6463-6465 N CALHOUN AVE 91401
Certificate Information: 6463-6465 N CALHOUN AVE 91401
- Application / Permit
- 20010-10000-01483
- Plan Check / Job No.
- B20LA07986
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2 STORY DUPLEX AT REAR
- Permit Issued
- Issued on 9/1/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/3/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/22/2020 | ZAW HAN |
| Corrections Issued | 6/9/2020 | ZAW HAN |
| Quality Review Completed | 6/18/2020 | HERNAN ARREOLA |
| Green Plans Picked Up | 8/11/2020 | APPLICANT |
| Applicant returned to address corrections | 8/21/2020 | ZAW HAN |
| Plan Check Approved | 8/26/2020 | ZAW HAN |
| Issued | 9/1/2020 | APPLICANT |
| CofO in Progress | 6/18/2021 | MICHAEL TEMPLE |
| CofO Issued | 7/3/2021 | MICHAEL SMITH |
| Permit Finaled | 7/3/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 7/15/2020 | GILBERT URREA |
| "Q" conditions | Cleared | 7/17/2020 | RUBEN VASQUEZ |
| CPC | Cleared | 7/17/2020 | RUBEN VASQUEZ |
| Frnt yard landscape/Water mgmt | Cleared | 7/17/2020 | RUBEN VASQUEZ |
| Address approval | Cleared | 7/22/2020 | GUILLERMO PETRA |
| Address approval | Cleared | 7/22/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 7/22/2020 | GUILLERMO PETRA |
| Permit | Cleared | 7/22/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 7/22/2020 | GUILLERMO PETRA |
| Low Impact Development | Cleared | 8/4/2020 | MARTIN FRAGOSO |
| Green Code | Cleared | 8/11/2020 | KHEDER ALRAZAA |
| Roof/Waste drainage to street | Cleared | 8/12/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | So Cal Construction Enterprises Inc; Lic. No.: 832488-B | P O BOX 96 SAN GABRIEL, CA 91778 |
| Engineer | Evangelista,, Gil Viernes; Lic. No.: S2422 | 749 N FEATHERWOOD DR DIAMOND BAR, CA 91765 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/3/2020 | Partial Approval | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 9/11/2020 | Corrections Issued | DANIEL ORRANTE |
| Excavation/Setback/Form/Re-Bar | 9/17/2020 | Conditional Approval | MISAEL ESPARZA |
| Underground Mechanical | 9/17/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2020 | Approved | MATTHEW NELSON |
| Underground Mechanical | 10/21/2020 | Not Ready for Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2020 | Conditional Approval | THOMAS FINNILA |
| Underground Mechanical | 11/2/2020 | No Access for Inspection | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 11/20/2020 | Approved | WILLIAM KUEHN |
| Green Building Rough | 11/20/2020 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 11/20/2020 | Partial Inspection | WILLIAM KUEHN |
| Rough-Elec/Plmb/HVAC | 11/20/2020 | Approved | WILLIAM KUEHN |
| Verify Sprinkler Sign Off | 11/20/2020 | Approved | WILLIAM KUEHN |
| Drywall Nailing | 12/1/2020 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 12/18/2020 | Approved | JOHN HAYES |
| Shower Pan | 12/18/2020 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 12/22/2020 | Approved | DAVID MATSON |
| Sewer | 1/25/2021 | Approved | DANIEL ORRANTE |
| Underground Mechanical | 1/25/2021 | Approved | DANIEL ORRANTE |
| Final | 2/11/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 2/11/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Final | 2/11/2021 | Not Ready for Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 2/11/2021 | SGSOV Not Ready | MATTHEW NELSON |
| Service/Power Release | 2/11/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Smoke Detectors | 2/11/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Special/Order Compliance | 2/11/2021 | Approved | DAVID MATSON |
| Final | 6/7/2021 | Corrections Issued | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 6/7/2021 | Approved | MICHAEL TEMPLE |
| Green Building Final | 6/7/2021 | Corrections Issued | MICHAEL TEMPLE |
| SGSOV-Seismic Gas S/O Valve | 6/7/2021 | SGSOV Not Ready | MICHAEL TEMPLE |
| Service/Power Release | 6/7/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| Smoke Detectors | 6/7/2021 | Approved | MICHAEL TEMPLE |
| Final | 6/14/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| Green Building Final | 6/14/2021 | Approved | MICHAEL TEMPLE |
| SGSOV-Seismic Gas S/O Valve | 6/14/2021 | SGSOV Approved | MICHAEL TEMPLE |
| Service/Power Release | 6/14/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| Final | 6/17/2021 | OK to Issue CofO | MICHAEL TEMPLE |
| Service/Power Release | 6/17/2021 | Approved | MICHAEL TEMPLE |