GCS 65852.2(E)(1)(B) 2 BEDROOM AND 2 BATHROOMS.
- Permit Issued
- Issued on 5/27/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/11/2020 | JESSE JIMENEZ |
| Corrections Issued | 5/12/2020 | JESSE JIMENEZ |
| Applicant returned to address corrections | 10/26/2020 | STARR CHEN |
| Applicant returned to address corrections | 3/18/2021 | AUNG SOE |
| Building Plans Picked Up | 3/22/2021 | APPLICANT |
| Plan Check Approved | 5/12/2021 | JESSE JIMENEZ |
| Issued | 5/27/2021 | APPLICANT |
| CofO in Progress | 3/31/2022 | LILIANA PORTILLO |
| Permit Finaled | 4/13/2022 | DEROLD HAUFF |
| CofO Issued | 4/13/2022 | DEROLD HAUFF |
| Permit Finaled | 4/13/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Certificate of Compliance | Cleared | 5/22/2020 | MAXFIELD VERMY |
| "Q" conditions | Cleared | 5/28/2020 | MAXFIELD VERMY |
| Address approval | Cleared | 5/28/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 5/28/2020 | JEANIE LAM |
| Sewer availability | Cleared | 5/28/2020 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 9/30/2020 | KURT CORRAL |
| Low Impact Development | Cleared | 10/6/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 10/16/2020 | JEANIE LAM |
| Highway dedication | Cleared | 2/16/2021 | JEANIE LAM |
| Trees in Parkway | Cleared | 4/27/2021 | JOHN KIM |
| Permit | Cleared | 5/4/2021 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Truong,, Phong Lap; Lic. No.: C70784 | 20754 TIMBERLINE LN WALNUT, CA 91789 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/11/2021 | Approved | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 8/11/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 8/18/2021 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Gas Test | 10/1/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 10/1/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Insulation | 10/1/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 10/1/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Sewer | 10/1/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Underground Mechanical | 10/1/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Insulation | 10/4/2021 | Partial Approval | EUGENE CASSIDY |
| Underground Mechanical | 10/4/2021 | Partial Approval | EUGENE CASSIDY |
| Insulation | 10/6/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 10/6/2021 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2021 | Partial Approval | ADAM ESCOTO |
| Insulation | 10/8/2021 | Partial Approval | ADAM ESCOTO |
| Footing/Foundation/Slab | 10/12/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 10/15/2021 | Partial Approval | CRAIG DAVIS |
| Footing/Foundation/Slab | 10/22/2021 | Approved | DANIEL GONZALEZ |
| BUILDING-Rough-Frame | 12/17/2021 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2021 | Approved | ANTHONY EGSON |
| Green Building Rough | 12/17/2021 | Corrections Issued | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 12/17/2021 | Corrections Issued | ANTHONY EGSON |
| Wood Frame | 12/17/2021 | Corrections Issued | ANTHONY EGSON |
| Interior/Exterior Lathing | 1/6/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 1/11/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 1/11/2022 | Approved | FREDDIE RIVERA |
| Green Building Rough | 1/11/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| HVAC-Rough | 1/11/2022 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 1/11/2022 | Approved | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 1/11/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| Shower Pan | 1/11/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 1/11/2022 | Approved | FREDDIE RIVERA |
| Wood Frame | 1/11/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 1/12/2022 | Approved | FREDDIE RIVERA |
| Green Building Rough | 1/12/2022 | Approved | FREDDIE RIVERA |
| Insulation | 1/19/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 1/24/2022 | Approved | LILIANA PORTILLO |
| Shower Pan | 1/24/2022 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 1/26/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 3/1/2022 | Approved | LILIANA PORTILLO |
| HVAC-Final | 3/1/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 3/1/2022 | Approved | LILIANA PORTILLO |
| Final | 3/4/2022 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 3/4/2022 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 3/4/2022 | SGSOV Not Ready | LILIANA PORTILLO |
| Smoke Detectors | 3/4/2022 | Approved | LILIANA PORTILLO |
| Gas Test | 3/10/2022 | Corrections Issued | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 3/10/2022 | SGSOV Approved | LILIANA PORTILLO |
| Gas Test | 3/17/2022 | Approved | LILIANA PORTILLO |
| Final | 3/30/2022 | OK to Issue CofO | LILIANA PORTILLO |
| Service/Power Release | 3/30/2022 | Approved | LILIANA PORTILLO |