1816 S MANSFIELD AVE 90019

Certificate Information: 1816 S MANSFIELD AVE 90019

Application / Permit
20010-10000-01128
Plan Check / Job No.
B20LA06275
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT (623 SF) PER ORDINANCE
Permit Issued
Issued on 11/24/2020
Issuing Office
Current Status
CofO Issued on 3/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/7/2020 APPLICANT
Assigned to Plan Check Engineer 4/16/2020 AMIR DANAI
Corrections Issued 4/21/2020 AMIR DANAI
Quality Review Completed 5/6/2020 ARMEN JIVALAGIAN
Building Plans Picked Up 5/19/2020 APPLICANT
Applicant returned to address corrections 10/6/2020 AMIR DANAI
Green Plans Picked Up 10/16/2020 APPLICANT
Plan Check Approved 11/12/2020 AMIR DANAI
Issued 11/24/2020 APPLICANT
CofO in Progress 10/24/2022 JOSE AVILA
Permit Finaled 3/4/2023 DANIEL ORRANTE
CofO Issued 3/4/2023 DANIEL ORRANTE
Permit Finaled 3/4/2023 DANIEL ORRANTE

Permit Application Clearance Information

Hydrant and Access approval Cleared 6/26/2020 MATTHEW CRAIG
Address approval Cleared 7/2/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 7/2/2020 CECILIO NAVARRO
Sewer availability Cleared 7/7/2020 CECILIO NAVARRO
Construction near power lines Cleared 9/13/2020 RIDWAN HARDY
Flood clearance Cleared 9/25/2020 BRYAN GATHUKA
Green Code Cleared 10/12/2020 VIVIAN LAO
Low Impact Development Cleared 10/21/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 11/12/2020 CECILIO NAVARRO

Contact Information

Contractor Pnr Builders Inc; Lic. No.: 1028148-B 21226 VENTURA BLVD #250      WOODLAND HILLS, CA 91364
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/21/2021 Corrections Issued JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 2/5/2021 Approved STUART CHAPMAN
BUILDING-Rough-Frame 3/4/2021 Partial Approval SCOTT FINNILA
PLUMBING-Rough 3/4/2021 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/10/2021 Partial Approval ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 6/3/2021 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 7/8/2021 Corrections Issued STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 7/8/2021 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 7/12/2021 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 7/12/2021 Approved STUART CHAPMAN
FLOOD-Proofing Certificate 7/12/2021 Approved STUART CHAPMAN
Green Building Rough 7/12/2021 Corrections Issued STUART CHAPMAN
HVAC-Rough 7/12/2021 Conditional Approval STUART CHAPMAN
PLUMBING-Rough 7/12/2021 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 7/12/2021 Approved STUART CHAPMAN
Underground Mechanical 11/24/2021 Approved JOSE AVILA
FLOOD-Elevation Certificate 1/13/2022 Approved JOSE AVILA
Footing/Foundation/Slab 1/13/2022 Partial Approval JOSE AVILA
BUILDING-Rough-Frame 1/20/2022 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 1/20/2022 Approved JOSE AVILA
Green Building Rough 1/20/2022 Corrections Issued JOSE AVILA
HVAC-Rough 1/20/2022 Approved JOSE AVILA
PLUMBING-Rough 1/20/2022 Approved JOSE AVILA
Interior/Exterior Lathing 1/25/2022 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 1/28/2022 Approved JOSE AVILA
Green Building Rough 1/28/2022 Approved JOSE AVILA
Interior/Exterior Lathing 1/28/2022 Approved JOSE AVILA
Insulation 2/2/2022 Approved JOSE AVILA
Drywall Nailing 2/4/2022 Approved JOSE AVILA
Underground Mechanical 3/4/2022 Corrections Issued JOSE AVILA
Final 7/11/2022 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 7/11/2022 Approved JOSE AVILA
Green Building Final 7/11/2022 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 7/11/2022 SGSOV Approved JOSE AVILA
Service/Power Release 7/11/2022 Corrections Issued JOSE AVILA
Smoke Detectors 7/11/2022 Approved JOSE AVILA
Final 7/25/2022 Corrections Issued JOSE AVILA
Gas Test 7/25/2022 Approved JOSE AVILA
Service/Power Release 7/25/2022 Approved JOSE AVILA
Final 8/15/2022 Corrections Issued JOSE AVILA
Final 10/24/2022 OK to Issue CofO JOSE AVILA