527 W 119TH ST 90044

Certificate Information: 527 W 119TH ST 90044

Application / Permit
20010-10000-01499
Plan Check / Job No.
B20LA08068
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONSTRUCT 1200 SQ FT ACCESSORY DWELLING PER ORDINANCE PER LAMC 12.22 A 33 (c)&(d).
Permit Issued
Issued on 8/6/2021
Issuing Office
Current Status
CofO Issued on 7/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/13/2020 APPLICANT
Assigned to Plan Check Engineer 5/13/2020 RAHEL BEYENE
Corrections Issued 5/27/2020 RAHEL BEYENE
Quality Review Completed 7/14/2020 FELIX FIGUEROA
Applicant returned to address corrections 10/8/2020 ADAM HEGAZI
Applicant returned to address corrections 12/9/2020 GEORGE ALVAREZ
Applicant returned to address corrections 2/26/2021 LUKE GONZALES
Applicant returned to address corrections 4/7/2021 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 7/20/2021 SINA KHOSRAVI
Applicant returned to address corrections 8/3/2021 ZAW HAN
Plan Check Approved 8/5/2021 ZAW HAN
Issued 8/6/2021 APPLICANT
Building Plans Picked Up 8/13/2021 APPLICANT
CofO in Progress 7/17/2024 JAMES CHAVEZ
Permit Finaled 7/17/2024 ANSON MAGLASANG
CofO Issued 7/17/2024 ANSON MAGLASANG
Permit Finaled 7/17/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 9/4/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 9/8/2020 CECILIO NAVARRO
Sewer availability Cleared 9/8/2020 CECILIO NAVARRO
Hydrant and Access approval Cleared 12/1/2020 MATTHEW CRAIG
Low Impact Development Cleared 5/26/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 8/4/2021 CECILIO NAVARRO

Contact Information

Architect , ; Lic. No.: C34210 P.O. BOX 55401      SHERMAN OAKS, CA 91413
Contractor Owner-Builder       ,

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/4/2022 Corrections Issued EUGENE CASSIDY
METHANE-Barrier 4/4/2022 Approved EUGENE CASSIDY
METHANE-Subgrade 4/4/2022 Approved EUGENE CASSIDY
Footing/Foundation/Slab 4/14/2022 Approved JOHN KLARIN
BUILDING-Rough-Frame 5/6/2022 Partial Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 5/6/2022 Partial Approval ALIZAH MAYAGOITIA
Sewer 5/6/2022 Approved ALIZAH MAYAGOITIA
Underground Mechanical 5/6/2022 Approved ALIZAH MAYAGOITIA
Insulation 5/17/2022 Partial Approval ALIZAH MAYAGOITIA
ELECTRICAL-Rough 7/7/2022 Partial Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 7/11/2022 Corrections Issued ANSON MAGLASANG
Green Building Rough 7/11/2022 Not Ready for Inspection ANSON MAGLASANG
MERV13>=Rough 7/11/2022 Not Ready for Inspection ANSON MAGLASANG
METHANE-Rough 7/11/2022 Not Ready for Inspection ANSON MAGLASANG
Verify Sprinkler Sign Off 7/11/2022 Not Ready for Inspection ANSON MAGLASANG
BUILDING-Rough-Frame 7/14/2022 Corrections Issued JOHN KLARIN
Green Building Rough 7/14/2022 Not Ready for Inspection JOHN KLARIN
MERV13>=Rough 7/14/2022 Not Ready for Inspection JOHN KLARIN
METHANE-Rough 7/14/2022 Not Ready for Inspection JOHN KLARIN
Verify Sprinkler Sign Off 7/14/2022 Not Ready for Inspection JOHN KLARIN
BUILDING-Rough-Frame 7/26/2022 Approved JOHN KLARIN
Green Building Rough 7/26/2022 Approved JOHN KLARIN
MERV13>=Rough 7/26/2022 Approved JOHN KLARIN
METHANE-Rough 7/26/2022 Approved JOHN KLARIN
Verify Sprinkler Sign Off 7/26/2022 Approved JOHN KLARIN
Interior/Exterior Lathing 7/28/2022 Approved JOHN KLARIN
Insulation 8/1/2022 Corrections Issued EUGENE CASSIDY
Insulation 8/2/2022 Approved JOHN KLARIN
Deputy Other (see comments) 8/3/2022 Approved JOHN KLARIN
Drywall Nailing 8/5/2022 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 8/16/2022 Approved JOHN KLARIN
ELECTRICAL-Rough 9/7/2022 Partial Approval EUGENE CASSIDY
Final 10/7/2022 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 10/7/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
MERV13>=Final 10/7/2022 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 10/7/2022 SGSOV Not Ready ALIZAH MAYAGOITIA
Service/Power Release 10/7/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 10/7/2022 Approved ALIZAH MAYAGOITIA
Green Building Final 6/16/2023 Corrections Issued JOHN KLARIN
Final 2/14/2024 Corrections Issued EUGENE CASSIDY
Green Building Final 2/14/2024 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 2/14/2024 SGSOV Not Ready EUGENE CASSIDY
Service/Power Release 2/14/2024 Not Ready for Inspection EUGENE CASSIDY
Final 6/17/2024 Corrections Issued BEN MOLSTAD
Green Building Final 6/17/2024 Approved BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 6/17/2024 SGSOV Not Ready BEN MOLSTAD
Service/Power Release 6/17/2024 Not Ready for Inspection BEN MOLSTAD
Final 7/8/2024 Conditional Approval JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 7/8/2024 SGSOV Approved JAMES CHAVEZ
Service/Power Release 7/8/2024 Approved JAMES CHAVEZ