1624 S AMHERST AVE 90025

Certificate Information: 1624 S AMHERST AVE 90025

Application / Permit
20010-10000-01025
Plan Check / Job No.
B20LA05810
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 2-Story Single Family Dwelling with attached garage
Permit Issued
Issued on 12/30/2020
Issuing Office
Current Status
CofO Issued on 10/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/1/2020 APPLICANT
Assigned to Plan Check Engineer 4/16/2020 DEAN LEE
Corrections Issued 4/23/2020 DEAN LEE
Quality Review Completed 4/30/2020 BILL STUTSMAN
Building Plans Picked Up 5/27/2020 APPLICANT
Applicant returned to address corrections 6/12/2020 DEAN LEE
Applicant returned to address corrections 12/17/2020 DEAN LEE
Green Plans Picked Up 12/21/2020 APPLICANT
Applicant returned to address corrections 12/29/2020 DEAN LEE
Plan Check Approved 12/29/2020 DEAN LEE
Issued 12/30/2020 APPLICANT
CofO in Progress 9/26/2023 CARLOS MATAMOROS
Permit Finaled 10/7/2023 DANIEL ORRANTE
CofO Issued 10/7/2023 DANIEL ORRANTE
Permit Finaled 10/7/2023 DANIEL ORRANTE

Permit Application Clearance Information

Hydrant and Access approval Cleared 7/30/2020 KURT CORRAL
Specific Plan Cleared 8/6/2020 PEDRO AYALA
Address approval Cleared 9/4/2020 DINAH GARIN
Permit Cleared 9/4/2020 DINAH GARIN
Sewer availability Cleared 9/4/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 9/8/2020 DINAH GARIN
Highway dedication Cleared 9/28/2020 RAYMOND MUGAMBWA
ZI Cleared 10/9/2020 DENZEL HENDERSON
Grading Pre-Inspection Cleared 10/20/2020 DEAN LEE
Low Impact Development Cleared 11/16/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 11/19/2020 DINAH GARIN
Green Code Cleared 12/17/2020 VIVIAN LAO

Contact Information

Contractor Owner-Builder       ,
Engineer Khanlou,, Amir; Lic. No.: C87550 10671 HOLMAN AVE   APT 207    LOS ANGELES, CA 90024

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/25/2021 Partial Approval OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 2/16/2021 Partial Approval OGANES TARAKHCHYAN
Deputy Reinf. Concrete 2/18/2021 Partial Approval OGANES TARAKHCHYAN
Sewer 5/15/2021 Not Ready for Inspection EVAN COOPER
Underground Mechanical 5/15/2021 Partial Approval EVAN COOPER
Deputy Steel/Welding 5/17/2021 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 6/1/2021 Partial Approval OGANES TARAKHCHYAN
Green Building Rough 6/1/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Structural Steel Frame 6/1/2021 Partial Approval OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 6/1/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Deputy Reinf. Concrete 6/4/2021 Conditional Approval ADAM ESCOTO
Footing/Foundation/Slab 6/15/2021 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 7/2/2021 Partial Approval OGANES TARAKHCHYAN
Green Building Rough 7/2/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 7/2/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 7/15/2021 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 8/13/2021 Corrections Issued OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 9/1/2021 Corrections Issued OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 1/6/2022 Not Ready for Inspection EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 1/10/2022 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 8/3/2022 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Rough 8/3/2022 Approved JOHN KIDWELL
Green Building Rough 8/3/2022 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Rough 8/3/2022 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 8/3/2022 Not Ready for Inspection JOHN KIDWELL
HVAC-Rough 8/19/2022 Approved JOHN KIDWELL
BUILDING-Rough-Frame 8/22/2022 Approved JOHN KIDWELL
Green Building Rough 8/22/2022 Approved JOHN KIDWELL
Interior/Exterior Lathing 8/22/2022 Partial Approval JOHN KIDWELL
Verify Sprinkler Sign Off 8/22/2022 Approved JOHN KIDWELL
Drywall Nailing 9/13/2022 Corrections Issued DAVID FEILER
Drywall Nailing 9/21/2022 Approved JOHN KIDWELL
Sewer 10/4/2022 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 10/5/2022 Partial Approval EVAN COOPER
Shower Pan 10/31/2022 No Access for Inspection ASHLEY THOMPSON
Shower Pan 11/2/2022 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 11/10/2022 Approved ASHLEY THOMPSON
Pre-Inspection 3/3/2023 Partial Inspection CLAYTON GRAHAM
Gas Test 4/12/2023 Corrections Issued JESUS PINEDA
Gas Test 4/14/2023 Partial Approval HERBERT GIRON
Pre-Inspection 4/24/2023 Partial Inspection JESUS PINEDA
ELECTRICAL-Final 6/12/2023 Approved JESUS PINEDA
Gas Test 6/12/2023 Approved JESUS PINEDA
PLUMBING-Final 6/14/2023 Approved JESUS PINEDA
Service/Power Release 6/26/2023 Approved JESUS PINEDA
HVAC-Final 7/31/2023 Corrections Issued DAVID FEILER
HVAC-Final 8/4/2023 Approved MEL KHACHATOURIAN
Final 9/25/2023 OK to Issue CofO CARLOS MATAMOROS
Green Building Final 9/25/2023 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 9/25/2023 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 9/25/2023 Approved CARLOS MATAMOROS
Structural Steel Frame 9/25/2023 Approved CARLOS MATAMOROS