6017 N LAUREL CANYON BLVD 91606
Certificate Information: 6017 N LAUREL CANYON BLVD 91606
- Application / Permit
- 20010-10000-01505
- Plan Check / Job No.
- B20LA08116
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (18) School - elementary or high
- Work Description
- PROPOSED 3-STORY SCHOOL. BUILDING IS LOCATED ENTIRELY IN C2-1VL ZONE ONLY. SCHOOL IS NOT ALLOWED IN P-1VL ZONE, ONLY ATTACHED PARKING STRUCTURE IS ALLOWED. PROPOSED USED IS 4TH TO 8TH GRADES.
- Permit Issued
- Issued on 6/21/2022
- Issuing Office
- Metro
- Current Status
- Issued on 6/21/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/28/2020 | ERWIN PASCUA |
| Corrections Issued | 6/10/2020 | ERWIN PASCUA |
| Quality Review Completed | 6/16/2020 | CHARLES CHANG |
| Building Plans Picked Up | 6/18/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 6/25/2020 | APPLICANT |
| Applicant returned to address corrections | 1/8/2021 | ERWIN PASCUA |
| Applicant returned to address corrections | 4/29/2021 | ERWIN PASCUA |
| Applicant returned to address corrections | 5/5/2021 | ERWIN PASCUA |
| Applicant returned to address corrections | 5/13/2021 | ERWIN PASCUA |
| Applicant returned to address corrections | 10/22/2021 | ERWIN PASCUA |
| Applicant returned to address corrections | 12/10/2021 | ERWIN PASCUA |
| Applicant returned to address corrections | 1/12/2022 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 1/31/2022 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 3/17/2022 | FARSHAD ALIMOHAMADI |
| Green Plans Picked Up | 5/12/2022 | APPLICANT |
| Plan Check Approved | 6/16/2022 | FARSHAD ALIMOHAMADI |
| Issued | 6/21/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/7/2020 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 8/14/2020 | MARKOS PEREZ-BRAN |
| Work Adjacent to Public Way | Cleared | 6/1/2021 | GABRIEL ROBLES |
| Redevelopment Project Area | Cleared | 6/10/2021 | GRACIELA ACOSTA |
| ZI | Cleared | 6/10/2021 | GRACIELA ACOSTA |
| Sewer availability | Cleared | 6/17/2021 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 6/23/2021 | OSCAR CASTRO |
| Highway dedication | Cleared | 6/24/2021 | GABRIEL ROBLES |
| Permit | Cleared | 6/24/2021 | GABRIEL ROBLES |
| "Q" conditions | Cleared | 7/1/2021 | TERRI OSBORNE |
| Trees in Parkway | Cleared | 7/8/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 8/9/2021 | MATTHEW CRAIG |
| DAS Clearance | Cleared | 10/20/2021 | ERWIN PASCUA |
| Green Code | Cleared | 1/11/2022 | AARON COSTA |
| Low Impact Development | Cleared | 3/13/2022 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 3/17/2022 | ABDULLAH SADOZAI |
| Fire Marshall Fire Life Safety | Cleared | 5/31/2022 | OSCAR SALGADO JR |
| Building over 36-ft | Cleared | 6/16/2022 | CALOSHA APPROVED |
Contact Information
| Architect | Mashihi,, Jacques; Lic. No.: C15922 | 10556 ASHTON AVENUE LOS ANGELES, CA 90024 |
| Contractor | Owner-Builder | , |
| Engineer | Minas,, Caro Jolfaie; Lic. No.: GE601 | 4742 SAN FERNANDO RD GLENDALE, CA 91204 |
| Engineer | Naim,, Soleiman Israel; Lic. No.: S2454 | 403 21ST ST SANTA MONICA, CA 90402 |
Inspector Information
| DEANDRE HOFFMAN, (818) 374-1182 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/14/2023 | Approved | JOHN KITCKO |
| Footing/Foundation/Slab | 7/7/2023 | No Access for Inspection | ROBERT DAVIS |
| Excavation/Setback/Form/Re-Bar | 7/13/2023 | Not Ready for Inspection | JOHN KITCKO |
| Excavation/Setback/Form/Re-Bar | 7/19/2023 | Not Ready for Inspection | JOHN KITCKO |
| Excavation/Setback/Form/Re-Bar | 7/27/2023 | Partial Inspection | JOHN KITCKO |
| Footing/Foundation/Slab | 7/27/2023 | Conditional Approval | JOHN KITCKO |
| Green Building Rough | 10/11/2023 | Not Ready for Inspection | JOHN KITCKO |
| Reinforced Masonry Frame | 10/11/2023 | Corrections Issued | JOHN KITCKO |
