650 S ORANGE DR 90036

Certificate Information: 650 S ORANGE DR 90036

Application / Permit
20010-10000-01398
Plan Check / Job No.
B20LA07514
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
DETACHED NEW CONSTRUCTION 2-STORY ADU PER GCS 65852.2 (e) (1)(B) WITH 1-CAR GARAGE .
Permit Issued
Issued on 3/10/2022
Issuing Office
Current Status
CofO Issued on 5/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/24/2020 APPLICANT
Assigned to Plan Check Engineer 5/14/2020 CRYSTEL MAALOUF
Corrections Issued 5/21/2020 CRYSTEL MAALOUF
Quality Review Completed 5/28/2020 BILL STUTSMAN
Green Plans Picked Up 6/30/2020 APPLICANT
Applicant returned to address corrections 5/27/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 6/9/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 6/11/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 8/12/2021 CRYSTEL MAALOUF
Plan Check Approved 9/21/2021 CRYSTEL MAALOUF
Issued 3/10/2022 APPLICANT
Building Plans Picked Up 3/15/2022 APPLICANT
CofO in Progress 5/14/2025 RONNIE MINDANAO
Permit Finaled 5/15/2025 DEROLD HAUFF
CofO Issued 5/15/2025 DEROLD HAUFF
Permit Finaled 5/15/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/23/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 6/23/2020 RENZ SORIANO
Sewer availability Cleared 6/23/2020 RENZ SORIANO
Construction near power lines Cleared 7/12/2020 RIDWAN HARDY
Low Impact Development Cleared 2/4/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 2/11/2021 THOMAS LANG
Hydrant and Access approval Cleared 3/23/2021 JOHN CONNEALLY
Green Code Cleared 6/11/2021 VIVIAN LAO

Contact Information

Contractor Auten Construction; Lic. No.: 554342-B 9018 BALBOA AVENUE #322      NORTHRIDGE, CA 91325
Engineer Garcia,, Francisco Diaz; Lic. No.: C88029 7333 RANCHITO AVE      VAN NUYS, CA 91405

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/27/2022 Approved ADAM ESCOTO
Excavation/Setback/Form/Re-Bar 6/29/2022 Partial Approval ADAM ESCOTO
Footing/Foundation/Slab 8/18/2022 Approved JEFFREY MEAD
METHANE-Barrier 8/18/2022 Approved JEFFREY MEAD
METHANE-Subgrade 8/18/2022 Approved JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 10/17/2022 Approved MICHAEL LEWIS
Special/Order Compliance 10/31/2022 No Access for Inspection JOSEPH MCGARRY
Pre-Inspection 12/8/2022 Approved RICHARD DOCKUS
Underground Mechanical 2/3/2023 Partial Approval RICHARD DOCKUS
Underground Mechanical 2/21/2023 Partial Approval MICHAEL LEWIS
Sewer 3/30/2023 Partial Approval MICHAEL LEWIS
Underground Mechanical 4/12/2023 Approved JEFFREY MEAD
ELECTRICAL-Rough 5/9/2023 Approved RICHARD DOCKUS
Green Building Rough 5/9/2023 Not Ready for Inspection RICHARD DOCKUS
METHANE-Rough 5/9/2023 Approved RICHARD DOCKUS
Verify Sprinkler Sign Off 5/9/2023 Approved RICHARD DOCKUS
Deputy Wood Construction 5/12/2023 Conditional Approval RICHARD DOCKUS
PLUMBING-Rough 5/12/2023 Not Ready for Inspection RICHARD DOCKUS
Wood Frame 5/12/2023 Partial Approval RICHARD DOCKUS
BUILDING-Rough-Frame 5/18/2023 Partial Approval RICHARD DOCKUS
HVAC-Rough 5/18/2023 Approved RICHARD DOCKUS
PLUMBING-Rough 5/18/2023 Approved RICHARD DOCKUS
Green Building Rough 7/20/2023 Corrections Issued LILIANA PORTILLO
Insulation 7/20/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 7/20/2023 Partial Approval LILIANA PORTILLO
Drywall Nailing 8/2/2023 Approved BRENDAN MORELLI
Green Building Rough 8/2/2023 Approved BRENDAN MORELLI
Underground Mechanical 11/30/2023 Partial Approval RICHARD DOCKUS
Sewer 12/8/2023 Approved RICHARD DOCKUS
Service/Power Release 5/3/2024 Approved JOSEPH MCGARRY
HVAC-Final 9/6/2024 Corrections Issued RONNIE MINDANAO
Final 10/24/2024 Corrections Issued RONNIE MINDANAO
HVAC-Final 10/24/2024 Approved RONNIE MINDANAO
BUILDING-Rough-Frame 3/7/2025 Approved RONNIE MINDANAO
ELECTRICAL-Final 3/7/2025 Corrections Issued RONNIE MINDANAO
Final 3/7/2025 Corrections Issued RONNIE MINDANAO
Green Building Final 3/7/2025 Approved RONNIE MINDANAO
PLUMBING-Final 3/7/2025 Corrections Issued RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 3/7/2025 SGSOV Not Ready RONNIE MINDANAO
Smoke Detectors 3/7/2025 Approved RONNIE MINDANAO
Final 4/3/2025 Not Ready for Inspection RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 4/3/2025 SGSOV Approved RONNIE MINDANAO
Final 4/25/2025 Corrections Issued RONNIE MINDANAO
Gas Test 4/25/2025 Approved RONNIE MINDANAO
Final 5/13/2025 OK to Issue CofO RONNIE MINDANAO