2722 S FIGUEROA ST 1-157 90007

Certificate Information: 2722 S FIGUEROA ST 1-157 90007

Application / Permit
20010-10000-01526
Plan Check / Job No.
B20LA08239
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
NEW 7 STORY LOW-RISE 157 UNITS (11% = 18 VLI) TO INCLUDE 5 STORY TYPE IIIA APARTMENT OVER 1 STORY TYPE IA APARTMENT OVER 1 STORY TYPE IA MIXED USED RETAIL / GARAGE OVER 1 LEVEL TYPE IA SUBTERRANEAN PARKING PER 12.22.A.25 DENSITY BONUS WITH ADDITIONAL INCENTIVES PER CPC-2020-4714-CU-DB-SPR-RDP-HCA.
Permit Issued
Issued on 1/14/2022
Issuing Office
Metro
Current Status
CofO Issued on 10/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Plan Check Approved 12/29/2021 KEVIN MORALES
Issued 1/14/2022 APPLICANT
Building Plans Picked Up 1/18/2022 APPLICANT
TCO Issued (Expire Date: 05-08-2024) 11/10/2023 ADAM BURGESS
TCO Issued (Expire Date: 08-05-2024) 2/7/2024 ERNESTO CORRAL
TCO Issued (Expire Date: 01-21-2025) 7/25/2024 WINSTON DUNNING
CofO in Progress 10/31/2024 JAMES POWERS
CofO Issued 10/31/2024 RAFAEL ESPINOZA
Permit Finaled 10/31/2024 RAFAEL ESPINOZA

Permit Application Clearance Information

Address approval Cleared 7/30/2020 ELENA LOPEZ
Eng Process Fee Ord 176,300 Cleared 7/30/2020 ELENA LOPEZ
Driveway location Cleared 1/25/2021 MOHAMMAD HASAN
Driveway location Cleared 1/25/2021 MOHAMMAD HASAN
Methane Ordinance Cleared 5/12/2021 VIDAL GARCIA
Permit Cleared 5/27/2021 CELINA MORENO
Building over 36-ft Cleared 6/2/2021 CALOSHA APPROVED
Trees in Parkway Cleared 6/30/2021 JOHN KIM
Sewer availability Cleared 7/8/2021 JEANIE LAM
Highway dedication Cleared 7/13/2021 RENZ SORIANO
Encroachment in public way Cleared 7/14/2021 MSTAFA AL-MSARI
Hydrant and Access approval Cleared 7/14/2021 KURT CORRAL
Bicycle Parking Cleared 7/19/2021 MSTAFA AL-MSARI
Work Adjacent to Public Way Cleared 8/4/2021 BOK GOH
Miscellaneous Cleared 8/23/2021 RUBEN VASQUEZ
Miscellaneous Cleared 8/23/2021 RUBEN VASQUEZ
ZA Case Cleared 8/23/2021 RUBEN VASQUEZ
Fire Marshall Fire Life Safety Cleared 9/24/2021 VIDAL GARCIA
Green Code Cleared 11/5/2021 EUGENE BARBEAU
Low Impact Development Cleared 11/23/2021 ANDRES COVARRUBIAS
DAS Clearance Cleared 12/1/2021 EUGENE BARBEAU
Density Bonus 12.22.A.25 Cleared 12/22/2021 MARITESS GO
Roof/Waste drainage to street Cleared 12/22/2021 MATIAS FARFAN
Miscellaneous Cleared 12/28/2021 ANNA VIDAL
Miscellaneous Cleared 12/28/2021 ANNA VIDAL
Miscellaneous Cleared 12/28/2021 ANNA VIDAL
Miscellaneous Cleared 12/28/2021 ANNA VIDAL
Opn space landscape/Water mgmt Cleared 12/28/2021 ANNA VIDAL
Redevelopment Project Area Cleared 12/28/2021 DAVID URITA
Site Plan review Cleared 12/28/2021 ANNA VIDAL
ZI Cleared 12/28/2021 ANNA VIDAL
Excavation more than 5-ft deep Cleared 12/29/2021 CALOSHA APPROVED

Contact Information

Architect Antunovich,, Joseph Michael; Lic. No.: C8708 224 W HURON ST 7TH FL      CHICAGO, IL 606543981
Contractor M W Residential Socal Corp; Lic. No.: 1043221-B 12655 W 54TH DRIVE      ARVADA, CO 80002
Engineer Aden,, Mark D; Lic. No.: S4779 1314 S GRAND BLVD 2-359      SPOKANE, WA 99202
Engineer Atry,, Andrew James; Lic. No.: C84728 215 N WOODS AVE      FULLERTON, CA 92832

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/8/2022 Partial Inspection RUSSELL BONVOULOIR
Green Building Rough 3/10/2022 Not Ready for Inspection JAMES POWERS
METHANE-Rough 3/10/2022 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 3/10/2022 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 3/10/2022 Not Ready for Inspection JAMES POWERS
METHANE-Barrier 3/11/2022 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 3/11/2022 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 3/11/2022 Not Ready for Inspection JAMES POWERS
Green Building Rough 3/12/2022 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Rough 3/12/2022 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 3/12/2022 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 3/12/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 3/16/2022 Partial Approval JAMES POWERS
Deputy Shotcrete 3/16/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/21/2022 Conditional Approval NICK DANERI
