1402 N ALEXANDRIA AVE 90027
Certificate Information: 1402 N ALEXANDRIA AVE 90027
- Application / Permit
- 20010-10000-01522
- Plan Check / Job No.
- B20LA08216
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 32'x37'6" 3-story single family dwelling at front of lot.
- Permit Issued
- Issued on 8/16/2022
- Issuing Office
- Metro
- Current Status
- Issued on 8/16/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/11/2020 | CRYSTEL MAALOUF |
| Corrections Issued | 6/24/2020 | CRYSTEL MAALOUF |
| Quality Review Completed | 7/21/2020 | TU HUA |
| Applicant returned to address corrections | 9/16/2020 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 12/14/2020 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 1/12/2021 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 2/26/2021 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 5/12/2021 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 6/23/2021 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 6/24/2021 | CRYSTEL MAALOUF |
| Plan Check Approved | 10/20/2021 | CRYSTEL MAALOUF |
| Issued | 8/16/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/23/2020 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 10/28/2020 | ELAINE LEI |
| Sewer availability | Cleared | 10/29/2020 | ELAINE LEI |
| Trees in Parkway | Cleared | 11/19/2020 | JOHN KIM |
| Hydrant and Access approval | Cleared | 12/7/2020 | KURT CORRAL |
| Low Impact Development | Cleared | 4/27/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 5/18/2021 | WALLIE JONG |
| Frnt yard landscape/Water mgmt | Cleared | 6/15/2021 | DANIEL CORONADO |
| Frnt yard landscape/Water mgmt | Cleared | 8/25/2021 | DANIEL CORONADO |
| Permit | Cleared | 8/25/2021 | THAN WIN |
| Green Code | Cleared | 9/1/2021 | CRYSTEL MAALOUF |
Contact Information
| Contractor | Emerald Builders And Developers; Lic. No.: 1068007-B | 1412 W 22ND STREET LOS ANGELES, CA 90007 |
| Engineer | Kim,, Eui S; Lic. No.: S5138 | 37325 8TH AVE S FEDERAL WAY, WA 98003 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 10/5/2022 | Approved | JOAQUIN GREENOUGH |
| Underground Mechanical | 10/19/2022 | Partial Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 11/17/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 12/5/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 12/13/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 12/16/2022 | Approved | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2023 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2023 | Partial Approval | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 12/21/2023 | Approved | STUART CHAPMAN |
| Deputy Wood Construction | 3/1/2024 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2024 | Corrections Issued | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2024 | Approved | ROY SPAULDING |
| ELECTRICAL-Rough | 3/15/2024 | Approved | ROY SPAULDING |
| HVAC-Rough | 3/15/2024 | Corrections Issued | ROY SPAULDING |
| BUILDING-Rough-Frame | 6/20/2024 | Not Ready for Inspection | ROY SPAULDING |
| Green Building Rough | 6/20/2024 | Not Ready for Inspection | ROY SPAULDING |
| HVAC-Rough | 6/20/2024 | Approved | ROY SPAULDING |
| Verify Sprinkler Sign Off | 6/20/2024 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 7/1/2024 | Corrections Issued | BRIAN SULLIVAN |
| Green Building Rough | 7/1/2024 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 7/16/2024 | Not Ready for Inspection | ROY SPAULDING |
| ELECTRICAL-Rough | 7/16/2024 | Approved | ROY SPAULDING |
| HVAC-Rough | 7/16/2024 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 7/16/2024 | Approved | ROY SPAULDING |
| Insulation | 7/22/2024 | Approved | ROY SPAULDING |
| Drywall Nailing | 8/14/2024 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 8/19/2024 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 9/17/2024 | Partial Approval | BRIAN SULLIVAN |