3560 S GREENWOOD AVE 90066
Certificate Information: 3560 S GREENWOOD AVE 90066
- Application / Permit
- 20010-10000-01374
- Plan Check / Job No.
- B20LA07361
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2 STORY SFD WITH ATTACHED GARAGE
- Permit Issued
- Issued on 1/11/2022
- Issuing Office
- Current Status
- CofO Issued on 3/28/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2020 | STARR CHEN |
| Green Plans Picked Up | 5/18/2020 | APPLICANT |
| Corrections Issued | 6/2/2020 | STARR CHEN |
| Quality Review Completed | 6/3/2020 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 11/16/2020 | STARR CHEN |
| Applicant returned to address corrections | 12/24/2020 | STARR CHEN |
| Applicant returned to address corrections | 8/5/2021 | STARR CHEN |
| Plan Check Approved | 12/22/2021 | STARR CHEN |
| Issued | 1/11/2022 | APPLICANT |
| Building Plans Picked Up | 1/14/2022 | APPLICANT |
| CofO in Progress | 3/16/2023 | JESUS RODRIGUEZ |
| Permit Finaled | 3/28/2023 | DANIEL ORRANTE |
| CofO Issued | 3/28/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/28/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 1/5/2021 | DINAH GARIN |
| Permit | Cleared | 1/5/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2021 | DINAH GARIN |
| Sewer availability | Cleared | 1/6/2021 | DINAH GARIN |
| Specific Plan | Cleared | 1/6/2021 | PEDRO AYALA |
| Hydrant and Access approval | Cleared | 2/8/2021 | JEREMY CARTER |
| Low Impact Development | Cleared | 6/16/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 6/24/2021 | DINAH GARIN |
| GPI Written Notices | Cleared | 8/5/2021 | STARR CHEN |
| Grading Pre-Inspection | Cleared | 8/5/2021 | STARR CHEN |
| Green Code | Cleared | 8/5/2021 | DONALD CRICHLOW |
| Trees in Parkway | Cleared | 9/22/2021 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Foroughi,, Mohammad Hossein; Lic. No.: C66179 | 767 NORTH HILL STREET 407 LOS ANGELES, CA 90012 |
| Engineer | Koujah,, Bachar; Lic. No.: C47490 | 37 ENCHANTED IRVINE, CA 92620 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 2/14/2022 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 2/14/2022 | Corrections Issued | STEPHANIE SWANSON |
| Sewer | 3/4/2022 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 4/5/2022 | Approved | PATRICK QUALEY |
| Footing/Foundation/Slab | 4/5/2022 | Approved | PATRICK QUALEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2022 | Conditional Approval | PATRICK QUALEY |
| Deputy Wood Construction | 5/3/2022 | No Access for Inspection | PATRICK QUALEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2022 | Conditional Approval | PATRICK QUALEY |
| PLUMBING-Rough | 5/5/2022 | Partial Approval | PATRICK QUALEY |
| Underground Mechanical | 5/5/2022 | Corrections Issued | PATRICK QUALEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2022 | Partial Inspection | JESUS RODRIGUEZ |
| Underground Mechanical | 5/11/2022 | Partial Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 5/16/2022 | Partial Approval | PATRICK QUALEY |
| ELECTRICAL-Rough | 5/19/2022 | Corrections Issued | PATRICK QUALEY |
| HVAC-Rough | 5/19/2022 | Approved | PATRICK QUALEY |
| PLUMBING-Rough | 5/24/2022 | Corrections Issued | PATRICK QUALEY |
| BUILDING-Rough-Frame | 5/31/2022 | Partial Approval | PATRICK QUALEY |
| ELECTRICAL-Final | 5/31/2022 | Approved | PATRICK QUALEY |
| Green Building Rough | 5/31/2022 | Not Ready for Inspection | PATRICK QUALEY |
| PLUMBING-Rough | 5/31/2022 | Approved | PATRICK QUALEY |
| Verify Sprinkler Sign Off | 5/31/2022 | Not Ready for Inspection | PATRICK QUALEY |
| Wood Frame | 6/6/2022 | Approved | PATRICK QUALEY |
| Interior/Exterior Lathing | 6/14/2022 | Partial Approval | PATRICK QUALEY |
| Shower Pan | 6/14/2022 | Corrections Issued | PATRICK QUALEY |
| BUILDING-Rough-Frame | 6/16/2022 | Approved | EVAN COOPER |
| Green Building Rough | 6/16/2022 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 6/16/2022 | Approved | EVAN COOPER |
| Insulation | 6/22/2022 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 6/22/2022 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 6/28/2022 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 6/28/2022 | Approved | STEPHANIE SWANSON |
| Final | 6/28/2022 | Corrections Issued | STEPHANIE SWANSON |
| Gas Test | 6/28/2022 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 7/1/2022 | Approved | PATRICK QUALEY |
| Masonry Wall/Backfill | 9/8/2022 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 9/23/2022 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 9/23/2022 | SGSOV Approved | JESUS RODRIGUEZ |
| Service/Power Release | 9/23/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Smoke Detectors | 9/23/2022 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 9/27/2022 | Approved | JESUS RODRIGUEZ |
| Final | 12/23/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 12/23/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 12/23/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 12/23/2022 | Approved | JESUS RODRIGUEZ |
| Reinforced Masonry Frame | 12/23/2022 | Approved | JESUS RODRIGUEZ |
| Final | 3/15/2023 | OK to Issue CofO | JESUS RODRIGUEZ |