Deputy Shotcrete 3/21/2022 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 3/22/2022 Partial Approval JAMES POWERS
Deputy Shotcrete 3/22/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/23/2022 Partial Approval JAMES POWERS
Deputy Shotcrete 3/23/2022 Partial Approval JAMES POWERS
Green Building Rough 3/23/2022 Not Ready for Inspection JAMES POWERS
METHANE-Rough 3/23/2022 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 3/23/2022 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 3/23/2022 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 3/24/2022 Partial Approval JAMES POWERS
Deputy Shotcrete 3/24/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/25/2022 Partial Approval JAMES POWERS
Deputy Shotcrete 3/25/2022 Partial Approval JAMES POWERS
Reinforced Masonry Frame 3/25/2022 Not Ready for Inspection JAMES POWERS
Green Building Rough 3/29/2022 Not Ready for Inspection NICK DANERI
METHANE-Rough 3/29/2022 Conditional Approval NICK DANERI
Reinforced Concrete Frame 3/29/2022 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 3/29/2022 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 4/1/2022 Conditional Approval RUSSELL BONVOULOIR
Deputy Shotcrete 4/5/2022 Partial Approval JAMES POWERS
Deputy Shotcrete 4/6/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 4/6/2022 Partial Approval JAMES POWERS
Deputy Shotcrete 4/7/2022 Partial Approval JAMES POWERS
Deputy Shotcrete 4/8/2022 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 4/8/2022 Partial Approval JAMES POWERS
Deputy Shotcrete 4/13/2022 Partial Approval JAMES POWERS
Deputy Shotcrete 4/14/2022 Partial Approval JAMES POWERS
Deputy Shotcrete 4/15/2022 Partial Approval JAMES POWERS
Deputy Shotcrete 4/18/2022 Conditional Approval RAFAEL ESPINOZA
Green Building Rough 4/18/2022 Approved RAFAEL ESPINOZA
METHANE-Rough 4/18/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 4/18/2022 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 4/18/2022 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 4/19/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 4/19/2022 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 4/19/2022 Partial Approval RAFAEL ESPINOZA
Deputy Pre-Stress Concrete 4/20/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 4/20/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Pre-Stress Concrete 4/21/2022 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 4/22/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 4/22/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 4/25/2022 Partial Approval JAMES POWERS
Deputy Shotcrete 4/25/2022 Partial Approval JAMES POWERS
METHANE-Rough 4/28/2022 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 4/28/2022 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 4/28/2022 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 4/29/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 4/29/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/2/2022 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/3/2022 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/4/2022 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/5/2022 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/6/2022 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/9/2022 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/10/2022 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/11/2022 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/12/2022 Partial Approval JAMES POWERS
METHANE-Rough 5/12/2022 Approved JAMES POWERS
Reinforced Concrete Frame 5/12/2022 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 5/12/2022 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 5/13/2022 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/16/2022 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/17/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/17/2022 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/18/2022 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/19/2022 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/23/2022 Conditional Approval ERNESTO CORRAL
Deputy Pre-Stress Concrete 5/24/2022 Conditional Approval ERNESTO CORRAL
