3017 N EVA TER 90031
Certificate Information: 3017 N EVA TER 90031
- Application / Permit
- 20010-10000-01229
- Plan Check / Job No.
- B20LA06627
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) TWO STORY DETACHED ACCESSORY BUILDING THAT INCLUDES 2 CAR GARAGE ON GROUND FLOOR AND SECOND FLOOR INCLUDES DETACHED ADU PER STATE LAW GCS 658552.2(e)(1)(B).
- Permit Issued
- Issued on 8/5/2020
- Issuing Office
- Current Status
- Issued on 8/5/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2020 | CRYSTEL MAALOUF |
| Corrections Issued | 5/1/2020 | CRYSTEL MAALOUF |
| Quality Review Completed | 5/4/2020 | BILL STUTSMAN |
| Building Plans Picked Up | 5/7/2020 | APPLICANT |
| Green Plans Picked Up | 5/20/2020 | APPLICANT |
| Applicant returned to address corrections | 7/13/2020 | CRYSTEL MAALOUF |
| Plan Check Approved | 8/5/2020 | CRYSTEL MAALOUF |
| Issued | 8/5/2020 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/1/2020 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/1/2020 | EMIL KYUPELYAN |
| Hydrant and Access approval | Cleared | 5/8/2020 | GEORGE SUCHAND |
| Grading Pre-Inspection | Cleared | 5/11/2020 | PATRICK MISCHLICH |
| Sewer availability | Cleared | 5/18/2020 | EMIL KYUPELYAN |
| Green Code | Cleared | 5/19/2020 | CRYSTEL MAALOUF |
| ZI | Cleared | 6/29/2020 | TERRI OSBORNE |
| Low Impact Development | Cleared | 7/1/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 7/1/2020 | EMIL KYUPELYAN |
| GPI Written Notices | Cleared | 7/27/2020 | CRYSTEL MAALOUF |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/26/2020 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 10/26/2020 | Not Ready for Inspection | STUART CHAPMAN |
| Footing/Foundation/Slab | 11/6/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 12/8/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 1/7/2021 | Partial Approval | OSVALDO PARAMO |
| Masonry Wall/Backfill | 1/21/2021 | Partial Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 3/4/2021 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 3/4/2021 | Partial Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 3/24/2021 | Partial Approval | OSVALDO PARAMO |
| Masonry Wall/Backfill | 3/24/2021 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 5/12/2021 | Partial Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 5/12/2021 | Partial Approval | OSVALDO PARAMO |
| Deputy Drilled-In Anchors | 6/16/2021 | No Access for Inspection | ELMER BLAND |
| Excavation/Setback/Form/Re-Bar | 7/6/2021 | Approved | OSVALDO PARAMO |
| Footing/Foundation/Slab | 7/6/2021 | Partial Approval | OSVALDO PARAMO |