815 S KINGSLEY DR 90005

Certificate Information: 815 S KINGSLEY DR 90005

Application / Permit
20010-10000-01382
Plan Check / Job No.
B20LA07400
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
PROPOSED 7-STORY 114-UNIT AFFORDABLE HOUSING PROJECT PER DIR 2020-1881-SPR-TOC-VHCA (TIER 3 STATUS) <VERIFY PERCENTAGE OF RESTRICTED INCOME UNITS FOR EXEMPTION TO LINKAGE FEE>
Permit Issued
Issued on 9/22/2021
Issuing Office
Metro
Current Status
Issued on 9/22/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Plan Check Approved 8/19/2021 VU NGUYEN
Issued 9/22/2021 APPLICANT
TCO Issued (Expire Date: 01-11-2025) 7/15/2024 ERNESTO CORRAL
TCO Issued (Expire Date: 06-18-2025) 12/20/2024 RAFAEL ESPINOZA
TCO Issued (Expire Date: 11-05-2025) 5/9/2025 RAFAEL ESPINOZA
TCO Issued (Expire Date: 04-29-2026) 10/31/2025 RAFAEL ESPINOZA
TCO Issued (Expire Date: 10-04-2026) 4/7/2026 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 7/24/2020 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 7/28/2020 ELAINE LEI
Permit Cleared 7/28/2020 ELAINE LEI
Highway dedication Cleared 7/29/2020 ELAINE LEI
Bicycle Parking Cleared 7/31/2020 ELAINE LEI
Construction near power lines Cleared 8/14/2020 RIDWAN HARDY
Green Code Cleared 12/2/2020 LAWRENCE QUIRANTE
Hydrant and Access approval Cleared 1/12/2021 MATTHEW CRAIG
Low Impact Development Cleared 1/29/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 3/5/2021 ELAINE LEI
Fire Marshall Fire Life Safety Cleared 3/25/2021 OSCAR SALGADO JR
DAS Clearance Cleared 5/21/2021 LAWRENCE QUIRANTE
Work Adjacent to Public Way Cleared 6/10/2021 JOSE RODRIGUEZ
Sewer availability Cleared 6/18/2021 CECILIO NAVARRO
Density Bonus 12.22.A.31 Cleared 6/22/2021 NICHOLAS KAWAZOE
Miscellaneous Cleared 7/28/2021 JASON CHAN
Frnt yard landscape/Water mgmt Cleared 7/30/2021 JASON CHAN
Opn space landscape/Water mgmt Cleared 7/30/2021 JASON CHAN
Site Plan review Cleared 7/30/2021 JASON CHAN
Redevelopment Project Area Cleared 8/5/2021 GRACIELA ACOSTA
Building over 36-ft Cleared 8/17/2021 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 8/17/2021 CALOSHA APPROVED

Contact Information

Architect Block,, Kara L; Lic. No.: C32273 4211 W 59TH ST      LOS ANGELES, CA 90043
Contractor Wilshire Construction L P; Lic. No.: 1048091-B 3470 WILSHIRE STE 1010      LOS ANGELES, CA 90010
Engineer Cai,, Luo B; Lic. No.: C80352 9428 ETAON AVE M      CHATSWORTH, CA 91311
Engineer Funk,, David Lyle; Lic. No.: S5421 319 MAIN STREET      EL SEGUNDO, CA 90245

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/12/2021 Partial Approval DANIEL COLLINS
Deputy Reinf. Concrete 10/22/2021 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 1/27/2022 Conditional Approval NICK DANERI
Green Building Rough 1/27/2022 Not Ready for Inspection NICK DANERI
Pre-Inspection 1/27/2022 Partial Inspection NICK DANERI
Reinforced Concrete Frame 1/27/2022 Partial Inspection NICK DANERI
Verify Sprinkler Sign Off 1/27/2022 Not Ready for Inspection NICK DANERI
Deputy Shotcrete 2/2/2022 Conditional Approval NICK DANERI
Pre-Inspection 2/3/2022 Partial Approval NICK DANERI
Deputy Reinf. Concrete 2/28/2022 Conditional Approval NICK DANERI
Footing/Foundation/Slab 2/28/2022 Partial Approval NICK DANERI
Deputy Reinf. Concrete 3/1/2022 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 3/2/2022 Conditional Approval NICK DANERI
Footing/Foundation/Slab 3/10/2022 Partial Approval NICK DANERI
Deputy Other (see comments) 3/14/2022 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 3/14/2022 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 3/15/2022 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 3/16/2022 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 3/17/2022 Conditional Approval NICK DANERI
Green Building Rough 3/18/2022 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 3/18/2022 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 3/18/2022 Not Ready for Inspection NICK DANERI
Green Building Rough 3/25/2022 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 3/25/2022 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 3/25/2022 Not Ready for Inspection NICK DANERI
Footing/Foundation/Slab 3/29/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Other (see comments) 3/30/2022 Conditional Approval NICK DANERI