Deputy Pre-Stress Concrete 5/25/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 5/25/2022 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 5/26/2022 Conditional Approval ERNESTO CORRAL
Deputy Pre-Stress Concrete 5/27/2022 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 6/21/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/22/2022 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 6/23/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/1/2022 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 7/5/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/5/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 7/11/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/21/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/22/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/25/2022 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 7/25/2022 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 7/26/2022 Conditional Approval ERNESTO CORRAL
Structural Steel Frame 7/27/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 7/28/2022 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 8/5/2022 Partial Approval JAMES POWERS
Special/Order Compliance 8/5/2022 Partial Inspection KATY RAMIREZ
Verify Sprinkler Sign Off 8/5/2022 Not Ready for Inspection JONATHAN QUACH
Deputy Steel/Welding 8/10/2022 Partial Approval JAMES POWERS
Deputy Shotcrete 8/11/2022 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 8/12/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/15/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/16/2022 Partial Approval JAMES POWERS
Deputy Shotcrete 8/16/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/17/2022 Partial Approval JAMES POWERS
Deputy Shotcrete 8/17/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/17/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/18/2022 Conditional Approval ERNESTO CORRAL
Verify Sprinkler Sign Off 9/7/2022 Off-Hour Fees Due
Wood Frame 9/7/2022 Off-Hour Fees Due
Deputy Reinf. Concrete 9/9/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 9/9/2022 Conditional Approval MICHAEL ROSENBERG
Structural Steel Frame 9/15/2022 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/19/2022 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/20/2022 Partial Approval JAMES POWERS
Drywall Nailing 9/23/2022 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 9/26/2022 Not Ready for Inspection JAMES POWERS
Wood Frame 9/26/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/28/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 10/3/2022 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 10/6/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/14/2022 Not Ready for Inspection RAFAEL ESPINOZA
Special/Order Compliance 10/14/2022 Not Ready for Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 10/17/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/21/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/27/2022 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/28/2022 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/8/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/14/2022 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 11/16/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/21/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/22/2022 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/23/2022 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/7/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/13/2022 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/16/2022 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/21/2022 Partial Approval JAMES POWERS
Insulation 12/22/2022 Not Ready for Inspection JAMES POWERS
Special/Order Compliance 12/29/2022 Not Ready for Inspection JAMES POWERS
Insulation 1/3/2023 Not Ready for Inspection JAMES POWERS
Insulation 1/9/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/11/2023 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 1/19/2023 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/23/2023 Partial Approval JAMES POWERS
Insulation 1/30/2023 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 1/30/2023 Not Ready for Inspection JAMES POWERS
