141 N BARRINGTON AVE 90049

Certificate Information: 141 N BARRINGTON AVE 90049

Application / Permit
20010-10000-01230
Plan Check / Job No.
B20LA06635
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW TWO-STORY SINGLE FAMILY DWELLING WITH ATTACHED FRONT GARAGE. ***DO NOT ISSUE CERTIFICATE OF OCCUPANCY UNTIL THE LINKAGE FEE AND ANTI-GRAFITTI AFFIDAVITS ARE RECORDED - A SUPPLEMENTAL PERMIT IS REQUIRED TO CAPTURE THE RECORDED AFFIDAVITS. RETURN TO PLAN CHECK*** GLASS GUARDRAIL IS A DEFERRED SUBMITTAL.
Permit Issued
Issued on 1/6/2021
Issuing Office
Current Status
CofO Issued on 12/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/9/2020 APPLICANT
Assigned to Plan Check Engineer 4/20/2020 ERWIN PASCUA
Corrections Issued 5/4/2020 ERWIN PASCUA
Quality Review Completed 5/5/2020 CHARLES CHANG
Applicant returned to address corrections 7/28/2020 ERWIN PASCUA
Applicant returned to address corrections 7/31/2020 ERWIN PASCUA
Green Plans Picked Up 8/4/2020 APPLICANT
Applicant returned to address corrections 8/7/2020 ERWIN PASCUA
Applicant returned to address corrections 9/18/2020 ERWIN PASCUA
Plan Check Approved 12/22/2020 ERWIN PASCUA
Issued 1/6/2021 APPLICANT
Building Plans Picked Up 11/3/2021 APPLICANT
CofO in Progress 11/10/2022 CARLOS MATAMOROS
Permit Finaled 12/17/2022 DANIEL ORRANTE
CofO Issued 12/17/2022 DANIEL ORRANTE
Permit Finaled 12/17/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/9/2020 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 6/10/2020 HISASHI KOBAYAKAWA
Sewer availability Cleared 6/10/2020 HISASHI KOBAYAKAWA
CPC Cleared 6/18/2020 RUBEN VASQUEZ
Tract Map conditions Cleared 6/18/2020 RUBEN VASQUEZ
Trees in Parkway Cleared 7/13/2020 JOHN KIM
Hydrant and Access approval Cleared 7/17/2020 KURT CORRAL
Green Code Cleared 8/4/2020 DONALD CRICHLOW
Excavation more than 5-ft deep Cleared 10/30/2020 CALOSHA APPROVED
GPI Written Notices Cleared 10/30/2020 ERWIN PASCUA
Grading Pre-Inspection Cleared 10/30/2020 ERWIN PASCUA
Low Impact Development Cleared 12/8/2020 ANDRES COVARRUBIAS
Permit Cleared 12/15/2020 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 12/17/2020 HISASHI KOBAYAKAWA

Contact Information

Architect Brookman,, Alan; Lic. No.: C32503 200 S. VISTA BONITA AVENUE      GLENDORA, CA 91741
Contractor Hartman Baldwin Inc; Lic. No.: 653340-B 100 WEST FOOTHILL BLVD      CLAREMONT, CA 91711
Engineer Tang,, Che Leng; Lic. No.: S4433 6171 OAKRIDGE CT      RANCHO CUCAMONGA, CA 91739
Engineer Varela,, Gregorio; Lic. No.: C81201 1108 S ADAMS ST      GLENDALE, CA 91205
Landscape Architect Walton,, Jamie D; Lic. No.: LA4113 1793 W ARROW HIGHWAY      UPLAND, CA 91786

