558-558 1/2 W 47TH ST 90037

Certificate Information: 558-558 1/2 W 47TH ST 90037

Application / Permit
20010-10000-01100
Plan Check / Job No.
B20LA06133
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2 STORY DUPLEX.
Permit Issued
Issued on 9/22/2020
Issuing Office
Current Status
CofO Issued on 3/26/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/2/2020 APPLICANT
Assigned to Plan Check Engineer 4/16/2020 JOHNNY WU
Corrections Issued 4/22/2020 JOHNNY WU
Quality Review Completed 4/29/2020 LAWRENCE QUIRANTE
Building Plans Picked Up 5/5/2020 APPLICANT
Green Plans Picked Up 6/17/2020 APPLICANT
Applicant returned to address corrections 8/21/2020 JOHNNY WU
Applicant returned to address corrections 8/25/2020 JOHNNY WU
Plan Check Approved 8/31/2020 JOHNNY WU
No Progress 8/31/2020 JOHNNY WU
Plan Check Approved 9/22/2020 JOHNNY WU
Issued 9/22/2020 APPLICANT
CofO in Progress 3/4/2021 ROBERT MCDOWELL
Permit Finaled 3/26/2021 DEROLD HAUFF
CofO Issued 3/26/2021 DEROLD HAUFF
Permit Finaled 3/26/2021 DEROLD HAUFF

Permit Application Clearance Information

ZI Cleared 5/19/2020 TERRI OSBORNE
Green Code Cleared 5/22/2020 VIVIAN LAO
Address approval Cleared 5/26/2020 EMIL KYUPELYAN
Sewer availability Cleared 5/26/2020 EMIL KYUPELYAN
Hydrant and Access approval Cleared 5/27/2020 MATTHEW CRAIG
Eng Process Fee Ord 176,300 Cleared 5/28/2020 EMIL KYUPELYAN
Low Impact Development Cleared 7/13/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 7/16/2020 EMIL KYUPELYAN
Highway dedication Cleared 8/18/2020 ELAINE LEI

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/13/2020 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 10/30/2020 Partial Approval ROBERT MCDOWELL
Underground Mechanical 10/30/2020 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 11/2/2020 Partial Approval JOSEPH MCGARRY
Insulation 11/2/2020 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 11/9/2020 Partial Approval DAVID FEILER
Deputy Wood Construction 11/25/2020 No Access for Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 11/25/2020 Approved ROBERT MCDOWELL
BUILDING-Rough-Frame 12/9/2020 Approved FREDDIE RIVERA
ELECTRICAL-Rough 12/9/2020 Approved FREDDIE RIVERA
Green Building Rough 12/9/2020 Approved FREDDIE RIVERA
HVAC-Rough 12/9/2020 Approved FREDDIE RIVERA
MERV13>=Rough 12/9/2020 Approved FREDDIE RIVERA
PLUMBING-Rough 12/9/2020 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 12/9/2020 Approved FREDDIE RIVERA
Insulation 12/10/2020 Approved ROBERT MCDOWELL
Drywall Nailing 12/22/2020 Approved ROBERT MCDOWELL
Interior/Exterior Lathing 12/22/2020 Approved ROBERT MCDOWELL
Sewer 12/22/2020 Approved ROBERT MCDOWELL
ELECTRICAL-Final 2/24/2021 Approved ROBERT MCDOWELL
Final 2/24/2021 Corrections Issued ROBERT MCDOWELL
Green Building Final 2/24/2021 Approved ROBERT MCDOWELL
HVAC-Final 2/24/2021 Approved ROBERT MCDOWELL
MERV13>=Final 2/24/2021 Approved ROBERT MCDOWELL
PLUMBING-Final 2/24/2021 Approved ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 2/24/2021 SGSOV Approved ROBERT MCDOWELL
Service/Power Release 2/24/2021 Approved ROBERT MCDOWELL
Smoke Detectors 2/24/2021 Approved ROBERT MCDOWELL
Final 3/4/2021 OK to Issue CofO ROBERT MCDOWELL