Wood Frame 1/30/2023 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/31/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/2/2023 Partial Approval EDWIN GREGORYONA
Deputy Other (see comments) 2/6/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 2/6/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/6/2023 Partial Approval JAMES POWERS
Deputy Other (see comments) 2/8/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 2/8/2023 Partial Approval JAMES POWERS
Insulation 2/9/2023 Partial Approval JAMES POWERS
Insulation 2/10/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 2/13/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/15/2023 Partial Approval JAMES POWERS
Insulation 2/21/2023 Partial Approval JAMES POWERS
Deputy Other (see comments) 2/22/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 2/22/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 2/23/2023 Partial Approval JAMES POWERS
Insulation 2/23/2023 Partial Approval JAMES POWERS
Wood Frame 2/24/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/28/2023 Corrections Issued GREGORY POMISH
Insulation 2/28/2023 Not Ready for Inspection GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 3/1/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/6/2023 Partial Approval GREGORY POMISH
Deputy Wood Construction 3/8/2023 Conditional Approval GREGORY POMISH
Drywall Nailing 3/8/2023 Partial Approval GREGORY POMISH
Insulation 3/9/2023 Partial Approval JAMES POWERS
Interior/Exterior Lathing 3/10/2023 Not Ready for Inspection JAMES POWERS
Insulation 3/15/2023 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 3/17/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/21/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 3/23/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/23/2023 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/24/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 3/24/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/30/2023 Partial Approval JAMES POWERS
Interior/Exterior Lathing 3/31/2023 Partial Approval JAMES POWERS
Insulation 4/3/2023 Partial Approval GREGORY POMISH
Insulation 4/4/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/5/2023 Not Ready for Inspection JAMES POWERS
Insulation 4/6/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/12/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/13/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/14/2023 Partial Approval JAMES POWERS
Drywall Nailing 4/18/2023 Partial Approval EDWIN GREGORYONA
Insulation 4/20/2023 Order to Comply Issued GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 4/21/2023 Partial Approval LARRY ARNICK
Insulation 4/21/2023 Partial Approval LARRY ARNICK
Drywall Nailing 4/25/2023 Partial Approval JAMES POWERS
Interior/Exterior Lathing 4/26/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/27/2023 Partial Approval JAMES POWERS
Insulation 5/2/2023 Partial Approval JAMES POWERS
Light Gage Steel Frame 5/3/2023 Partial Approval JAMES POWERS
Insulation 5/4/2023 Partial Approval JAMES POWERS
Insulation 5/6/2023 Off-Hour Fees Due
Wall Anchors 5/6/2023 Off-Hour Fees Due
Insulation 5/8/2023 Off-Hour Fees Due
Insulation 5/8/2023 Partial Approval LARRY ARNICK
Wall Anchors 5/8/2023 Off-Hour Fees Due
Wall Anchors 5/8/2023 Partial Approval LARRY ARNICK
Insulation 5/9/2023 Not Ready for Inspection JAMES POWERS
Wall Anchors 5/9/2023 Not Ready for Inspection JAMES POWERS
Insulation 5/12/2023 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 5/15/2023 Partial Approval GREGORY POMISH
Interior/Exterior Lathing 5/15/2023 Not Ready for Inspection GREGORY POMISH
Insulation 5/19/2023 Partial Approval JAMES POWERS
Interior/Exterior Lathing 5/22/2023 Partial Approval JAMES POWERS
Drywall Nailing 5/24/2023 Partial Approval GREGORY POMISH
Interior/Exterior Lathing 5/26/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 5/30/2023 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 5/30/2023 Partial Approval RAFAEL ESPINOZA
Insulation 6/1/2023 Partial Approval LARRY ARNICK
Drywall Nailing 6/2/2023 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 6/2/2023 Not Ready for Inspection LARRY ARNICK
