1501 S FAIRFAX AVE UNIT B 90019

Certificate Information: 1501 S FAIRFAX AVE UNIT B 90019

Application / Permit
20010-10000-01422
Plan Check / Job No.
B20LA07584
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2 OF 4: UNIT B, Building 2 of 4 CONSTRUCTION OF (4) NEW SMALL LOT SUBDIVISION SINGLE FAMILY DWELLINGS
Permit Issued
Issued on 11/15/2021
Issuing Office
Current Status
CofO Issued on 8/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/27/2020 APPLICANT
Assigned to Plan Check Engineer 5/22/2020 JOHNNY WU
Corrections Issued 6/4/2020 JOHNNY WU
Quality Review Completed 6/5/2020 LAWRENCE QUIRANTE
Green Plans Picked Up 9/18/2020 APPLICANT
Applicant returned to address corrections 11/6/2020 JOHNNY WU
Applicant returned to address corrections 11/12/2020 JOHNNY WU
Applicant returned to address corrections 12/11/2020 JOHNNY WU
Applicant returned to address corrections 12/16/2020 JOHNNY WU
Applicant returned to address corrections 4/9/2021 JOHNNY WU
Applicant returned to address corrections 4/12/2021 JOHNNY WU
Applicant returned to address corrections 4/15/2021 JOHNNY WU
Applicant returned to address corrections 5/19/2021 JOHNNY WU
Plan Check Approved 6/21/2021 JOHNNY WU
Issued 11/15/2021 APPLICANT
Building Plans Picked Up 11/19/2021 APPLICANT
Refund in Progress 9/9/2024 SELENIA GARCIA
Refund Closed 9/9/2024 SELENIA GARCIA
Issued 9/9/2024 SELENIA GARCIA
CofO in Progress 7/24/2025 NICHOLAS LOPEZ
Permit Finaled 8/1/2025 DEROLD HAUFF
Permit Finaled 8/1/2025 DEROLD HAUFF
CofO Issued 8/1/2025 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 9/16/2020 NEGAR NEJAD
Address approval Cleared 10/22/2020 RENZ SORIANO
Address approval Cleared 10/22/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 10/22/2020 RENZ SORIANO
Permit Cleared 10/22/2020 RENZ SORIANO
Highway dedication Cleared 11/9/2020 RENZ SORIANO
Sewer availability Cleared 11/19/2020 RENZ SORIANO
"Q" conditions Cleared 1/21/2021 MARITZA PRZEKOP
ZA Case Cleared 1/21/2021 MARITZA PRZEKOP
ZA Case Cleared 2/24/2021 TERRI OSBORNE
ZA Case Cleared 2/24/2021 TERRI OSBORNE
Trees in Parkway Cleared 3/8/2021 JOHN KIM
Abandoned oil well approval Cleared 4/19/2021 KURT CORRAL
Hydrant and Access approval Cleared 4/19/2021 KURT CORRAL
Low Impact Development Cleared 4/30/2021 IDA MEISAMI-FARD
Disturb/Remove Protected Trees Cleared 5/20/2021 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 5/20/2021 ROSA SILVA
Miscellaneous Cleared 6/2/2021 ARMEN MEHRABIAN

