5405 E HUNTINGTON DR NORT 90032
Certificate Information: 5405 E HUNTINGTON DR NORT 90032
- Application / Permit
- 20010-10000-01131
- Plan Check / Job No.
- B20LA06283
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 3 STORY SFD
- Permit Issued
- Issued on 10/2/2020
- Issuing Office
- Current Status
- CofO Issued on 2/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2020 | JESSE ARELLANO |
| Corrections Issued | 4/29/2020 | JESSE ARELLANO |
| Quality Review Completed | 4/30/2020 | BILL STUTSMAN |
| Building Plans Picked Up | 5/19/2020 | APPLICANT |
| Applicant returned to address corrections | 7/17/2020 | JESSE ARELLANO |
| Green Plans Picked Up | 7/28/2020 | APPLICANT |
| Plan Check Approved | 8/27/2020 | JESSE ARELLANO |
| Issued | 10/2/2020 | APPLICANT |
| CofO in Progress | 1/27/2022 | OSVALDO PARAMO |
| CofO in Progress | 1/27/2022 | OSVALDO PARAMO |
| Permit Finaled | 2/3/2022 | RONALD MYRICK |
| CofO Issued | 2/3/2022 | RONALD MYRICK |
| Permit Finaled | 2/3/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 6/1/2020 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2020 | RENZ SORIANO |
| Green Code | Cleared | 6/30/2020 | DONALD CRICHLOW |
Contact Information
| Contractor | Ganpat Properties; Lic. No.: 778755-B | 2606 FOOTHILL BLVD SUITE #E LA CRESCENTA, CA 91214 |
| Engineer | Garcia,, Lionel Jesus; Lic. No.: S4653 | 24702 NARBONNE AVE LOMITA, CA 90717 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/25/2020 | Partial Approval | COREY HUPP |
| Footing/Foundation/Slab | 12/2/2020 | Corrections Issued | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 12/7/2020 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 12/24/2020 | Corrections Issued | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2021 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 1/4/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 1/26/2021 | Partial Approval | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2021 | Partial Approval | CRAIG VAUGHAN |
| Deputy Wood Construction | 4/5/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 4/21/2021 | Corrections Issued | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2021 | Partial Approval | RUBEN SALAS |
| HVAC-Rough | 4/21/2021 | Corrections Issued | RUBEN SALAS |
| PLUMBING-Rough | 4/21/2021 | Corrections Issued | RUBEN SALAS |
| ELECTRICAL-Rough | 4/28/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2021 | Partial Approval | CRAIG VAUGHAN |
| HVAC-Rough | 4/28/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 4/28/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Rough | 5/7/2021 | Approved | OSVALDO PARAMO |
| Shower Pan | 5/7/2021 | Approved | OSVALDO PARAMO |
| Wood Frame | 5/7/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Interior/Exterior Lathing | 5/17/2021 | Partial Approval | COREY HUPP |
| PLUMBING-Rough | 5/17/2021 | Approved | COREY HUPP |
| ELECTRICAL-Rough | 5/18/2021 | Corrections Issued | COREY HUPP |
| BUILDING-Rough-Frame | 5/26/2021 | Approved | COREY HUPP |
| ELECTRICAL-Rough | 5/26/2021 | Approved | COREY HUPP |
| Green Building Rough | 5/26/2021 | Approved | COREY HUPP |
| Verify Sprinkler Sign Off | 5/26/2021 | Approved | COREY HUPP |
| Drywall Nailing | 6/24/2021 | Approved | COREY HUPP |
| Underground Mechanical | 9/2/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Gas Test | 9/9/2021 | Partial Approval | OSVALDO PARAMO |
| Sewer | 9/9/2021 | Approved | OSVALDO PARAMO |
| Underground Mechanical | 9/15/2021 | Approved | COREY HUPP |
| Gas Test | 10/5/2021 | Not Ready for Inspection | ADAM ESCOTO |
| Gas Test | 10/7/2021 | Approved | COREY HUPP |
| ELECTRICAL-Final | 11/2/2021 | Corrections Issued | COREY HUPP |
| PLUMBING-Final | 11/8/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| HVAC-Final | 11/12/2021 | Corrections Issued | OSVALDO PARAMO |
| PLUMBING-Final | 11/12/2021 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 11/16/2021 | Approved | COREY HUPP |
| Footing/Foundation/Slab | 11/17/2021 | Approved | COREY HUPP |
| Green Building Final | 11/17/2021 | Approved | COREY HUPP |
| HVAC-Final | 11/17/2021 | Approved | COREY HUPP |
| SGSOV-Seismic Gas S/O Valve | 11/17/2021 | SGSOV Approved | COREY HUPP |
| Service/Power Release | 11/17/2021 | Approved | COREY HUPP |
| Smoke Detectors | 11/17/2021 | Approved | COREY HUPP |
| Final | 1/14/2022 | Not Ready for Inspection | AMY COLIN |
| Final | 1/25/2022 | OK to Issue CofO | OSVALDO PARAMO |