Deputy Shotcrete 3/30/2022 Conditional Approval NICK DANERI
Footing/Foundation/Slab 4/5/2022 Partial Approval NICK DANERI
Footing/Foundation/Slab 4/7/2022 Not Ready for Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 4/26/2022 Partial Approval RUSSELL BONVOULOIR
Deputy Other (see comments) 4/28/2022 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 4/28/2022 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 5/2/2022 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 5/3/2022 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 5/4/2022 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 5/5/2022 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 5/6/2022 Conditional Approval NICK DANERI
Reinforced Masonry Frame 5/13/2022 Partial Approval NICK DANERI
Footing/Foundation/Slab 5/24/2022 Not Ready for Inspection NICK DANERI
Green Building Rough 5/25/2022 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 5/25/2022 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 5/25/2022 Not Ready for Inspection NICK DANERI
Deputy Other (see comments) 5/27/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 5/27/2022 Conditional Approval ERNESTO CORRAL
Green Building Rough 6/1/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 6/1/2022 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 6/1/2022 Not Ready for Inspection RAFAEL ESPINOZA
Green Building Rough 6/6/2022 Partial Approval NICK DANERI
Reinforced Concrete Frame 6/6/2022 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 6/6/2022 No Access for Inspection NICK DANERI
Deputy Other (see comments) 6/8/2022 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 6/8/2022 Conditional Approval ERNESTO CORRAL
Masonry Wall/Backfill 6/16/2022 Partial Approval NICK DANERI
Reinforced Masonry Frame 6/16/2022 Partial Approval NICK DANERI
Piling/Pier/Caisson 6/22/2022 Partial Inspection NICK DANERI
Deputy Drilled-In Anchors 6/24/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 6/27/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 6/28/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 6/29/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 6/30/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/1/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 7/1/2022 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 7/5/2022 Partial Approval RAFAEL ESPINOZA
Deputy Other (see comments) 7/7/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/7/2022 Conditional Approval ERNESTO CORRAL
Piling/Pier/Caisson 7/14/2022 Partial Inspection NICK DANERI
Deputy Reinf. Concrete 7/15/2022 Conditional Approval GREGORY POMISH
Green Building Rough 7/18/2022 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 7/18/2022 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 7/18/2022 Not Ready for Inspection NICK DANERI
Green Building Rough 7/22/2022 Not Ready for Inspection TED RIES
Reinforced Concrete Frame 7/22/2022 Partial Approval TED RIES
Verify Sprinkler Sign Off 7/22/2022 Not Ready for Inspection TED RIES
Reinforced Masonry Frame 7/29/2022 Partial Approval NICK DANERI
Deputy Reinf. Concrete 8/12/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/15/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/16/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/17/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/18/2022 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 8/19/2022 Partial Approval NICK DANERI
Green Building Rough 8/22/2022 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 8/22/2022 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 8/22/2022 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 8/23/2022 Conditional Approval WINSTON DUNNING
Deputy Other (see comments) 8/24/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Concrete 8/24/2022 Conditional Approval WINSTON DUNNING
Green Building Rough 8/29/2022 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 8/29/2022 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 8/29/2022 Not Ready for Inspection NICK DANERI
Green Building Rough 8/31/2022 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 8/31/2022 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 8/31/2022 Not Ready for Inspection NICK DANERI
