9542-9544 S HOLMES AVE 90002

Certificate Information: 9542-9544 S HOLMES AVE 90002

Application / Permit
20010-10000-01021
Plan Check / Job No.
B20LA05794
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2 STORY DUPLEX WITH 3 CAR GARAGE ATTACHED
Permit Issued
Issued on 10/6/2020
Issuing Office
Current Status
CofO Issued on 7/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/31/2020 APPLICANT
Assigned to Plan Check Engineer 4/9/2020 JESSE ARELLANO
Corrections Issued 4/29/2020 JESSE ARELLANO
Quality Review Completed 4/30/2020 BILL STUTSMAN
Green Plans Picked Up 7/2/2020 APPLICANT
Applicant returned to address corrections 9/16/2020 JESSE ARELLANO
Plan Check Approved 9/18/2020 JESSE ARELLANO
Issued 10/6/2020 APPLICANT
Building Plans Picked Up 10/7/2020 APPLICANT
CofO in Progress 6/28/2021 ANSON MAGLASANG
CofO Issued 7/1/2021 DEROLD HAUFF
Permit Finaled 7/1/2021 DEROLD HAUFF

Permit Application Clearance Information

Hydrant and Access approval Cleared 6/18/2020 MATTHEW CRAIG
Eng Process Fee Ord 176,300 Cleared 6/19/2020 JUAN ASHTON
Green Code Cleared 7/1/2020 DONALD CRICHLOW
Sewer availability Cleared 8/5/2020 CECILIO NAVARRO
Low Impact Development Cleared 8/12/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 8/26/2020 CELINA MORENO
Address approval Cleared 9/16/2020 CELINA MORENO

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/23/2020 Approved EUGENE CASSIDY
Deputy Seismic Resistance 10/29/2020 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 11/12/2020 Partial Approval EUGENE CASSIDY
Underground Mechanical 11/12/2020 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 11/13/2020 Partial Approval EUGENE CASSIDY
Insulation 11/13/2020 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 11/16/2020 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 11/30/2020 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 12/21/2020 Approved DAVID FEILER
BUILDING-Rough-Frame 1/15/2021 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 1/15/2021 Approved EUGENE CASSIDY
Green Building Rough 1/15/2021 Approved EUGENE CASSIDY
HVAC-Rough 1/15/2021 Approved EUGENE CASSIDY
PLUMBING-Rough 1/15/2021 Partial Approval EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 1/15/2021 Partial Approval EUGENE CASSIDY
Verify Sprinkler Sign Off 1/15/2021 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 1/19/2021 Approved EUGENE CASSIDY
Insulation 1/19/2021 Approved EUGENE CASSIDY
PLUMBING-Rough 1/19/2021 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 1/19/2021 Approved EUGENE CASSIDY
Drywall Nailing 1/26/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 1/26/2021 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 4/16/2021 SGSOV Not Ready EUGENE CASSIDY
ELECTRICAL-Final 4/22/2021 Corrections Issued EUGENE CASSIDY
HVAC-Final 4/22/2021 Approved EUGENE CASSIDY
PLUMBING-Final 4/22/2021 Approved EUGENE CASSIDY
ELECTRICAL-Final 4/28/2021 Approved EUGENE CASSIDY
Final 4/28/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 4/28/2021 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 4/28/2021 SGSOV Approved EUGENE CASSIDY
Service/Power Release 4/28/2021 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 4/28/2021 Approved EUGENE CASSIDY
Final 6/21/2021 Corrections Issued EUGENE CASSIDY
Service/Power Release 6/21/2021 Not Ready for Inspection EUGENE CASSIDY
Final 6/28/2021 OK to Issue CofO ANSON MAGLASANG
Service/Power Release 6/28/2021 Approved ANSON MAGLASANG