218-220 E 105TH ST 90003
Certificate Information: 218-220 E 105TH ST 90003
- Application / Permit
- 20010-10000-01107
- Plan Check / Job No.
- B20LA06152
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW FULLY SPRINKLERED 2 STORY DUPLEX WITH ATTACHED 1-CAR AND ATTACHED 2-CAR GARAGES.
- Permit Issued
- Issued on 11/2/2020
- Issuing Office
- Current Status
- CofO Issued on 6/24/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/23/2020 | SAMUEL GONZALEZ |
| Corrections Issued | 4/29/2020 | SAMUEL GONZALEZ |
| Quality Review Completed | 5/4/2020 | LAWRENCE QUIRANTE |
| Green Plans Picked Up | 8/12/2020 | APPLICANT |
| Applicant returned to address corrections | 9/17/2020 | SAMUEL GONZALEZ |
| Plan Check Approved | 10/26/2020 | SAMUEL GONZALEZ |
| Issued | 11/2/2020 | APPLICANT |
| Building Plans Picked Up | 11/5/2020 | APPLICANT |
| CofO in Progress | 5/13/2021 | EUGENE CASSIDY |
| Permit Finaled | 6/24/2021 | DEROLD HAUFF |
| CofO Issued | 6/24/2021 | DEROLD HAUFF |
| Permit Finaled | 6/24/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 6/18/2020 | MATTHEW CRAIG |
| Eng Process Fee Ord 176,300 | Cleared | 6/19/2020 | CECILIO NAVARRO |
| Permit | Cleared | 6/19/2020 | CECILIO NAVARRO |
| Address approval | Cleared | 7/21/2020 | CECILIO NAVARRO |
| Community Plan Implem. Overlay | Cleared | 7/28/2020 | TERRI OSBORNE |
| Trees in Parkway | Cleared | 7/28/2020 | JOHN KIM |
| Green Code | Cleared | 8/4/2020 | KHEDER ALRAZAA |
| Sewer availability | Cleared | 8/4/2020 | CECILIO NAVARRO |
| Low Impact Development | Cleared | 8/28/2020 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 8/31/2020 | CELINA MORENO |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/15/2020 | Approved | EUGENE CASSIDY |
| Deputy Reinf. Concrete | 12/16/2020 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 12/30/2020 | Partial Approval | EUGENE CASSIDY |
| Sewer | 12/30/2020 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 12/30/2020 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 12/30/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2021 | Partial Approval | EUGENE CASSIDY |
| Insulation | 1/4/2021 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2021 | Partial Approval | JOHN KLARIN |
| Deputy Wood Construction | 1/22/2021 | Conditional Approval | WILLIAM ROSE |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2021 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 1/29/2021 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 1/29/2021 | Approved | EUGENE CASSIDY |
| Green Building Rough | 1/29/2021 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 1/29/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 1/29/2021 | Approved | EUGENE CASSIDY |
| Rough-Elec/Plmb/HVAC | 1/29/2021 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 1/29/2021 | Approved | EUGENE CASSIDY |
| Insulation | 2/1/2021 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 2/17/2021 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 2/17/2021 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 4/12/2021 | SGSOV Not Ready | EUGENE CASSIDY |
| ELECTRICAL-Final | 4/30/2021 | Approved | EUGENE CASSIDY |
| Final | 4/30/2021 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 4/30/2021 | Approved | EUGENE CASSIDY |
| HVAC-Final | 4/30/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 4/30/2021 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 4/30/2021 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 4/30/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 4/30/2021 | Approved | EUGENE CASSIDY |
| Final | 5/13/2021 | OK to Issue CofO | EUGENE CASSIDY |
| Service/Power Release | 5/13/2021 | Approved | EUGENE CASSIDY |