1351 W 37TH ST 90007

Certificate Information: 1351 W 37TH ST 90007

Application / Permit
20010-10000-01029
Plan Check / Job No.
B20LA05842
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 3-STORY SINGLE FAMILY DWELLING IN FRONT
Permit Issued
Issued on 11/9/2020
Issuing Office
Current Status
CofO Issued on 9/11/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/2/2020 APPLICANT
Assigned to Plan Check Engineer 4/16/2020 VU NGUYEN
Corrections Issued 5/5/2020 VU NGUYEN
Quality Review Completed 5/5/2020 QUAN NGHIEM
Green Plans Picked Up 8/27/2020 APPLICANT
Applicant returned to address corrections 10/13/2020 VU NGUYEN
Plan Check Approved 10/29/2020 VU NGUYEN
Issued 11/9/2020 APPLICANT
Building Plans Picked Up 11/12/2020 APPLICANT
CofO in Progress 8/10/2021 HORACE FULTZ
Permit Finaled 9/11/2021 DEROLD HAUFF
CofO Issued 9/11/2021 DEROLD HAUFF
Permit Finaled 9/11/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/15/2020 EMIL KYUPELYAN
Sewer availability Cleared 6/15/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 6/17/2020 EMIL KYUPELYAN
Community Plan Implem. Overlay Cleared 6/29/2020 RAFAEL FONTES
Supp. Use District POD/CDO/TDO Cleared 7/10/2020 JASON CHAN
Hydrant and Access approval Cleared 7/30/2020 KURT CORRAL
Green Code Cleared 8/27/2020 DONALD CRICHLOW
Low Impact Development Cleared 10/5/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 10/15/2020 THOMAS LANG

Contact Information

Contractor Emerald Builders And Developers; Lic. No.: 1068007-B 1412 W 22ND STREET      LOS ANGELES, CA 90007
Engineer Salto,, Alvaro; Lic. No.: C83859 7366 W MANCHESTER AVE #B      LOS ANGELES, CA 90045
Engineer Sanchez,, Pablo Beltran; Lic. No.: C86223 1840 S GAFFEY ST 382      SAN PEDRO, CA 90731

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/24/2020 Approved ROBERT MCDOWELL
Excavation/Setback/Form/Re-Bar 12/4/2020 Approved ROBERT MCDOWELL
BUILDING-Rough-Frame 2/17/2021 Approved ROBERT MCDOWELL
ELECTRICAL-Rough 2/17/2021 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 2/17/2021 Approved ROBERT MCDOWELL
Green Building Rough 2/17/2021 Approved ROBERT MCDOWELL
HVAC-Rough 2/17/2021 Approved ROBERT MCDOWELL
Interior/Exterior Lathing 2/17/2021 Approved ROBERT MCDOWELL
METHANE-Rough 2/17/2021 Approved ROBERT MCDOWELL
PLUMBING-Rough 2/17/2021 Approved ROBERT MCDOWELL
Verify Sprinkler Sign Off 2/17/2021 Approved ROBERT MCDOWELL
Insulation 2/19/2021 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 2/24/2021 Partial Approval ROBERT MCDOWELL
Drywall Nailing 3/1/2021 Approved ROBERT MCDOWELL
Insulation 3/1/2021 Approved ROBERT MCDOWELL
Interior/Exterior Lathing 3/1/2021 Approved ROBERT MCDOWELL
PLUMBING-Rough 3/1/2021 Approved ROBERT MCDOWELL
ELECTRICAL-Final 5/12/2021 Approved ROBERT MCDOWELL
Final 5/12/2021 Conditional Approval ROBERT MCDOWELL
Footing/Foundation/Slab 5/12/2021 Approved ROBERT MCDOWELL
Green Building Final 5/12/2021 Approved ROBERT MCDOWELL
HVAC-Final 5/12/2021 Approved ROBERT MCDOWELL
METHANE-Barrier 5/12/2021 Approved ROBERT MCDOWELL
METHANE-Subgrade 5/12/2021 Approved ROBERT MCDOWELL
PLUMBING-Final 5/12/2021 Approved ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 5/12/2021 SGSOV Approved ROBERT MCDOWELL
Service/Power Release 5/12/2021 Approved ROBERT MCDOWELL
Smoke Detectors 5/12/2021 Approved ROBERT MCDOWELL
Final 5/27/2021 OK to Issue CofO ROBERT MCDOWELL
Service/Power Release 8/20/2021 Approved SABAS ALONSO