1549 S RIDGELEY DR 90019
Certificate Information: 1549 S RIDGELEY DR 90019
- Application / Permit
- 20010-10000-01324
- Plan Check / Job No.
- B20LA07013
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW 2 CAR GARAGE 2 OF 2
- Permit Issued
- Issued on 9/21/2020
- Issuing Office
- Current Status
- CofO Issued on 4/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/14/2020 | JESSE ARELLANO |
| Corrections Issued | 5/21/2020 | JESSE ARELLANO |
| Quality Review Completed | 5/28/2020 | BILL STUTSMAN |
| Building Plans Picked Up | 6/1/2020 | APPLICANT |
| Applicant returned to address corrections | 7/24/2020 | JESSE ARELLANO |
| Applicant returned to address corrections | 7/28/2020 | JESSE ARELLANO |
| Green Plans Picked Up | 8/5/2020 | APPLICANT |
| Plan Check Approved | 8/23/2020 | JESSE ARELLANO |
| Issued | 9/21/2020 | APPLICANT |
| CofO in Progress | 3/11/2022 | JOSE AVILA |
| Permit Finaled | 4/6/2022 | RONALD MYRICK |
| CofO Issued | 4/6/2022 | RONALD MYRICK |
| Permit Finaled | 4/6/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Green Code | Cleared | 7/20/2020 | DONALD CRICHLOW |
Contact Information
| Contractor | J M E Construction; Lic. No.: 921816-B | 1450 RONAN AVENUE WILMINGTON, CA 90744 |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/16/2020 | Approved | DAVID CHAN |
| Footing/Foundation/Slab | 11/16/2020 | Not Ready for Inspection | DAVID CHAN |
| METHANE-Barrier | 11/16/2020 | Not Ready for Inspection | DAVID CHAN |
| METHANE-Subgrade | 11/16/2020 | Not Ready for Inspection | DAVID CHAN |
| Excavation/Setback/Form/Re-Bar | 11/23/2020 | Approved | DAVID CHAN |
| Footing/Foundation/Slab | 11/23/2020 | Approved | DAVID CHAN |
| METHANE-Barrier | 11/23/2020 | Approved | DAVID CHAN |
| METHANE-Subgrade | 11/23/2020 | Approved | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2021 | Partial Approval | DAVID CHAN |
| Wood Frame | 1/13/2021 | Partial Approval | DAVID CHAN |
| Interior/Exterior Lathing | 1/19/2021 | Not Ready for Inspection | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Insulation | 6/16/2021 | Approved | SCOTT FINNILA |
| Interior/Exterior Lathing | 6/16/2021 | Corrections Issued | SCOTT FINNILA |
| Drywall Nailing | 7/9/2021 | Approved | STUART CHAPMAN |
| Green Building Rough | 7/9/2021 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 1/20/2022 | Partial Approval | JOSE AVILA |
| Green Building Final | 1/20/2022 | Approved | JOSE AVILA |
| METHANE-Final | 1/20/2022 | Corrections Issued | JOSE AVILA |
| METHANE-Rough | 1/20/2022 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 1/20/2022 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 1/20/2022 | SGSOV Not Ready | JOSE AVILA |
| Service/Power Release | 1/20/2022 | Not Ready for Inspection | JOSE AVILA |
| Smoke Detectors | 1/20/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 2/1/2022 | Approved | JOSE AVILA |
| Final | 2/1/2022 | Corrections Issued | JOSE AVILA |
| METHANE-Final | 2/1/2022 | Approved | JOSE AVILA |
| METHANE-Rough | 2/1/2022 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 2/1/2022 | SGSOV Not Ready | JOSE AVILA |
| Service/Power Release | 2/1/2022 | Corrections Issued | JOSE AVILA |
| Final | 2/9/2022 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 2/9/2022 | SGSOV Approved | JOSE AVILA |
| Service/Power Release | 2/9/2022 | Approved | JOSE AVILA |
| Final | 3/10/2022 | OK to Issue CofO | JOSE AVILA |