Contact Information

Architect Dewitt,, Justin Jeffrey; Lic. No.: C30879 312 W. 5TH ST. #1111      LOS ANGELES, CA 90013
Contractor Cornerstone Construction And Design; Lic. No.: 775449-B 4910 MT ROYAL DRIVE      LOS ANGELES, CA 90041
Engineer Esperanza,, Feldronio Juan; Lic. No.: C55246 2024 FEDERAL AVE      COSTA MESA, CA 92627
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Subgrade 2/28/2022 Not Ready for Inspection STUART CHAPMAN
Underground Mechanical 2/28/2022 Corrections Issued STUART CHAPMAN
METHANE-Rough 3/2/2022 No Access for Inspection CRAIG DAVIS
METHANE-Subgrade 3/3/2022 Corrections Issued CRAIG DAVIS
METHANE-Subgrade 3/4/2022 Approved CRAIG DAVIS
Footing/Foundation/Slab 3/10/2022 Corrections Issued ALEJANDRO DE ARTOLA
METHANE-Rough 3/10/2022 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 3/10/2022 Approved ALEJANDRO DE ARTOLA
METHANE-Subgrade 3/18/2022 Partial Approval ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 4/12/2022 Corrections Issued ALEJANDRO DE ARTOLA
METHANE-Barrier 4/12/2022 Corrections Issued ALEJANDRO DE ARTOLA
METHANE-Subgrade 4/12/2022 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 4/15/2022 Corrections Issued SCOTT FINNILA
METHANE-Barrier 4/15/2022 Approved SCOTT FINNILA
METHANE-Subgrade 4/15/2022 Approved SCOTT FINNILA
Footing/Foundation/Slab 4/20/2022 Partial Approval ALEJANDRO DE ARTOLA
Deputy Reinf. Concrete 4/22/2022 Partial Approval SCOTT FINNILA
Special/Order Compliance 5/13/2022 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 5/16/2022 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/16/2022 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 5/17/2022 Partial Approval ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 5/17/2022 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 6/23/2022 Partial Approval ALEJANDRO DE ARTOLA
Wood Frame 7/5/2022 Conditional Approval SCOTT FINNILA
Drywall Nailing 7/8/2022 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/11/2022 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 7/13/2022 Partial Approval ALEJANDRO DE ARTOLA
Wood Frame 8/15/2022 Partial Approval STUART CHAPMAN
Wood Frame 8/25/2022 Partial Approval STUART CHAPMAN
Drywall Nailing 8/30/2022 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 9/2/2022 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 9/22/2022 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 9/29/2022 Partial Approval SCOTT FINNILA
Wood Frame 9/29/2022 Partial Inspection SCOTT FINNILA
Masonry Wall/Backfill 10/24/2022 Corrections Issued ALEJANDRO DE ARTOLA
Wood Frame 11/9/2022 Approved ALEJANDRO DE ARTOLA
Wood Frame 11/15/2022 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/21/2022 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/29/2022 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 4/26/2023 Corrections Issued ALIZAH MAYAGOITIA
ELECTRICAL-Rough 5/3/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 5/3/2023 Corrections Issued ALIZAH MAYAGOITIA
Wood Frame 5/15/2023 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 5/23/2023 Conditional Approval ALIZAH MAYAGOITIA
HVAC-Rough 5/24/2023 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 6/6/2023 Partial Approval ALEJANDRO DE ARTOLA
HVAC-Rough 6/6/2023 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 8/11/2023 Not Ready for Inspection BRENDAN MORELLI
Rough-Elec/Plmb/HVAC 8/11/2023 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Rough 8/24/2023 Approved BRENDAN MORELLI
HVAC-Rough 8/24/2023 Approved BRENDAN MORELLI
PLUMBING-Rough 8/24/2023 Corrections Issued BRENDAN MORELLI
Interior/Exterior Lathing 8/29/2023 Not Ready for Inspection BRENDAN MORELLI
PLUMBING-Rough 8/29/2023 Not Ready for Inspection BRENDAN MORELLI
BUILDING-Rough-Frame 8/31/2023 Corrections Issued ALIZAH MAYAGOITIA
Green Building Rough 8/31/2023 Approved ALIZAH MAYAGOITIA
METHANE-Rough 8/31/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 8/31/2023 Approved ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 8/31/2023 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 9/8/2023 Conditional Approval ALIZAH MAYAGOITIA
ELECTRICAL-Rough 9/8/2023 Approved ALIZAH MAYAGOITIA
METHANE-Final 9/8/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
METHANE-Rough 9/8/2023 Approved ALIZAH MAYAGOITIA
Insulation 9/20/2023 Conditional Approval BRENDAN MORELLI
Drywall Nailing 9/26/2023 Approved BRENDAN MORELLI
Shower Pan 10/20/2023 Approved BRENDAN MORELLI
Interior/Exterior Lathing 11/2/2023 Partial Approval BRENDAN MORELLI
Interior/Exterior Lathing 11/28/2023 Approved BRENDAN MORELLI
Pre-Inspection 6/10/2024 Partial Approval JOSEPH MCGARRY
Underground Mechanical 7/30/2024 Partial Approval BRENDAN MORELLI
Underground Mechanical 8/1/2024 Corrections Issued SCOTT FINNILA
Underground Mechanical 9/11/2024 Corrections Issued BRENDAN MORELLI
Underground Mechanical 9/24/2024 Corrections Issued BRENDAN MORELLI
Underground Mechanical 9/27/2024 Partial Approval BRENDAN MORELLI
ELECTRICAL-Rough 10/29/2024 Approved BRENDAN MORELLI
ELECTRICAL-Final 12/17/2024 Corrections Issued NICHOLAS LOPEZ
PLUMBING-Final 12/18/2024 Not Ready for Inspection NICHOLAS LOPEZ
PLUMBING-Final 12/24/2024 Corrections Issued NICHOLAS LOPEZ
ELECTRICAL-Final 1/14/2025 Approved BRENDAN MORELLI
HVAC-Final 1/14/2025 Corrections Issued BRENDAN MORELLI
PLUMBING-Final 1/14/2025 Approved BRENDAN MORELLI
ELECTRICAL-Final 1/23/2025 Approved NICHOLAS LOPEZ
HVAC-Final 1/23/2025 Partial Approval NICHOLAS LOPEZ
BUILDING-Rough-Frame 6/4/2025 Approved BRENDAN MORELLI
Footing/Foundation/Slab 6/4/2025 Approved BRENDAN MORELLI
METHANE-Rough 6/4/2025 Approved BRENDAN MORELLI
Final 7/18/2025 Corrections Issued NICHOLAS LOPEZ
Green Building Final 7/18/2025 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 7/18/2025 SGSOV Approved NICHOLAS LOPEZ
Service/Power Release 7/18/2025 Approved NICHOLAS LOPEZ
Smoke Detectors 7/18/2025 Approved NICHOLAS LOPEZ
Final 7/24/2025 OK to Issue CofO NICHOLAS LOPEZ