1340 S CLUB VIEW DR 90024
Certificate Information: 1340 S CLUB VIEW DR 90024
- Application / Permit
- 20010-10000-01109
- Plan Check / Job No.
- B20LA06165
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 2 STORY SINGLE FAMILY DWELLING WITH AN ATTACHED 2-CAR GARAGE OVER BASEMENT. ***SPRINKLERED PER NFPA 13D*** 1 OF 5
- Permit Issued
- Issued on 5/6/2021
- Issuing Office
- Current Status
- Issued on 5/6/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/30/2020 | MICHAEL LOPEZ |
| Corrections Issued | 5/7/2020 | MICHAEL LOPEZ |
| Quality Review Completed | 5/12/2020 | QUAN NGHIEM |
| Building Plans Picked Up | 5/14/2020 | APPLICANT |
| Applicant returned to address corrections | 9/1/2020 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 9/2/2020 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 11/5/2020 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 2/5/2021 | MICHAEL LOPEZ |
| Green Plans Picked Up | 3/22/2021 | APPLICANT |
| Applicant returned to address corrections | 4/22/2021 | MICHAEL LOPEZ |
| Plan Check Approved | 5/6/2021 | MICHAEL LOPEZ |
| Issued | 5/6/2021 | APPLICANT |
Permit Application Clearance Information
| Work Adjacent to Public Way | Cleared | 6/3/2020 | SAUL GARCIA |
| Permit | Cleared | 6/5/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/9/2020 | DINAH GARIN |
| Sewer availability | Cleared | 6/9/2020 | DINAH GARIN |
| Trees in Parkway | Cleared | 7/13/2020 | JOHN KIM |
| Hydrant and Access approval | Cleared | 8/25/2020 | MATTHEW CRAIG |
| GPI Written Notices | Cleared | 8/27/2020 | KIRK LINKLATER |
| Grading Pre-Inspection | Cleared | 8/27/2020 | KIRK LINKLATER |
| Excavation more than 5-ft deep | Cleared | 12/3/2020 | CALOSHA APPROVED |
| Low Impact Development | Cleared | 12/30/2020 | ANDRES COVARRUBIAS |
| Green Code | Cleared | 1/21/2021 | MICHAEL LOPEZ |
| Roof/Waste drainage to street | Cleared | 2/2/2021 | DINAH GARIN |
Contact Information
| Architect | Kostic,, Vasa; Lic. No.: C10740 | 1827-10TH ST_#4 SANTA MONICA, CA 90404 |
| Contractor | Owner-Builder | , |
| Engineer | Azarmy,, Cyrus; Lic. No.: L9404 | 20206 ARCHWOOD ST WINNETKA, CA 91306 |
| Engineer | Mahmoudkhani,, Behnam; Lic. No.: C88488 | 321 E FAIRVIEW AVE APT 307 GLENDALE, CA 91207 |
| Engineer | Pirbadian,, Amir; Lic. No.: C72413 | 5435 BALBOA BLVD 214 ENCINO, CA 91342 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 5/24/2021 | Corrections Issued | ANTHONY MCDOWALL |
| Deputy Methane Barrier | 8/16/2021 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 8/26/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| METHANE-Barrier | 8/26/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| METHANE-Subgrade | 8/26/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Excavation/Setback/Form/Re-Bar | 8/30/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Reinforced Concrete Frame | 9/16/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Reinforced Concrete Frame | 10/14/2021 | Partial Approval | KENNETH NAGLE |
| Underground Mechanical | 10/18/2021 | Partial Approval | BRENDAN LOONEY |
| METHANE-Subgrade | 10/28/2021 | Partial Approval | BRENDAN LOONEY |
| Footing/Foundation/Slab | 11/9/2021 | Corrections Issued | BRENDAN LOONEY |
| METHANE-Barrier | 11/9/2021 | Conditional Approval | BRENDAN LOONEY |
| METHANE-Subgrade | 11/9/2021 | Approved | BRENDAN LOONEY |
| Footing/Foundation/Slab | 11/10/2021 | Approved | BRENDAN LOONEY |
| METHANE-Barrier | 11/10/2021 | Approved | BRENDAN LOONEY |
| Reinforced Concrete Frame | 12/7/2021 | Partial Approval | BRENDAN LOONEY |
| Deputy Reinf. Concrete | 12/8/2021 | Conditional Approval | BRENDAN LOONEY |
| Deputy Steel/Welding | 1/6/2022 | Conditional Approval | BRENDAN LOONEY |
| Deputy Steel/Welding | 1/7/2022 | Conditional Approval | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2022 | Conditional Approval | BRENDAN LOONEY |
| Structural Steel Frame | 1/14/2022 | Conditional Approval | BRENDAN LOONEY |
| Deputy Wood Construction | 5/24/2023 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 7/6/2023 | Corrections Issued | STEPHANIE SWANSON |
| Sewer | 7/6/2023 | Corrections Issued | STEPHANIE SWANSON |
| Sewer | 7/11/2023 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 8/23/2023 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 8/23/2023 | Partial Approval | STEPHANIE SWANSON |
| Special/Order Compliance | 8/23/2023 | Partial Inspection | BEN MOLSTAD |
| Special/Order Compliance | 8/23/2023 | Partial Inspection | MICHAEL PELHAM |
| Special/Order Compliance | 8/23/2023 | Partial Inspection | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2023 | Partial Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 10/4/2023 | Corrections Issued | STEPHANIE SWANSON |
| Masonry Wall/Backfill | 10/4/2023 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2023 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 10/19/2023 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 10/19/2023 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2023 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 10/19/2023 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2023 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 10/23/2023 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 10/23/2023 | Conditional Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 12/19/2023 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Rough | 12/19/2023 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 12/19/2023 | Partial Approval | STEPHANIE SWANSON |
| METHANE-Rough | 12/19/2023 | Corrections Issued | STEPHANIE SWANSON |
| Verify Sprinkler Sign Off | 12/19/2023 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 3/14/2024 | Conditional Approval | STEPHANIE SWANSON |
| METHANE-Rough | 3/14/2024 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 3/22/2024 | Conditional Approval | STEPHANIE SWANSON |
| HVAC-Rough | 3/22/2024 | Approved | STEPHANIE SWANSON |
| Insulation | 3/22/2024 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 4/4/2024 | Approved | MICHAEL PELHAM |
| Smoke Detectors | 4/4/2024 | Corrections Issued | MICHAEL PELHAM |
| Interior/Exterior Lathing | 4/26/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Shower Pan | 4/26/2024 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 4/29/2024 | Conditional Approval | STEPHANIE SWANSON |
| Shower Pan | 4/29/2024 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 5/1/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Shower Pan | 5/1/2024 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 5/17/2024 | Approved | STEPHANIE SWANSON |
| Shower Pan | 5/17/2024 | Approved | STEPHANIE SWANSON |
| Final | 1/15/2026 | Corrections Issued | CHRISTOPHER WILSON |
| PLUMBING-Final | 2/9/2026 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Final | 4/27/2026 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Final | 4/28/2026 | Approved | RYAN SALAZAR |
| HVAC-Final | 4/29/2026 | Not Ready for Inspection | RYAN SALAZAR |
| ELECTRICAL-Final | 5/1/2026 | Corrections Issued | CHRISTOPHER WILSON |
| HVAC-Final | 6/1/2026 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Final | 7/6/2026 | Approved | DAVID SCANTLIN |
| Service/Power Release | 7/15/2026 | Approved | DAVID SCANTLIN |