7226 N ZELZAH AVE 91335

Certificate Information: 7226 N ZELZAH AVE 91335

Application / Permit
20010-10000-01111
Plan Check / Job No.
B20LA06173
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ONE STORY ADU (20' X 15' 6") PER LAMC SECTION 12.22A.33(c) and (d)
Permit Issued
Issued on 11/6/2020
Issuing Office
Current Status
CofO Issued on 9/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/9/2020 APPLICANT
Assigned to Plan Check Engineer 4/9/2020 RACHEL BEYENE
Corrections Issued 4/9/2020 RACHEL BEYENE
Plan Check Approved 7/28/2020 LUKE GONZALES
Issued 11/6/2020 APPLICANT
Building Plans Picked Up 11/10/2020 APPLICANT
CofO in Progress 8/2/2025 ROBERT GOLD
Permit Finaled 9/9/2025 MICHAEL PELHAM
CofO Issued 9/9/2025 MICHAEL PELHAM
Permit Finaled 9/9/2025 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 7/14/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 7/14/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 7/15/2020 ADRIAN CASTRO
Sewer availability Cleared 7/15/2020 ADRIAN CASTRO

Contact Information

Contractor Levet Inc; Lic. No.: 1027447-B 1110 SONORA AVE #101      GLENDALE, CA 91201
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 1/8/2021 Approved VINCENT HANLEY
Underground Mechanical 1/8/2021 Partial Approval VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 1/19/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 4/9/2021 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 4/9/2021 Approved VINCENT HANLEY
Green Building Rough 4/9/2021 Approved VINCENT HANLEY
HVAC-Rough 4/9/2021 Approved VINCENT HANLEY
PLUMBING-Rough 4/9/2021 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 4/9/2021 Not Ready for Inspection VINCENT HANLEY
Wood Frame 4/9/2021 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 4/16/2021 Approved VINCENT HANLEY
Insulation 4/16/2021 Approved VINCENT HANLEY
Drywall Nailing 5/13/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 7/15/2021 Partial Approval VINCENT HANLEY
Final 7/15/2021 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 7/15/2021 Approved VINCENT HANLEY
Green Building Final 7/15/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 7/15/2021 SGSOV Approved VINCENT HANLEY
Service/Power Release 7/15/2021 Approved VINCENT HANLEY
Smoke Detectors 7/15/2021 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 7/15/2021 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 8/2/2025 Approved ROBERT GOLD
Final 8/2/2025 OK to Issue CofO ROBERT GOLD