- PROPOSED TWO STORY SINGLE FAMILY DWELLING WITH AN ATTACHED 2-CAR GARAGE LOCATED AT REAR OF LOT. 2 OF 2
- Permit Issued
- Issued on 9/8/2021
- Issuing Office
- Current Status
- CofO Issued on 8/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2020 | MICHAEL LOPEZ |
| Corrections Issued | 5/14/2020 | MICHAEL LOPEZ |
| Quality Review Completed | 6/2/2020 | QUAN NGHIEM |
| Green Plans Picked Up | 7/31/2020 | APPLICANT |
| Plan Check Approved | 10/28/2020 | MICHAEL LOPEZ |
| Issued | 9/8/2021 | APPLICANT |
| Building Plans Picked Up | 9/8/2021 | APPLICANT |
| CofO in Progress | 8/1/2022 | STUART CHAPMAN |
| Permit Finaled | 8/13/2022 | DEROLD HAUFF |
| CofO Issued | 8/13/2022 | DEROLD HAUFF |
| Permit Finaled | 8/13/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/28/2020 | JEANIE LAM |
| Green Code | Cleared | 7/29/2020 | KHEDER ALRAZAA |
| Eng Process Fee Ord 176,300 | Cleared | 7/30/2020 | JEANIE LAM |
| Sewer availability | Cleared | 7/30/2020 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 8/25/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 9/28/2020 | ROBIN YAMADA |
| Roof/Waste drainage to street | Cleared | 9/29/2020 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/23/2021 | Approved | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 10/21/2021 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 10/21/2021 | Partial Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 11/2/2021 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 11/24/2021 | Partial Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 2/17/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 2/17/2022 | Approved | FREDDIE RIVERA |
| Green Building Rough | 2/17/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| HVAC-Rough | 2/17/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 2/17/2022 | Approved | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 2/17/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| Deputy Wood Construction | 2/18/2022 | Conditional Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 3/2/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Rough | 3/2/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| HVAC-Rough | 3/2/2022 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 3/2/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 3/2/2022 | Corrections Issued | FREDDIE RIVERA |
| Wood Frame | 3/18/2022 | Approved | ENRIQUE MIRELES |
| Insulation | 3/24/2022 | Corrections Issued | HORACE FULTZ |
| Insulation | 3/29/2022 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 4/4/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 5/24/2022 | Approved | ENRIQUE MIRELES |
| Green Building Final | 5/24/2022 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 5/24/2022 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 5/24/2022 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 5/24/2022 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 5/24/2022 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 5/24/2022 | Approved | ENRIQUE MIRELES |
| Final | 7/22/2022 | Corrections Issued | ENRIQUE MIRELES |
| Service/Power Release | 7/22/2022 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Final | 7/29/2022 | Approved | STUART CHAPMAN |
| Final | 7/29/2022 | OK to Issue CofO | STUART CHAPMAN |
| HVAC-Final | 7/29/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 7/29/2022 | Approved | STUART CHAPMAN |
| Pre-Inspection | 7/29/2022 | Approved | STUART CHAPMAN |
| Service/Power Release | 7/29/2022 | Approved | STUART CHAPMAN |