Deputy Shotcrete 9/1/2022 Conditional Approval TED RIES
Deputy Shotcrete 9/2/2022 Conditional Approval GREGORY POMISH
Green Building Rough 10/12/2022 Not Ready for Inspection TED RIES
Reinforced Concrete Frame 10/12/2022 Partial Approval TED RIES
Verify Sprinkler Sign Off 10/12/2022 Not Ready for Inspection TED RIES
Footing/Foundation/Slab 10/13/2022 Not Ready for Inspection GREGORY POMISH
Deputy Reinf. Concrete 10/14/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/2/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/15/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/17/2022 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 11/17/2022 Partial Approval NICK DANERI
Deputy Reinf. Concrete 11/22/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/30/2022 Conditional Approval MICHAEL ROSENBERG
Pre-Inspection 12/2/2022 Partial Approval NICK DANERI
Wood Frame 12/2/2022 Partial Inspection NICK DANERI
Pre-Inspection 12/6/2022 Partial Approval JAMES POWERS
Wood Frame 12/6/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 12/7/2022 Conditional Approval MICHAEL ROSENBERG
Wood Frame 12/7/2022 Partial Approval NICK DANERI
Deputy Wood Construction 12/8/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 12/9/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 12/12/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 12/13/2022 Conditional Approval MICHAEL ROSENBERG
Pre-Inspection 12/16/2022 Partial Inspection NICK DANERI
Deputy Wood Construction 12/19/2022 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 12/19/2022 Partial Approval NICK DANERI
Wood Frame 12/19/2022 Partial Approval NICK DANERI
Deputy Wood Construction 12/20/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 12/21/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 12/22/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 12/23/2022 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 12/27/2022 Partial Approval NICK DANERI
Deputy Wood Construction 12/28/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 12/29/2022 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 12/29/2022 Partial Approval NICK DANERI
Deputy Wood Construction 12/30/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 1/3/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 1/3/2023 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 1/4/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 1/17/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 1/18/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 1/19/2023 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 1/19/2023 Partial Approval NICK DANERI
Deputy Wood Construction 1/20/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 1/23/2023 Conditional Approval MICHAEL ROSENBERG
Pre-Inspection 1/23/2023 Partial Inspection GREGORY POMISH
Deputy Wood Construction 1/26/2023 Conditional Approval GREGORY POMISH
Insulation 1/26/2023 Partial Approval GREGORY POMISH
Deputy Wood Construction 1/27/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 1/27/2023 Not Ready for Inspection NICK DANERI
Deputy Wood Construction 1/30/2023 Conditional Approval MICHAEL ROSENBERG
Drywall Nailing 1/30/2023 Not Ready for Inspection GREGORY POMISH
Insulation 1/30/2023 Not Ready for Inspection GREGORY POMISH
Interior/Exterior Lathing 1/30/2023 Not Ready for Inspection GREGORY POMISH
Wood Frame 1/30/2023 Not Ready for Inspection GREGORY POMISH
Deputy Wood Construction 1/31/2023 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 1/31/2023 Partial Approval NICK DANERI
Insulation 1/31/2023 Not Ready for Inspection NICK DANERI
Light Gage Steel Frame 1/31/2023 Partial Inspection NICK DANERI
Wood Frame 1/31/2023 Partial Approval NICK DANERI
Deputy Wood Construction 2/1/2023 Conditional Approval MICHAEL ROSENBERG
Drywall Nailing 2/6/2023 Not Ready for Inspection EDWIN GREGORYONA
Insulation 2/6/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 2/8/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 2/21/2023 Partial Approval NICK DANERI
Insulation 2/23/2023 Partial Approval NICK DANERI
Insulation 2/27/2023 Not Ready for Inspection NICK DANERI
Deputy Wood Construction 3/2/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 3/6/2023 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 3/6/2023 Partial Approval NICK DANERI
