7423 S CENTRAL AVE 90001
Certificate Information: 7423 S CENTRAL AVE 90001
- Application / Permit
- 20010-10000-01352
- Plan Check / Job No.
- B20LA07273
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (5) Apartment
- Work Description
- New 3- story apartment and office mixed use building with a parking garage and office space on grade level and 5 Units apartment dwelling on 2nd and 3rd floors. Parking required utilized AB2097
- Permit Issued
- Issued on 2/26/2025
- Issuing Office
- Metro
- Current Status
- Issued on 2/26/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2020 | SAM CHANG |
| Corrections Issued | 5/13/2020 | SAM CHANG |
| Quality Review Completed | 6/2/2020 | ARMEN JIVALAGIAN |
| Building Plans Picked Up | 6/3/2020 | APPLICANT |
| Applicant returned to address corrections | 10/28/2021 | SAM CHANG |
| Green Plans Picked Up | 10/28/2021 | APPLICANT |
| Applicant returned to address corrections | 7/23/2024 | SAM CHANG |
| Plan Check Approved | 11/22/2024 | SAM CHANG |
| Issued | 2/26/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/4/2020 | CECILIO NAVARRO |
| Opn space landscape/Water mgmt | Cleared | 11/5/2020 | RICHARD REASER |
| Sewer availability | Cleared | 11/24/2020 | CECILIO NAVARRO |
| Community Plan Implem. Overlay | Cleared | 12/10/2020 | ALBERT TAM |
| Eng Process Fee Ord 176,300 | Cleared | 12/14/2020 | CECILIO NAVARRO |
| Redevelopment Project Area | Cleared | 6/22/2021 | GRACIELA ACOSTA |
| Hydrant and Access approval | Cleared | 10/19/2021 | KURT CORRAL |
| Community Plan Implem. Overlay | Cleared | 11/24/2021 | ADALBERTO VERA |
| Fire Marshall Fire Life Safety | Cleared | 2/1/2022 | PEJMAN NOORI |
| Highway dedication | Cleared | 2/3/2022 | CINDY QI |
| Permit | Cleared | 2/3/2022 | CINDY QI |
| Trees in Parkway | Cleared | 2/23/2022 | ADALBERTO VERA |
| Building over 36-ft | Cleared | 3/4/2022 | CALOSHA APPROVED |
| Low Impact Development | Cleared | 4/19/2022 | SARAH YOUSSEF |
| Green Code | Cleared | 4/27/2022 | AARON COSTA |
| Roof/Waste drainage to street | Cleared | 5/3/2022 | CINDY QI |
| DAS Clearance | Cleared | 5/23/2022 | SAM CHANG |
| Community Plan Implem. Overlay | Cleared | 7/26/2022 | HELEN JADALI |
| ZI | Cleared | 8/27/2024 | YINGSHI HUANG |
| Work Adjacent to Public Way | Cleared | 10/23/2024 | JOSE RODRIGUEZ |
Contact Information
| Architect | Wang,, Johann D; Lic. No.: C27010 | 3375 CANTON WAY STUDIO CITY, CA 91604 |
| Contractor | Owner-Builder | , |
| Engineer | Baroonian,, Armen; Lic. No.: S4227 | 867 N FAIR OAKS AVE 100 PASADENA, CA 91103 |
| Engineer | Vidal,, Juan Alonso; Lic. No.: GE861 | 7438 SHIRLEY AVE RESEDA, CA 91335 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| No Data Available. |