7455 S MCCONNELL AVE 90045
Certificate Information: 7455 S MCCONNELL AVE 90045
- Application / Permit
- 20010-10000-01117
- Plan Check / Job No.
- B20LA06227
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ONE-STORY DETACEHD ACCESSORY DWELLING UNIT PER ORDINANCE
- Permit Issued
- Issued on 3/31/2022
- Issuing Office
- Current Status
- Permit Closed on 8/21/2025
- Certificate of Occupancy
- Permit Closed More Information
Permit Application Status History
| Submitted | 4/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/23/2020 | ARSALAN SHABESTARI |
| Corrections Issued | 5/4/2020 | ARSALAN SHABESTARI |
| Quality Review Completed | 5/15/2020 | HERNAN ARREOLA |
| Applicant returned to address corrections | 5/22/2020 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 6/11/2020 | ARSALAN SHABESTARI |
| Green Plans Picked Up | 8/12/2020 | APPLICANT |
| Applicant returned to address corrections | 8/14/2020 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 9/21/2020 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 9/23/2020 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 1/29/2021 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 4/5/2021 | ARSALAN SHABESTARI |
| Plan Check Approved | 4/27/2021 | ARSALAN SHABESTARI |
| Plan Check Approved | 6/24/2021 | ARSALAN SHABESTARI |
| Issued | 3/31/2022 | APPLICANT |
| Building Plans Picked Up | 4/8/2022 | APPLICANT |
| Permit Closed | 8/21/2025 | DAVID FEILER |
Permit Application Clearance Information
| ZA Case | Cleared | 6/3/2020 | ANACANY HURTADO |
| Excavation more than 5-ft deep | Cleared | 6/15/2020 | CALOSHA APPROVED |
| Eng Process Fee Ord 176,300 | Cleared | 6/26/2020 | DINAH GARIN |
| Sewer availability | Cleared | 6/26/2020 | DINAH GARIN |
| Construction near power lines | Cleared | 7/29/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 7/29/2020 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 8/10/2020 | MATTHEW CRAIG |
| Green Code | Cleared | 8/12/2020 | VIVIAN LAO |
| Low Impact Development | Cleared | 10/2/2020 | ORVAL HERNANDEZ-MARCI |
| Address approval | Cleared | 10/20/2020 | DINAH GARIN |
| Miscellaneous | Cleared | 10/26/2020 | KATHLEEN LEE |
| Roof/Waste drainage to street | Cleared | 10/26/2020 | KATHLEEN LEE |
Contact Information
| Contractor | Liel Construction Inc; Lic. No.: 929105-B | 11690 OVERLAND DRIVE FONTANA, CA 92337 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 6/2/2022 | Approved | MICHAEL PELHAM |
| Piling/Pier/Caisson | 7/29/2022 | Partial Approval | BOBBY KEY |
| Deputy Reinf. Concrete | 5/29/2025 | Conditional Approval | JESUS PINEDA |
| Special/Order Compliance | 8/21/2025 | Permit Closed | DAVID FEILER |