| Verify Sprinkler Sign Off | 10/11/2023 | Not Ready for Inspection | JOHN KITCKO |
| Masonry Wall/Backfill | 10/13/2023 | Corrections Issued | ROBERT DAVIS |
| Green Building Rough | 10/17/2023 | Not Ready for Inspection | JOHN KITCKO |
| Reinforced Masonry Frame | 10/17/2023 | Partial Approval | JOHN KITCKO |
| Verify Sprinkler Sign Off | 10/17/2023 | Not Ready for Inspection | JOHN KITCKO |
| Deputy Reinf. Masonry | 10/19/2023 | Conditional Approval | JOHN KITCKO |
| Deputy Reinf. Masonry | 10/31/2023 | Approved | JOHN KITCKO |
| Masonry Wall/Backfill | 11/1/2023 | Partial Approval | JOHN KITCKO |
| Deputy Reinf. Masonry | 11/3/2023 | Conditional Approval | JOHN KITCKO |
| Deputy Reinf. Masonry | 11/15/2023 | Conditional Approval | JOHN KITCKO |
| Masonry Wall/Backfill | 11/15/2023 | Not Ready for Inspection | JOHN KITCKO |
| Masonry Wall/Backfill | 11/17/2023 | Partial Approval | ROBERT DAVIS |
| Footing/Foundation/Slab | 12/8/2023 | Corrections Issued | ANDREW DORSO |
| Footing/Foundation/Slab | 12/12/2023 | Partial Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 12/14/2023 | Conditional Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 3/12/2024 | Conditional Approval | JOHN KITCKO |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2024 | Not Ready for Inspection | JOHN KITCKO |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2024 | Partial Approval | JOHN KITCKO |
| Deputy Wood Construction | 10/9/2024 | Conditional Approval | JOHN KITCKO |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2024 | Corrections Issued | JOHN KITCKO |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2024 | Corrections Issued | JOHN KITCKO |
| Deputy Wood Construction | 12/17/2024 | Conditional Approval | JOHN KITCKO |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2024 | Partial Approval | JOHN KITCKO |
| Green Building Rough | 1/29/2025 | Not Ready for Inspection | JOHN KITCKO |
| Verify Sprinkler Sign Off | 1/29/2025 | Not Ready for Inspection | JOHN KITCKO |
| Wood Frame | 1/29/2025 | Partial Approval | JOHN KITCKO |
| Interior/Exterior Lathing | 2/13/2025 | Partial Inspection | JOHN KITCKO |
| Drywall Nailing | 4/2/2025 | Partial Inspection | JOHN KITCKO |
| Green Building Rough | 4/2/2025 | Not Ready for Inspection | JOHN KITCKO |
| Insulation | 4/7/2025 | Partial Approval | JOHN KITCKO |
| Drywall Nailing | 4/11/2025 | Partial Approval | JOHN KITCKO |
| Green Building Rough | 4/11/2025 | Not Ready for Inspection | JOHN KITCKO |
| Insulation | 7/24/2025 | Conditional Approval | JOHN KITCKO |
| Wall Anchors | 8/1/2025 | Partial Approval | JOHN KITCKO |
| Wood Frame | 8/1/2025 | Partial Approval | JOHN KITCKO |
| Insulation | 8/8/2025 | Partial Approval | JOHN KITCKO |
| Drywall Nailing | 8/12/2025 | Not Ready for Inspection | JOHN KITCKO |
| Green Building Rough | 8/12/2025 | Partial Inspection | JOHN KITCKO |
| Drywall Nailing | 8/18/2025 | Partial Inspection | BRIAN KELLY |
| Green Building Rough | 8/18/2025 | Partial Inspection | BRIAN KELLY |
| T-Bar Ceiling | 1/14/2026 | Partial Inspection | JOHN KITCKO |
| Drywall Nailing | 3/26/2026 | Partial Inspection | DEANDRE HOFFMAN |
| Final | 3/26/2026 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 3/26/2026 | Approved | DEANDRE HOFFMAN |
| Green Building Final | 3/26/2026 | Partial Inspection | DEANDRE HOFFMAN |
| Green Building Rough | 3/26/2026 | Approved | DEANDRE HOFFMAN |
| Reinforced Masonry Frame | 3/26/2026 | Partial Inspection | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 3/26/2026 | SGSOV Not Ready | DEANDRE HOFFMAN |
| Smoke Detectors | 3/26/2026 | Approved | DEANDRE HOFFMAN |
| Structural Steel Frame | 3/26/2026 | Partial Inspection | DEANDRE HOFFMAN |
| Verify Sprinkler Sign Off | 3/26/2026 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Wood Frame | 3/26/2026 | Partial Inspection | DEANDRE HOFFMAN |