1021 W 20TH ST 90007
Certificate Information: 1021 W 20TH ST 90007
- Application / Permit
- 20010-10000-01098
- Plan Check / Job No.
- B20LA06125
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 25'X39'-1/2" DETACHED 2-STORY ACCESSORY DWELLING UNIT WITH 1-CAR ATTACHED GARAGE (1189 SQFT).
- Permit Issued
- Issued on 9/4/2020
- Issuing Office
- Current Status
- CofO Issued on 8/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2020 | CHUNG-WEN CHUANG |
| Corrections Issued | 4/30/2020 | CHUNG-WEN CHUANG |
| Quality Review Completed | 5/13/2020 | KESETE HAREGOT |
| Building Plans Picked Up | 5/19/2020 | APPLICANT |
| Green Plans Picked Up | 7/24/2020 | APPLICANT |
| Applicant returned to address corrections | 8/11/2020 | CHUNG-WEN CHUANG |
| Plan Check Approved | 8/28/2020 | CHUNG-WEN CHUANG |
| Issued | 9/4/2020 | APPLICANT |
| CofO in Progress | 1/7/2022 | ADAM ESCOTO |
| No Progress | 6/10/2022 | JOAQUIN GREENOUGH |
| CofO in Progress | 8/9/2022 | KATHRYN BUTTERWORTH |
| Permit Finaled | 8/13/2022 | DEROLD HAUFF |
| CofO Issued | 8/13/2022 | DEROLD HAUFF |
| Permit Finaled | 8/13/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 5/14/2020 | KATIE DEBIASE |
| "Q" conditions | Cleared | 5/21/2020 | MAXFIELD VERMY |
| ZA Case | Cleared | 5/21/2020 | MAXFIELD VERMY |
| ZI | Cleared | 5/21/2020 | MAXFIELD VERMY |
| ZI | Cleared | 5/21/2020 | MAXFIELD VERMY |
| ZI | Cleared | 5/26/2020 | RAFAEL FONTES |
| Address approval | Cleared | 5/27/2020 | JUAN ASHTON |
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2020 | JUAN ASHTON |
| Sewer availability | Cleared | 6/2/2020 | JUAN ASHTON |
| Hydrant and Access approval | Cleared | 6/15/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 7/10/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 7/15/2020 | JEANIE LAM |
| Green Code | Cleared | 7/23/2020 | CHUNG-WEN CHUANG |
Contact Information
| Architect | Zbikowski,, Jeffrey; Lic. No.: C35389 | 5919 S CROSFT AVENUE LOS ANGELES, CA 90056 |
| Contractor | Owner-Builder | , |
| Engineer | Kang,, Danniel; Lic. No.: S6242 | 633 E 223RD ST B CARSON, CA 90745 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/8/2020 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2020 | Partial Approval | ROBERT MCDOWELL |
| Deputy Wood Construction | 9/16/2020 | No Access for Inspection | ELMER BLAND |
| Wood Frame | 9/24/2020 | Partial Approval | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 10/5/2020 | Partial Approval | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 10/5/2020 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 10/5/2020 | Approved | ROBERT MCDOWELL |
| HVAC-Rough | 10/5/2020 | Approved | ROBERT MCDOWELL |
| MERV13>=Rough | 10/5/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 10/5/2020 | Approved | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 10/5/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Shower Pan | 10/9/2020 | Approved | HORACE FULTZ |
| Drywall Nailing | 10/16/2020 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 11/13/2020 | Not Ready for Inspection | DAVID FEILER |
| Final | 11/13/2020 | Not Ready for Inspection | DAVID FEILER |
| Green Building Final | 11/13/2020 | No Access for Inspection | DAVID FEILER |
| MERV13>=Final | 11/13/2020 | Not Ready for Inspection | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 11/13/2020 | SGSOV Not Ready | DAVID FEILER |
| Service/Power Release | 11/13/2020 | Not Ready for Inspection | DAVID FEILER |
| Smoke Detectors | 11/13/2020 | No Access for Inspection | DAVID FEILER |
| Verify Sprinkler Sign Off | 11/13/2020 | Not Ready for Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 11/23/2020 | Conditional Approval | ROBERT MCDOWELL |
| ELECTRICAL-Final | 11/23/2020 | Approved | ROBERT MCDOWELL |
| Final | 11/23/2020 | Corrections Issued | ROBERT MCDOWELL |
| Green Building Final | 11/23/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| HVAC-Final | 11/23/2020 | Approved | ROBERT MCDOWELL |
| MERV13>=Final | 11/23/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 11/23/2020 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 11/23/2020 | SGSOV Approved | ROBERT MCDOWELL |
| Service/Power Release | 11/23/2020 | Corrections Issued | ROBERT MCDOWELL |
| Smoke Detectors | 11/23/2020 | Approved | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 11/23/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 11/29/2021 | Not Ready for Inspection | ADAM ESCOTO |
| Final | 11/29/2021 | Not Ready for Inspection | ADAM ESCOTO |
| Green Building Final | 11/29/2021 | Approved | ADAM ESCOTO |
| Service/Power Release | 11/29/2021 | Conditional Approval | ADAM ESCOTO |
| Verify Sprinkler Sign Off | 11/29/2021 | Approved | ADAM ESCOTO |
| BUILDING-Rough-Frame | 12/2/2021 | Approved | ADAM ESCOTO |
| Final | 12/2/2021 | Not Ready for Inspection | ADAM ESCOTO |
| Service/Power Release | 12/2/2021 | Not Ready for Inspection | ADAM ESCOTO |
| Final | 12/3/2021 | Corrections Issued | ADAM ESCOTO |
| Service/Power Release | 12/3/2021 | Not Ready for Inspection | ADAM ESCOTO |
| Final | 12/15/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Service/Power Release | 12/15/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Final | 1/7/2022 | OK to Issue CofO | ADAM ESCOTO |
| Service/Power Release | 1/7/2022 | Approved | ADAM ESCOTO |
| Special/Order Compliance | 3/4/2022 | Corrections Issued | JOAQUIN GREENOUGH |