New Single-Story Accessory Dwelling Unit.
Permit Issued
Issued on 8/21/2020
Issuing Office
Current Status
CofO Issued on 1/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/31/2020 APPLICANT
Assigned to Plan Check Engineer 4/9/2020 RODOLFO ARIAS
Corrections Issued 4/17/2020 RODOLFO ARIAS
Quality Review Completed 4/22/2020 KEN GILL
Applicant returned to address corrections 5/5/2020 RODOLFO ARIAS
Green Plans Picked Up 5/6/2020 APPLICANT
Applicant returned to address corrections 5/19/2020 RODOLFO ARIAS
Applicant returned to address corrections 5/22/2020 RODOLFO ARIAS
Plan Check Approved 7/13/2020 RODOLFO ARIAS
Issued 8/21/2020 APPLICANT
CofO in Progress 11/5/2021 CHRISTOPHE COCHRAN
CofO in Progress 1/6/2022 CHRISTOPHE COCHRAN
Permit Finaled 1/26/2022 MICHAEL SMITH
CofO Issued 1/26/2022 MICHAEL SMITH
Permit Finaled 1/26/2022 MICHAEL SMITH

Permit Application Clearance Information

Green Code Cleared 4/30/2020 NEGAR NEJAD
Hydrant and Access approval Cleared 5/5/2020 KURT CORRAL
Construction near power lines Cleared 5/6/2020 RIDWAN HARDY
Construction within easement Cleared 5/6/2020 RIDWAN HARDY
Address approval Cleared 5/13/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 5/13/2020 CECILIO NAVARRO
Sewer availability Cleared 5/21/2020 CECILIO NAVARRO
Low Impact Development Cleared 5/27/2020 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 6/29/2020 CECILIO NAVARRO

Contact Information

Contractor Bayaslyan Yesay Eddie Construction Co; Lic. No.: 643783-B 1070 E ANGELENO AVE      BURBANK, CA 91501
Engineer Rahman,, Moksudur; Lic. No.: C69263 14616 MCKENDREE AVE      CHINO, CA 91708

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/11/2020 Corrections Issued BRENDAN LOONEY
PLUMBING-Rough 9/11/2020 Partial Approval BRENDAN LOONEY
Footing/Foundation/Slab 9/17/2020 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 10/20/2020 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Rough 10/20/2020 Partial Approval BRENDAN LOONEY
Green Building Rough 10/20/2020 Not Ready for Inspection BRENDAN LOONEY
HVAC-Rough 10/20/2020 Approved BRENDAN LOONEY
PLUMBING-Rough 10/20/2020 Approved BRENDAN LOONEY
Verify Sprinkler Sign Off 10/20/2020 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 10/29/2020 Approved MATTHEW NELSON
Green Building Rough 10/29/2020 Approved MATTHEW NELSON
Insulation 11/24/2020 Approved BEAU COLLINS
Interior/Exterior Lathing 11/24/2020 Partial Approval BEAU COLLINS
Drywall Nailing 12/10/2020 Approved BRENDAN LOONEY
PLUMBING-Rough 12/10/2020 Approved BRENDAN LOONEY
Shower Pan 12/10/2020 Approved BRENDAN LOONEY
Interior/Exterior Lathing 12/16/2020 Approved BRENDAN LOONEY
ELECTRICAL-Rough 12/24/2020 Approved BRENDAN LOONEY
Final 3/19/2021 Corrections Issued BRENDAN LOONEY
Green Building Final 3/19/2021 Not Ready for Inspection BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 3/19/2021 SGSOV Approved BRENDAN LOONEY
Service/Power Release 3/19/2021 Not Ready for Inspection BRENDAN LOONEY
Smoke Detectors 3/19/2021 Not Ready for Inspection BRENDAN LOONEY
Final 4/8/2021 Partial Inspection RICHARD DOCKUS
Green Building Final 4/8/2021 Approved RICHARD DOCKUS
Smoke Detectors 4/8/2021 Corrections Issued RICHARD DOCKUS
Final 4/27/2021 Conditional Approval RICHARD DOCKUS
Service/Power Release 4/27/2021 Approved RICHARD DOCKUS
Smoke Detectors 4/27/2021 Approved RICHARD DOCKUS
Final 5/4/2021 Corrections Issued DANIEL ORRANTE
Final 11/5/2021 OK to Issue CofO CHRISTOPHE COCHRAN