240 N MADISON AVE 90004
Certificate Information: 240 N MADISON AVE 90004
- Application / Permit
- 20010-10000-01341
- Plan Check / Job No.
- B20LA07162
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (18) School Building
- Work Description
- New 2 story classroom building for grades TK-8th grade (total of 20 classrooms) with support spaces, offices, multi purpose room, boys and girls locker rooms, elevator, and utility rooms. Maximum number of student enrolled is 480 students. (Sign is under separate permit #20048-10000-01490)
- Permit Issued
- Issued on 3/31/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/28/2020 | YOUNG KIM |
| Corrections Issued | 6/9/2020 | YOUNG KIM |
| Quality Review Completed | 6/26/2020 | ALLEN MANALANSAN |
| Building Plans Picked Up | 7/2/2020 | APPLICANT |
| Applicant returned to address corrections | 8/24/2020 | YOUNG KIM |
| Applicant returned to address corrections | 8/29/2020 | YOUNG KIM |
| Applicant returned to address corrections | 9/10/2020 | YOUNG KIM |
| Applicant returned to address corrections | 11/4/2020 | YOUNG KIM |
| Applicant returned to address corrections | 11/10/2020 | YOUNG KIM |
| Green Plans Picked Up | 12/11/2020 | APPLICANT |
| Applicant returned to address corrections | 2/3/2021 | YOUNG KIM |
| Applicant returned to address corrections | 2/5/2021 | YOUNG KIM |
| Plan Check Approved | 3/5/2021 | YOUNG KIM |
| Issued | 3/31/2021 | APPLICANT |
| TCO Issued (Expire Date: 11-05-2022) | 5/9/2022 | ERNESTO CORRAL |
| CofO in Progress | 11/1/2022 | DAVID BURKHEAD |
| Permit Finaled | 11/1/2022 | TERRY HERR |
| CofO Issued | 11/1/2022 | TERRY HERR |
| Permit Finaled | 11/1/2022 | TERRY HERR |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2020 | CECILIO NAVARRO |
| Green Code | Cleared | 8/6/2020 | YOUNG KIM |
| DAS Clearance | Cleared | 8/11/2020 | SOMKIAT SUPANYACHOTSKUL |
| Hydrant and Access approval | Cleared | 9/2/2020 | MATTHEW CRAIG |
| Sewer availability | Cleared | 10/20/2020 | CECILIO NAVARRO |
| Grading Pre-Inspection | Cleared | 11/15/2020 | YOUNG KIM |
| Encroachment in public way | Cleared | 11/25/2020 | ELAINE LEI |
| Fire Marshall Fire Life Safety | Cleared | 11/30/2020 | ANDREW KO |
| Low Impact Development | Cleared | 12/6/2020 | ORVAL HERNANDEZ-MARCI |
| Historic Resource Verification | Cleared | 1/11/2021 | MICAELA TORRES-GIL |
| CPC | Cleared | 1/13/2021 | KENTON TRINH |
| Specific Plan | Cleared | 1/13/2021 | KENTON TRINH |
| Redevelopment Project Area | Cleared | 1/15/2021 | DAVID URITA |
| Roof/Waste drainage to street | Cleared | 1/25/2021 | SAM NAVID |
| Permit | Cleared | 2/22/2021 | WALLIE JONG |
Contact Information
| Architect | Csda, Design Group; Lic. No.: C35165 | 889 N. DOUGLAS ST. 100 EL SEGUNDO, CA 90245 |
| Contractor | Consolidated Contracting Services Inc; Lic. No.: 475813-B | 181 AVENIDA LA PATA SUITE 200 SAN CLEMENTE, CA 92673 |
| Engineer | Grossman, & Speer Associates, Inc.; Lic. No.: S6228 | 529 HAHN AVE STE #200 GLENDALE, CA 91203 |
| Engineer | Vca, Engineering Inc.; Lic. No.: C36079 | 1041 S GARFIELD AVE STE #210 ALHAMBRA, CA 91801 |
| Landscape Architect | Brightview, Design Group; Lic. No.: LA1846 | 1715 18TH ST. SANTA MONICA, CA 90404 |
Inspector Information
| DAVID BURKHEAD, (213) 482-7294 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Barrier | 5/21/2021 | Partial Approval | DANIEL MC AULIFFE |
| Pre-Inspection | 5/21/2021 | Partial Inspection | DANIEL MC AULIFFE |
| Excavation/Setback/Form/Re-Bar | 6/2/2021 | Partial Inspection | DAVID BURKHEAD |
| Excavation/Setback/Form/Re-Bar | 6/3/2021 | Partial Approval | DAVID BURKHEAD |
| Footing/Foundation/Slab | 7/13/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| METHANE-Barrier | 7/13/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| METHANE-Subgrade | 7/13/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| Structural Steel Frame | 7/13/2021 | Partial Inspection | DAVID BURKHEAD |
| Excavation/Setback/Form/Re-Bar | 7/14/2021 | Partial Approval | DAVID BURKHEAD |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2021 | Partial Approval | DAVID BURKHEAD |
| Green Building Rough | 9/7/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| METHANE-Rough | 9/7/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| Verify Sprinkler Sign Off | 9/7/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| Footing/Foundation/Slab | 9/16/2021 | Partial Approval | DAVID BURKHEAD |
| METHANE-Barrier | 9/16/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| METHANE-Subgrade | 9/16/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| Green Building Rough | 9/28/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| METHANE-Rough | 9/28/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| Verify Sprinkler Sign Off | 9/28/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| Wood Frame | 9/28/2021 | Partial Approval | DAVID BURKHEAD |
