1549 S RIDGELEY DR 90019

Certificate Information: 1549 S RIDGELEY DR 90019

Application / Permit
20010-10000-01324
Plan Check / Job No.
B20LA07013
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
NEW 2 CAR GARAGE 2 OF 2
Permit Issued
Issued on 9/21/2020
Issuing Office
Current Status
CofO Issued on 4/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/23/2020 APPLICANT
Assigned to Plan Check Engineer 5/14/2020 JESSE ARELLANO
Corrections Issued 5/21/2020 JESSE ARELLANO
Quality Review Completed 5/28/2020 BILL STUTSMAN
Building Plans Picked Up 6/1/2020 APPLICANT
Applicant returned to address corrections 7/24/2020 JESSE ARELLANO
Applicant returned to address corrections 7/28/2020 JESSE ARELLANO
Green Plans Picked Up 8/5/2020 APPLICANT
Plan Check Approved 8/23/2020 JESSE ARELLANO
Issued 9/21/2020 APPLICANT
CofO in Progress 3/11/2022 JOSE AVILA
Permit Finaled 4/6/2022 RONALD MYRICK
CofO Issued 4/6/2022 RONALD MYRICK
Permit Finaled 4/6/2022 RONALD MYRICK

Permit Application Clearance Information

Green Code Cleared 7/20/2020 DONALD CRICHLOW

Contact Information

Contractor J M E Construction; Lic. No.: 921816-B 1450 RONAN AVENUE      WILMINGTON, CA 90744
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/16/2020 Approved DAVID CHAN
Footing/Foundation/Slab 11/16/2020 Not Ready for Inspection DAVID CHAN
METHANE-Barrier 11/16/2020 Not Ready for Inspection DAVID CHAN
METHANE-Subgrade 11/16/2020 Not Ready for Inspection DAVID CHAN
Excavation/Setback/Form/Re-Bar 11/23/2020 Approved DAVID CHAN
Footing/Foundation/Slab 11/23/2020 Approved DAVID CHAN
METHANE-Barrier 11/23/2020 Approved DAVID CHAN
METHANE-Subgrade 11/23/2020 Approved DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 1/13/2021 Partial Approval DAVID CHAN
Wood Frame 1/13/2021 Partial Approval DAVID CHAN
Interior/Exterior Lathing 1/19/2021 Not Ready for Inspection DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 2/18/2021 Partial Approval KATHRYN BUTTERWORTH
Insulation 6/16/2021 Approved SCOTT FINNILA
Interior/Exterior Lathing 6/16/2021 Corrections Issued SCOTT FINNILA
Drywall Nailing 7/9/2021 Approved STUART CHAPMAN
Green Building Rough 7/9/2021 Approved STUART CHAPMAN
BUILDING-Rough-Frame 1/20/2022 Partial Approval JOSE AVILA
Green Building Final 1/20/2022 Approved JOSE AVILA
METHANE-Final 1/20/2022 Corrections Issued JOSE AVILA
METHANE-Rough 1/20/2022 Corrections Issued JOSE AVILA
PLUMBING-Final 1/20/2022 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 1/20/2022 SGSOV Not Ready JOSE AVILA
Service/Power Release 1/20/2022 Not Ready for Inspection JOSE AVILA
Smoke Detectors 1/20/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 2/1/2022 Approved JOSE AVILA
Final 2/1/2022 Corrections Issued JOSE AVILA
METHANE-Final 2/1/2022 Approved JOSE AVILA
METHANE-Rough 2/1/2022 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 2/1/2022 SGSOV Not Ready JOSE AVILA
Service/Power Release 2/1/2022 Corrections Issued JOSE AVILA
Final 2/9/2022 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 2/9/2022 SGSOV Approved JOSE AVILA
Service/Power Release 2/9/2022 Approved JOSE AVILA
Final 3/10/2022 OK to Issue CofO JOSE AVILA