218-220 E 105TH ST 90003

Certificate Information: 218-220 E 105TH ST 90003

Application / Permit
20010-10000-01107
Plan Check / Job No.
B20LA06152
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW FULLY SPRINKLERED 2 STORY DUPLEX WITH ATTACHED 1-CAR AND ATTACHED 2-CAR GARAGES.
Permit Issued
Issued on 11/2/2020
Issuing Office
Current Status
CofO Issued on 6/24/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/2/2020 APPLICANT
Assigned to Plan Check Engineer 4/23/2020 SAMUEL GONZALEZ
Corrections Issued 4/29/2020 SAMUEL GONZALEZ
Quality Review Completed 5/4/2020 LAWRENCE QUIRANTE
Green Plans Picked Up 8/12/2020 APPLICANT
Applicant returned to address corrections 9/17/2020 SAMUEL GONZALEZ
Plan Check Approved 10/26/2020 SAMUEL GONZALEZ
Issued 11/2/2020 APPLICANT
Building Plans Picked Up 11/5/2020 APPLICANT
CofO in Progress 5/13/2021 EUGENE CASSIDY
Permit Finaled 6/24/2021 DEROLD HAUFF
CofO Issued 6/24/2021 DEROLD HAUFF
Permit Finaled 6/24/2021 DEROLD HAUFF

Permit Application Clearance Information

Hydrant and Access approval Cleared 6/18/2020 MATTHEW CRAIG
Eng Process Fee Ord 176,300 Cleared 6/19/2020 CECILIO NAVARRO
Permit Cleared 6/19/2020 CECILIO NAVARRO
Address approval Cleared 7/21/2020 CECILIO NAVARRO
Community Plan Implem. Overlay Cleared 7/28/2020 TERRI OSBORNE
Trees in Parkway Cleared 7/28/2020 JOHN KIM
Green Code Cleared 8/4/2020 KHEDER ALRAZAA
Sewer availability Cleared 8/4/2020 CECILIO NAVARRO
Low Impact Development Cleared 8/28/2020 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 8/31/2020 CELINA MORENO

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/15/2020 Approved EUGENE CASSIDY
Deputy Reinf. Concrete 12/16/2020 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 12/30/2020 Partial Approval EUGENE CASSIDY
Sewer 12/30/2020 Approved EUGENE CASSIDY
Underground Mechanical 12/30/2020 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 12/30/2020 Not Ready for Inspection EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 1/4/2021 Partial Approval EUGENE CASSIDY
Insulation 1/4/2021 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 1/11/2021 Partial Approval JOHN KLARIN
Deputy Wood Construction 1/22/2021 Conditional Approval WILLIAM ROSE
Floor/Roof Diaphrgm/Shear Wall 1/22/2021 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 1/29/2021 Approved EUGENE CASSIDY
ELECTRICAL-Rough 1/29/2021 Approved EUGENE CASSIDY
Green Building Rough 1/29/2021 Approved EUGENE CASSIDY
HVAC-Rough 1/29/2021 Approved EUGENE CASSIDY
PLUMBING-Rough 1/29/2021 Approved EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 1/29/2021 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 1/29/2021 Approved EUGENE CASSIDY
Insulation 2/1/2021 Approved EUGENE CASSIDY
Drywall Nailing 2/17/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 2/17/2021 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 4/12/2021 SGSOV Not Ready EUGENE CASSIDY
ELECTRICAL-Final 4/30/2021 Approved EUGENE CASSIDY
Final 4/30/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 4/30/2021 Approved EUGENE CASSIDY
HVAC-Final 4/30/2021 Approved EUGENE CASSIDY
PLUMBING-Final 4/30/2021 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 4/30/2021 SGSOV Approved EUGENE CASSIDY
Service/Power Release 4/30/2021 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 4/30/2021 Approved EUGENE CASSIDY
Final 5/13/2021 OK to Issue CofO EUGENE CASSIDY
Service/Power Release 5/13/2021 Approved EUGENE CASSIDY