| Piling/Pier/Caisson | 10/1/2021 | Conditional Approval | DAVID BURKHEAD |
| Reinforced Concrete Frame | 10/1/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2021 | Partial Approval | DAVID BURKHEAD |
| Reinforced Concrete Frame | 10/13/2021 | Partial Approval | RAFAEL ESPINOZA |
| Green Building Rough | 10/19/2021 | Not Ready for Inspection | DANIEL MC AULIFFE |
| METHANE-Rough | 10/19/2021 | Conditional Approval | DANIEL MC AULIFFE |
| Verify Sprinkler Sign Off | 10/19/2021 | Partial Inspection | DANIEL MC AULIFFE |
| Wood Frame | 10/19/2021 | Partial Approval | DANIEL MC AULIFFE |
| Green Building Rough | 10/22/2021 | Approved | DANIEL COLLINS |
| METHANE-Rough | 10/22/2021 | Not Ready for Inspection | DANIEL COLLINS |
| Verify Sprinkler Sign Off | 10/22/2021 | Not Ready for Inspection | DANIEL COLLINS |
| Wood Frame | 10/22/2021 | Partial Approval | DANIEL COLLINS |
| Insulation | 10/26/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| METHANE-Rough | 10/26/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| Verify Sprinkler Sign Off | 10/26/2021 | Partial Approval | DAVID BURKHEAD |
| Wood Frame | 10/26/2021 | Partial Approval | DAVID BURKHEAD |
| Drywall Nailing | 10/28/2021 | Partial Approval | DAVID BURKHEAD |
| METHANE-Rough | 11/5/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| Verify Sprinkler Sign Off | 11/5/2021 | Partial Approval | DAVID BURKHEAD |
| Wood Frame | 11/5/2021 | Partial Inspection | DAVID BURKHEAD |
| Interior/Exterior Lathing | 11/10/2021 | Approved | DAVID BURKHEAD |
| Drywall Nailing | 11/12/2021 | Partial Approval | DAVID BURKHEAD |
| Drywall Nailing | 11/19/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| T-Bar Ceiling | 12/7/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| METHANE-Rough | 12/16/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| Verify Sprinkler Sign Off | 12/16/2021 | Partial Approval | DAVID BURKHEAD |
| Wood Frame | 12/16/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| Footing/Foundation/Slab | 12/21/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| METHANE-Barrier | 12/21/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| METHANE-Subgrade | 12/21/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| METHANE-Rough | 12/22/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| Piling/Pier/Caisson | 12/22/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| Verify Sprinkler Sign Off | 12/22/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| Wood Frame | 12/22/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| Wood Frame | 12/29/2021 | Partial Approval | DAVID BURKHEAD |
| Wood Frame | 12/30/2021 | Partial Approval | DAVID BURKHEAD |
| T-Bar Ceiling | 1/10/2022 | Not Ready for Inspection | DAVID BURKHEAD |
| T-Bar Ceiling | 1/14/2022 | Partial Approval | DAVID BURKHEAD |
| Pre-Inspection | 3/9/2022 | Approved | DAVID BURKHEAD |
| Pre-Inspection | 4/4/2022 | Partial Inspection | DAVID BURKHEAD |
| Pre-Inspection | 4/5/2022 | Partial Inspection | DAVID BURKHEAD |
| Pre-Inspection | 4/7/2022 | Approved | DAVID BURKHEAD |
| Pre-Inspection | 4/12/2022 | Partial Inspection | DAVID BURKHEAD |
| Pre-Inspection | 4/18/2022 | Corrections Issued | DAVID BURKHEAD |
| Pre-Inspection | 4/19/2022 | Corrections Issued | DAVID BURKHEAD |
| Special/Order Compliance | 4/19/2022 | Corrections Issued | DAVID BURKHEAD |
| Special/Order Compliance | 4/20/2022 | Approved | DAVID BURKHEAD |
| Pre-Inspection | 5/5/2022 | Corrections Issued | DAVID BURKHEAD |
| Green Building Final | 5/6/2022 | Approved | DAVID BURKHEAD |
| Pre-Inspection | 5/6/2022 | Approved | DAVID BURKHEAD |
| Special/Order Compliance | 10/12/2022 | Partial Inspection | DAVID BURKHEAD |
| Drywall Nailing | 10/31/2022 | Approved | DAVID BURKHEAD |
| Final | 10/31/2022 | OK to Issue CofO | DAVID BURKHEAD |
| Footing/Foundation/Slab | 10/31/2022 | Approved | DAVID BURKHEAD |
| METHANE-Barrier | 10/31/2022 | Approved | DAVID BURKHEAD |
| METHANE-Final | 10/31/2022 | Approved | DAVID BURKHEAD |
| METHANE-Rough | 10/31/2022 | Approved | DAVID BURKHEAD |
| METHANE-Subgrade | 10/31/2022 | Approved | DAVID BURKHEAD |
| Pre-Inspection | 10/31/2022 | Approved | DAVID BURKHEAD |
| SGSOV-Seismic Gas S/O Valve | 10/31/2022 | SGSOV Approved | DAVID BURKHEAD |
| Smoke Detectors | 10/31/2022 | Approved | DAVID BURKHEAD |
| Verify Sprinkler Sign Off | 10/31/2022 | Approved | DAVID BURKHEAD |
| Wood Frame | 10/31/2022 | Approved | DAVID BURKHEAD |