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/20/2021 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 4/16/2021 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 4/16/2021 Corrections Issued CARLOS MATAMOROS
Footing/Foundation/Slab 4/27/2021 Not Ready for Inspection CARLOS MATAMOROS
Underground Mechanical 4/27/2021 Approved CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 4/29/2021 Not Ready for Inspection CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 4/30/2021 Not Ready for Inspection CARLOS MATAMOROS
Footing/Foundation/Slab 5/5/2021 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 5/6/2021 Conditional Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 5/14/2021 Conditional Approval CARLOS MATAMOROS
Footing/Foundation/Slab 5/20/2021 Corrections Issued CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 5/24/2021 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 6/10/2021 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 6/16/2021 Conditional Approval CARLOS MATAMOROS
Underground Mechanical 6/28/2021 Partial Approval CARLOS MATAMOROS
Underground Mechanical 7/2/2021 Approved CARLOS MATAMOROS
Underground Mechanical 7/7/2021 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 7/8/2021 Partial Approval CARLOS MATAMOROS
Pre-Inspection 7/9/2021 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 7/21/2021 Conditional Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 7/29/2021 Conditional Approval CARLOS MATAMOROS
Footing/Foundation/Slab 7/29/2021 Partial Approval CARLOS MATAMOROS
Deputy Steel/Welding 8/4/2021 Conditional Approval CARLOS MATAMOROS
Footing/Foundation/Slab 8/5/2021 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 8/6/2021 Conditional Approval DANIEL ORRANTE
Floor/Roof Diaphrgm/Shear Wall 9/15/2021 Conditional Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 12/13/2021 Approved CARLOS MATAMOROS
Deputy Drilled-In Anchors 12/16/2021 Conditional Approval CARLOS MATAMOROS
Deputy Wood Construction 12/16/2021 Conditional Approval CARLOS MATAMOROS
ELECTRICAL-Rough 2/7/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 2/7/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 2/7/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 2/9/2022 Corrections Issued CARLOS MATAMOROS
BUILDING-Rough-Frame 2/10/2022 Partial Approval CARLOS MATAMOROS
Green Building Rough 2/10/2022 Partial Approval CARLOS MATAMOROS
Verify Sprinkler Sign Off 2/10/2022 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 2/15/2022 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Rough 2/15/2022 Partial Approval CARLOS MATAMOROS
Green Building Rough 2/15/2022 Partial Approval CARLOS MATAMOROS
HVAC-Rough 2/15/2022 Partial Approval CARLOS MATAMOROS
PLUMBING-Rough 2/15/2022 Partial Approval CARLOS MATAMOROS
BUILDING-Rough-Frame 2/18/2022 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Rough 2/18/2022 Partial Approval BRENDAN LOONEY
Green Building Rough 2/18/2022 Not Ready for Inspection BRENDAN LOONEY
HVAC-Rough 2/18/2022 Corrections Issued BRENDAN LOONEY
PLUMBING-Rough 2/18/2022 Partial Approval BRENDAN LOONEY
BUILDING-Rough-Frame 3/1/2022 Partial Approval CARLOS MATAMOROS
ELECTRICAL-Rough 3/1/2022 Approved CARLOS MATAMOROS
Green Building Rough 3/1/2022 Approved CARLOS MATAMOROS
HVAC-Rough 3/1/2022 Corrections Issued CARLOS MATAMOROS
PLUMBING-Rough 3/1/2022 Approved CARLOS MATAMOROS
Insulation 3/8/2022 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 3/8/2022 Not Ready for Inspection CARLOS MATAMOROS
Drywall Nailing 3/16/2022 Approved MICHAEL PELHAM
Interior/Exterior Lathing 3/16/2022 Partial Approval MICHAEL PELHAM
Smoke Detectors 3/16/2022 Corrections Issued MICHAEL PELHAM
Pre-Inspection 3/31/2022 Approved CARLOS MATAMOROS
Pre-Inspection 3/31/2022 Corrections Issued MICHAEL PELHAM
Interior/Exterior Lathing 4/4/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Shower Pan 4/4/2022 Approved GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 5/3/2022 Partial Inspection MICHAEL PELHAM
Special/Order Compliance 5/18/2022 Partial Inspection MICHAEL PELHAM
Gas Test 6/17/2022 Corrections Issued JOHN KIDWELL
Sewer 6/23/2022 Approved CARLOS MATAMOROS
Underground Mechanical 6/23/2022 Approved CARLOS MATAMOROS
Gas Test 7/22/2022 Not Ready for Inspection CARLOS MATAMOROS
Wood Frame 7/22/2022 Not Ready for Inspection CARLOS MATAMOROS
Final 7/25/2022 Corrections Issued MICHAEL PELHAM
Gas Test 7/29/2022 Approved CARLOS MATAMOROS
HVAC-Final 7/29/2022 Corrections Issued CARLOS MATAMOROS
PLUMBING-Final 7/29/2022 Partial Inspection CARLOS MATAMOROS
ELECTRICAL-Final 8/4/2022 Not Ready for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 8/8/2022 Not Ready for Inspection JUAN VALENZUELA
Final 8/8/2022 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 8/8/2022 Not Ready for Inspection JUAN VALENZUELA
Green Building Final 8/8/2022 Corrections Issued JUAN VALENZUELA
HVAC-Final 8/8/2022 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 8/8/2022 SGSOV Not Ready JUAN VALENZUELA
Service/Power Release 8/8/2022 Not Ready for Inspection JUAN VALENZUELA
Smoke Detectors 8/8/2022 Approved JUAN VALENZUELA
ELECTRICAL-Final 8/10/2022 Corrections Issued ANDREW NAVE
ELECTRICAL-Final 8/12/2022 Approved KENNETH NAGLE
BUILDING-Rough-Frame 8/16/2022 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 8/16/2022 Approved CARLOS MATAMOROS
Green Building Final 8/16/2022 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Final 8/16/2022 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 8/16/2022 SGSOV Not Ready CARLOS MATAMOROS
Service/Power Release 8/16/2022 Not Ready for Inspection CARLOS MATAMOROS
Final 8/18/2022 Not Ready for Inspection MICHAEL PELHAM
SGSOV-Seismic Gas S/O Valve 8/18/2022 SGSOV Not Ready MICHAEL PELHAM
Service/Power Release 8/18/2022 Approved MICHAEL PELHAM
Final 8/22/2022 Corrections Issued MICHAEL PELHAM
Green Building Final 8/22/2022 Approved MICHAEL PELHAM
SGSOV-Seismic Gas S/O Valve 8/22/2022 SGSOV Approved MICHAEL PELHAM
Special/Order Compliance 9/29/2022 Partial Inspection MICHAEL PELHAM
Final 11/10/2022 OK to Issue CofO CARLOS MATAMOROS