1628 W 81ST ST 90047

Certificate Information: 1628 W 81ST ST 90047

Application / Permit
20010-10000-01334
Plan Check / Job No.
B20LA07081
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED TWO STORY SINGLE FAMILY DWELLING WITH AN ATTACHED 2-CAR GARAGE LOCATED AT REAR OF LOT. 2 OF 2
Permit Issued
Issued on 9/8/2021
Issuing Office
Current Status
CofO Issued on 8/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/22/2020 APPLICANT
Assigned to Plan Check Engineer 5/6/2020 MICHAEL LOPEZ
Corrections Issued 5/14/2020 MICHAEL LOPEZ
Quality Review Completed 6/2/2020 QUAN NGHIEM
Green Plans Picked Up 7/31/2020 APPLICANT
Plan Check Approved 10/28/2020 MICHAEL LOPEZ
Issued 9/8/2021 APPLICANT
Building Plans Picked Up 9/8/2021 APPLICANT
CofO in Progress 8/1/2022 STUART CHAPMAN
Permit Finaled 8/13/2022 DEROLD HAUFF
CofO Issued 8/13/2022 DEROLD HAUFF
Permit Finaled 8/13/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/28/2020 JEANIE LAM
Green Code Cleared 7/29/2020 KHEDER ALRAZAA
Eng Process Fee Ord 176,300 Cleared 7/30/2020 JEANIE LAM
Sewer availability Cleared 7/30/2020 JEANIE LAM
Hydrant and Access approval Cleared 8/25/2020 MATTHEW CRAIG
Low Impact Development Cleared 9/28/2020 ROBIN YAMADA
Roof/Waste drainage to street Cleared 9/29/2020 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/23/2021 Approved FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 10/21/2021 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 10/21/2021 Partial Approval FREDDIE RIVERA
Footing/Foundation/Slab 11/2/2021 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 11/24/2021 Partial Approval FREDDIE RIVERA
BUILDING-Rough-Frame 2/17/2022 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 2/17/2022 Approved FREDDIE RIVERA
Green Building Rough 2/17/2022 Not Ready for Inspection FREDDIE RIVERA
HVAC-Rough 2/17/2022 Not Ready for Inspection FREDDIE RIVERA
PLUMBING-Rough 2/17/2022 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 2/17/2022 Not Ready for Inspection FREDDIE RIVERA
Deputy Wood Construction 2/18/2022 Conditional Approval FREDDIE RIVERA
BUILDING-Rough-Frame 3/2/2022 Not Ready for Inspection FREDDIE RIVERA
Green Building Rough 3/2/2022 Not Ready for Inspection FREDDIE RIVERA
HVAC-Rough 3/2/2022 Approved FREDDIE RIVERA
Interior/Exterior Lathing 3/2/2022 Not Ready for Inspection FREDDIE RIVERA
Verify Sprinkler Sign Off 3/2/2022 Corrections Issued FREDDIE RIVERA
Wood Frame 3/18/2022 Approved ENRIQUE MIRELES
Insulation 3/24/2022 Corrections Issued HORACE FULTZ
Insulation 3/29/2022 Approved ENRIQUE MIRELES
Drywall Nailing 4/4/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 5/24/2022 Approved ENRIQUE MIRELES
Green Building Final 5/24/2022 Approved ENRIQUE MIRELES
Green Building Rough 5/24/2022 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 5/24/2022 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 5/24/2022 Approved ENRIQUE MIRELES
Underground Mechanical 5/24/2022 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 5/24/2022 Approved ENRIQUE MIRELES
Final 7/22/2022 Corrections Issued ENRIQUE MIRELES
Service/Power Release 7/22/2022 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Final 7/29/2022 Approved STUART CHAPMAN
Final 7/29/2022 OK to Issue CofO STUART CHAPMAN
HVAC-Final 7/29/2022 Approved STUART CHAPMAN
PLUMBING-Final 7/29/2022 Approved STUART CHAPMAN
Pre-Inspection 7/29/2022 Approved STUART CHAPMAN
Service/Power Release 7/29/2022 Approved STUART CHAPMAN