421 1/4-3/4 E 56TH ST 90011
Certificate Information: 421 1/4-3/4 E 56TH ST 90011
- Application / Permit
- 20010-10000-01332
- Plan Check / Job No.
- B20LA07077
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 2 NEW DETACHED ADUS FOR MULTI-FAMILY PER GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33 (c)(d) AND (g). PER WFPP.
- Permit Issued
- Issued on 1/18/2021
- Issuing Office
- Current Status
- CofO Issued on 12/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2020 | CRYSTEL MAALOUF |
| Corrections Issued | 5/15/2020 | CRYSTEL MAALOUF |
| Quality Review Completed | 5/20/2020 | BILL STUTSMAN |
| Green Plans Picked Up | 12/15/2020 | APPLICANT |
| Plan Check Approved | 12/30/2020 | CRYSTEL MAALOUF |
| Issued | 1/18/2021 | APPLICANT |
| Building Plans Picked Up | 1/19/2021 | APPLICANT |
| CofO in Progress | 12/4/2021 | JOAQUIN GREENOUGH |
| Permit Finaled | 12/17/2021 | DEROLD HAUFF |
| CofO Issued | 12/17/2021 | DEROLD HAUFF |
| Permit Finaled | 12/17/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/4/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/5/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 6/5/2020 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 6/19/2020 | KURT CORRAL |
| Construction near power lines | Cleared | 12/4/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 12/9/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 12/9/2020 | CECILIO NAVARRO |
| Green Code | Cleared | 12/15/2020 | KHEDER ALRAZAA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/2/2021 | Partial Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 3/4/2021 | Corrections Issued | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 3/10/2021 | Conditional Approval | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2021 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 4/6/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| Green Building Rough | 4/6/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 4/6/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| Wood Frame | 4/6/2021 | Partial Approval | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 4/26/2021 | Conditional Approval | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 4/26/2021 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2021 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 4/26/2021 | Approved | ROBERT MCDOWELL |
| Interior/Exterior Lathing | 4/26/2021 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 4/26/2021 | Approved | ROBERT MCDOWELL |
| Insulation | 5/5/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 5/5/2021 | Partial Inspection | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 5/7/2021 | Approved | ROBERT MCDOWELL |
| Underground Mechanical | 5/7/2021 | Approved | ROBERT MCDOWELL |
| Drywall Nailing | 5/10/2021 | Approved | ROBERT MCDOWELL |
| Gas Test | 5/14/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Sewer | 5/14/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 5/14/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| Gas Test | 5/21/2021 | Partial Approval | STUART CHAPMAN |
| HVAC-Rough | 5/21/2021 | Approved | STUART CHAPMAN |
| Insulation | 5/21/2021 | Approved | STUART CHAPMAN |
| Sewer | 5/21/2021 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 9/8/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 9/8/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| HVAC-Final | 9/8/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Final | 9/8/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 9/15/2021 | Corrections Issued | FREDDIE RIVERA |
| Gas Test | 9/15/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| HVAC-Final | 9/15/2021 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Final | 9/21/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Gas Test | 9/21/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Final | 9/21/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 11/5/2021 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 11/5/2021 | Approved | JOAQUIN GREENOUGH |
| Final | 11/5/2021 | Partial Inspection | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 11/5/2021 | Approved | JOAQUIN GREENOUGH |
| Gas Test | 11/5/2021 | Approved | JOAQUIN GREENOUGH |
| Green Building Final | 11/5/2021 | Approved | JOAQUIN GREENOUGH |
| HVAC-Final | 11/5/2021 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 11/5/2021 | SGSOV Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 11/5/2021 | Approved | JOAQUIN GREENOUGH |
| Smoke Detectors | 11/5/2021 | Approved | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 11/5/2021 | Approved | JOAQUIN GREENOUGH |
| Final | 11/6/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Final | 12/2/2021 | OK to Issue CofO | JOAQUIN GREENOUGH |
| Service/Power Release | 12/2/2021 | Approved | JOAQUIN GREENOUGH |