Insulation 3/8/2023 Partial Inspection NICK DANERI
Pre-Inspection 3/8/2023 Partial Approval NICK DANERI
Pre-Inspection 3/23/2023 Approved EDWIN GREGORYONA
Wood Frame 3/23/2023 Partial Approval EDWIN GREGORYONA
Insulation 3/24/2023 Partial Inspection DAVID BURKHEAD
Drywall Nailing 3/28/2023 Partial Inspection NICK DANERI
Insulation 3/28/2023 Partial Inspection NICK DANERI
Wood Frame 3/28/2023 Partial Approval NICK DANERI
Deputy Wood Construction 3/31/2023 Conditional Approval GREGORY POMISH
Insulation 3/31/2023 Partial Inspection GREGORY POMISH
Pre-Inspection 3/31/2023 Partial Inspection GREGORY POMISH
Wood Frame 3/31/2023 Partial Inspection GREGORY POMISH
Insulation 4/4/2023 Partial Approval GREGORY POMISH
Wood Frame 4/4/2023 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 4/7/2023 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 4/10/2023 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 4/11/2023 Partial Approval NICK DANERI
Insulation 4/12/2023 Partial Approval NICK DANERI
Insulation 4/13/2023 Partial Approval JAMES POWERS
Wood Frame 4/13/2023 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/17/2023 Partial Inspection NICK DANERI
Wood Frame 4/17/2023 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 4/20/2023 Partial Inspection NICK DANERI
Insulation 4/20/2023 Partial Inspection NICK DANERI
Wood Frame 4/20/2023 Partial Approval NICK DANERI
Drywall Nailing 4/25/2023 Partial Inspection GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 4/25/2023 Partial Inspection GREGORY POMISH
Insulation 4/25/2023 Partial Inspection GREGORY POMISH
Wood Frame 4/26/2023 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 5/3/2023 Not Ready for Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 5/5/2023 Partial Approval RAFAEL ESPINOZA
Insulation 5/5/2023 Partial Approval RAFAEL ESPINOZA
Insulation 5/9/2023 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 5/11/2023 Partial Inspection NICK DANERI
Insulation 5/11/2023 Partial Approval NICK DANERI
Drywall Nailing 5/15/2023 Partial Approval DAVID BURKHEAD
Drywall Nailing 5/17/2023 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 5/17/2023 Partial Inspection GREGORY POMISH
Insulation 5/17/2023 Partial Inspection GREGORY POMISH
Pre-Inspection 5/17/2023 Not Ready for Inspection GREGORY POMISH
Wood Frame 5/17/2023 Partial Approval GREGORY POMISH
Insulation 5/23/2023 Partial Approval NICK DANERI
Deputy Reinf. Concrete 5/26/2023 Conditional Approval NICK DANERI
Drywall Nailing 5/26/2023 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 5/26/2023 Not Ready for Inspection NICK DANERI
Insulation 5/26/2023 Not Ready for Inspection NICK DANERI
Light Gage Steel Frame 5/26/2023 Not Ready for Inspection NICK DANERI
Pre-Inspection 5/26/2023 Partial Inspection NICK DANERI
Structural Steel Frame 5/26/2023 Partial Approval NICK DANERI
Insulation 5/30/2023 Partial Approval GREGORY POMISH
Insulation 6/1/2023 Partial Approval NICK DANERI
Pre-Inspection 6/1/2023 Partial Inspection NICK DANERI
Insulation 6/2/2023 Partial Approval NICK DANERI
Drywall Nailing 6/8/2023 Partial Approval GREGORY POMISH
Insulation 6/13/2023 Not Ready for Inspection GREGORY POMISH
Pre-Inspection 6/14/2023 Not Ready for Inspection NICK DANERI
Wood Frame 6/14/2023 Not Ready for Inspection NICK DANERI
Wood Frame 6/15/2023 Partial Approval NICK DANERI
Insulation 6/20/2023 Partial Approval NICK DANERI
Special/Order Compliance 6/21/2023 Partial Inspection NICK DANERI
Insulation 6/26/2023 Partial Approval NICK DANERI
Drywall Nailing 6/27/2023 Partial Approval NICK DANERI
Pre-Inspection 6/28/2023 Partial Approval NICK DANERI
Insulation 6/30/2023 Partial Approval NICK DANERI
Insulation 7/3/2023 Corrections Issued LARRY ARNICK
Insulation 7/5/2023 Partial Approval JAMES POWERS
Wood Frame 7/5/2023 Not Ready for Inspection JAMES POWERS
Drywall Nailing 7/6/2023 Not Ready for Inspection TIMOTHY POWELL
Drywall Nailing 7/7/2023 Partial Approval GREGORY POMISH
Drywall Nailing 7/10/2023 Partial Inspection RAFAEL ESPINOZA
Wood Frame 7/10/2023 Partial Approval RAFAEL ESPINOZA
Insulation 7/11/2023 Not Ready for Inspection LARRY ARNICK
Insulation 7/13/2023 Partial Approval GREGORY POMISH
Insulation 7/14/2023 Partial Approval NICK DANERI