Wood Frame 6/2/2023 Corrections Issued LARRY ARNICK
Insulation 6/5/2023 Partial Approval JAMES POWERS
Wall Anchors 6/7/2023 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/13/2023 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 6/15/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/20/2023 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 6/20/2023 Partial Approval JAMES POWERS
Drywall Nailing 6/22/2023 Partial Approval ALAN MORELOS
Light Gage Steel Frame 6/27/2023 Partial Approval JAMES POWERS
Interior/Exterior Lathing 7/6/2023 Partial Approval JAMES POWERS
Drywall Nailing 7/12/2023 Not Ready for Inspection JAMES POWERS
Insulation 7/12/2023 Partial Approval JAMES POWERS
Insulation 7/13/2023 Not Ready for Inspection EDWIN GREGORYONA
Drywall Nailing 7/19/2023 Partial Approval ALAN MORELOS
Wood Frame 7/20/2023 Not Ready for Inspection JAMES POWERS
Drywall Nailing 7/25/2023 Partial Approval JAMES POWERS
Wall Anchors 7/28/2023 Partial Approval JAMES POWERS
Drywall Nailing 8/16/2023 Partial Approval ALAN MORELOS
Final 8/25/2023 Not Ready for Inspection ALAN MORELOS
Special/Order Compliance 8/28/2023 Approved ALAN MORELOS
Drywall Nailing 9/7/2023 Not Ready for Inspection LARRY ARNICK
Final 9/7/2023 Partial Inspection LARRY ARNICK
Footing/Foundation/Slab 9/7/2023 Not Ready for Inspection LARRY ARNICK
Green Building Final 9/7/2023 Not Ready for Inspection LARRY ARNICK
METHANE-Barrier 9/7/2023 Not Ready for Inspection LARRY ARNICK
METHANE-Subgrade 9/7/2023 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 9/7/2023 Not Ready for Inspection LARRY ARNICK
SGSOV-Seismic Gas S/O Valve 9/7/2023 SGSOV Not Ready LARRY ARNICK
Smoke Detectors 9/7/2023 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 9/7/2023 Not Ready for Inspection LARRY ARNICK
Wood Frame 9/7/2023 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 10/13/2023 Approved JAMES POWERS
Final 10/13/2023 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 10/13/2023 Partial Approval JAMES POWERS
Green Building Final 10/13/2023 Approved JAMES POWERS
METHANE-Barrier 10/13/2023 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 10/13/2023 Not Ready for Inspection JAMES POWERS
Pre-Inspection 10/13/2023 Approved JAMES POWERS
Reinforced Concrete Frame 10/13/2023 Partial Approval JAMES POWERS
SGSOV-Seismic Gas S/O Valve 10/13/2023 SGSOV Approved JAMES POWERS
Smoke Detectors 10/13/2023 Approved JAMES POWERS
Verify Sprinkler Sign Off 10/13/2023 Not Ready for Inspection JAMES POWERS
Wood Frame 10/13/2023 Partial Approval JAMES POWERS
Pre-Inspection 10/16/2023 Not Ready for Inspection JAMES POWERS
Final 10/19/2023 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 10/19/2023 Partial Approval JAMES POWERS
METHANE-Barrier 10/19/2023 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 10/19/2023 Approved JAMES POWERS
Reinforced Concrete Frame 10/19/2023 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 10/19/2023 Not Ready for Inspection JAMES POWERS
Wood Frame 10/19/2023 Partial Approval JAMES POWERS
Final 10/30/2023 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 10/30/2023 Partial Approval JAMES POWERS
METHANE-Barrier 10/30/2023 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 10/30/2023 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 10/30/2023 Not Ready for Inspection JAMES POWERS
Wood Frame 10/30/2023 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 11/3/2023 Not Ready for Inspection JAMES POWERS
Wood Frame 11/3/2023 Partial Approval JAMES POWERS
Structural Steel Frame 11/7/2023 Approved JAMES POWERS
Verify Sprinkler Sign Off 11/7/2023 Approved JAMES POWERS
Wood Frame 11/7/2023 Partial Approval JAMES POWERS
Final 1/2/2024 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 1/2/2024 Approved JAMES POWERS
METHANE-Barrier 1/2/2024 Approved JAMES POWERS
Reinforced Concrete Frame 1/2/2024 Approved JAMES POWERS
Wood Frame 1/2/2024 Approved JAMES POWERS
Final 3/28/2024 Not Ready for Inspection JAMES POWERS
Final 6/3/2024 Not Ready for Inspection JAMES POWERS
Special/Order Compliance 7/9/2024 Not Ready for Inspection JAMES POWERS
Final 10/31/2024 OK to Issue CofO JAMES POWERS