127 W 85TH PL 90003
Certificate Information: 127 W 85TH PL 90003
- Application / Permit
- 20010-10000-01183
- Plan Check / Job No.
- B20LA06575
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 3-STORY SINGLE FAMILY DWELLING AT FRONT HALF OF THE LOT W/ATTACHED ONE CAR GARAGE
- Permit Issued
- Issued on 12/22/2020
- Issuing Office
- Current Status
- CofO Issued on 12/4/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2020 | AMIR DANAI |
| Corrections Issued | 4/23/2020 | AMIR DANAI |
| Quality Review Completed | 5/6/2020 | ARMEN JIVALAGIAN |
| Green Plans Picked Up | 7/7/2020 | APPLICANT |
| Plan Check Approved | 11/12/2020 | AMIR DANAI |
| Issued | 12/22/2020 | APPLICANT |
| Building Plans Picked Up | 12/28/2020 | APPLICANT |
| CofO in Progress | 11/20/2021 | ALEJANDRO DE ARTOLA |
| CofO in Progress | 11/22/2021 | ALEJANDRO DE ARTOLA |
| CofO in Progress | 11/23/2021 | ALEJANDRO DE ARTOLA |
| No Progress | 11/23/2021 | ALEJANDRO DE ARTOLA |
| CofO in Progress | 12/1/2021 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 12/4/2021 | DEROLD HAUFF |
| CofO Issued | 12/4/2021 | DEROLD HAUFF |
| Permit Finaled | 12/4/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| "Q" conditions | Cleared | 5/29/2020 | DANIEL CORONADO |
| Address approval | Cleared | 6/2/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 6/4/2020 | CECILIO NAVARRO |
| Green Code | Cleared | 7/7/2020 | AMIR DANAI |
| Hydrant and Access approval | Cleared | 8/4/2020 | KURT CORRAL |
| Redevelopment Project Area | Cleared | 9/29/2020 | GISELLE CORELLA |
| Low Impact Development | Cleared | 10/1/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 10/1/2020 | CECILIO NAVARRO |
Contact Information
| Contractor | Pacific Coast Builders; Lic. No.: 834794-B | 9277OTTO ST DOWNEY, CA 90240 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 7366 W MANCHESTER AVE #B LOS ANGELES, CA 90045 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/30/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 12/30/2020 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 12/31/2020 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Green Building Rough | 12/31/2020 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 12/31/2020 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 1/4/2021 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2021 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 4/22/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 4/22/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| Rough-Elec/Plmb/HVAC | 4/22/2021 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 4/22/2021 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 4/28/2021 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 4/28/2021 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 4/28/2021 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 5/10/2021 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 5/10/2021 | Partial Approval | DAVID FEILER |
| Drywall Nailing | 5/17/2021 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 5/17/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| Shower Pan | 5/17/2021 | Approved | ALEJANDRO DE ARTOLA |
| Gas Test | 6/29/2021 | Approved | ALEJANDRO DE ARTOLA |
| Sewer | 6/29/2021 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 6/29/2021 | Approved | ALEJANDRO DE ARTOLA |
| Verify Rec and Parks Fee Memo | 6/29/2021 | Approved | ALEJANDRO DE ARTOLA |
| Final | 8/26/2021 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Verify Rec and Parks Fee Memo | 8/26/2021 | Approved | ALEJANDRO DE ARTOLA |
| Gas Test | 9/23/2021 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 9/23/2021 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 10/19/2021 | Approved | ALEJANDRO DE ARTOLA |
| Final | 10/19/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 10/19/2021 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 10/19/2021 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 10/19/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 10/19/2021 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 10/19/2021 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 10/19/2021 | Approved | ALEJANDRO DE ARTOLA |
| Final | 10/28/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 11/19/2021 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Final | 11/22/2021 | OK to Issue CofO | ALEJANDRO DE ARTOLA |