Drywall Nailing 7/17/2023 Not Ready for Inspection NICK DANERI
Insulation 7/17/2023 Partial Approval NICK DANERI
Light Gage Steel Frame 7/17/2023 Partial Approval NICK DANERI
Wood Frame 7/17/2023 Partial Approval NICK DANERI
Interior/Exterior Lathing 7/21/2023 Partial Approval GREGORY POMISH
Pre-Inspection 7/25/2023 Not Ready for Inspection GREGORY POMISH
Insulation 8/2/2023 Partial Approval NICK DANERI
Insulation 8/9/2023 Partial Approval NICK DANERI
Interior/Exterior Lathing 8/14/2023 Partial Approval GREGORY POMISH
Pre-Inspection 8/16/2023 Partial Approval NICK DANERI
Pre-Inspection 8/22/2023 Partial Approval NICK DANERI
Interior/Exterior Lathing 8/23/2023 Partial Approval NICK DANERI
Insulation 8/25/2023 Not Ready for Inspection NICK DANERI
Pre-Inspection 8/25/2023 Not Ready for Inspection NICK DANERI
Pre-Inspection 8/28/2023 Partial Approval NICK DANERI
Insulation 8/29/2023 Partial Approval NICK DANERI
Pre-Inspection 8/31/2023 Not Ready for Inspection NICK DANERI
Pre-Inspection 9/1/2023 Partial Approval NICK DANERI
Pre-Inspection 9/6/2023 Partial Approval NICK DANERI
Footing/Foundation/Slab 9/11/2023 Partial Approval NICK DANERI
Pre-Inspection 9/13/2023 Partial Approval NICK DANERI
Wood Frame 9/15/2023 Partial Approval NICK DANERI
Pre-Inspection 9/20/2023 Partial Approval GREGORY POMISH
Interior/Exterior Lathing 9/26/2023 Partial Approval NICK DANERI
Pre-Inspection 9/29/2023 Partial Approval NICK DANERI
Masonry Wall/Backfill 10/2/2023 Partial Inspection NICK DANERI
Pre-Inspection 10/2/2023 Partial Approval NICK DANERI
Pre-Inspection 10/3/2023 Partial Inspection GREGORY POMISH
Drywall Nailing 10/23/2023 Partial Approval NICK DANERI
Light Gage Steel Frame 11/2/2023 Partial Approval NICK DANERI
Pre-Inspection 11/2/2023 Partial Inspection NICK DANERI
T-Bar Ceiling 11/6/2023 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 11/14/2023 Partial Approval NICK DANERI
Drywall Nailing 11/28/2023 Partial Inspection GREGORY POMISH
Drywall Nailing 12/5/2023 Partial Approval NICK DANERI
Pre-Inspection 12/13/2023 Corrections Issued NICK DANERI
Drywall Nailing 12/19/2023 Not Ready for Inspection EDWIN GREGORYONA
Pre-Inspection 12/19/2023 Partial Inspection EDWIN GREGORYONA
Pre-Inspection 12/28/2023 Partial Inspection NICK DANERI
Pre-Inspection 12/29/2023 Partial Inspection NICK DANERI
Pre-Inspection 1/18/2024 Partial Inspection NICK DANERI
Drywall Nailing 1/25/2024 Partial Inspection NICK DANERI
Light Gage Steel Frame 1/25/2024 Partial Inspection NICK DANERI
Pre-Inspection 1/25/2024 Partial Approval NICK DANERI
Special/Order Compliance 1/29/2024 Partial Inspection NICK DANERI
Special/Order Compliance 2/8/2024 Partial Inspection NICK DANERI
Special/Order Compliance 2/12/2024 Corrections Issued NICK DANERI
Final 2/13/2024 Partial Inspection NICK DANERI
Footing/Foundation/Slab 2/13/2024 Approved NICK DANERI
Green Building Final 2/13/2024 Not Ready for Inspection NICK DANERI
Green Building Rough 2/13/2024 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 2/13/2024 Not Ready for Inspection NICK DANERI
SGSOV-Seismic Gas S/O Valve 2/13/2024 SGSOV Not Ready NICK DANERI
Smoke Detectors 2/13/2024 Not Ready for Inspection NICK DANERI
Verify Sprinkler Sign Off 2/13/2024 Not Ready for Inspection NICK DANERI
Special/Order Compliance 2/14/2024 Partial Inspection NICK DANERI
Special/Order Compliance 3/5/2024 Partial Inspection NICK DANERI
Special/Order Compliance 3/20/2024 Partial Approval NICK DANERI
Special/Order Compliance 4/5/2024 Partial Approval NICK DANERI
Pre-Inspection 5/31/2024 Partial Approval NICK DANERI
Pre-Inspection 7/8/2024 Approved EDWIN GREGORYONA
Final 7/11/2024 Not Ready for Inspection NICK DANERI
Green Building Final 7/11/2024 Not Ready for Inspection NICK DANERI
Green Building Rough 7/11/2024 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 7/11/2024 Not Ready for Inspection NICK DANERI
SGSOV-Seismic Gas S/O Valve 7/11/2024 SGSOV Approved NICK DANERI
Smoke Detectors 7/11/2024 Approved NICK DANERI
Verify Sprinkler Sign Off 7/11/2024 Approved NICK DANERI
Special/Order Compliance 7/15/2024 Conditional Approval NICK DANERI
Special/Order Compliance 12/18/2024 Conditional Approval NICK DANERI
Special/Order Compliance 10/7/2025 Approved JOEY BUCHANAN
Special/Order Compliance 4/1/2026 Approved JOEY BUCHANAN