6201 S NORMANDIE AVE 90047

Certificate Information: 6201 S NORMANDIE AVE 90047

Application / Permit
20010-10000-00996
Plan Check / Job No.
B20LA05730
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 27 UNIT 4 STORY TYPE VA (100% AFFORDABLE) APARTMENT PER 12.22.A.25/AB 1763
Permit Issued
Issued on 5/1/2024
Issuing Office
Current Status
Issued on 5/1/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/2/2020 APPLICANT
Assigned to Plan Check Engineer 4/9/2020 LARRY LEE
Corrections Issued 4/23/2020 LARRY LEE
Quality Review Completed 4/29/2020 CHARLES CHANG
Building Plans Picked Up 5/7/2020 APPLICANT
Disabled Access Plans Picked Up 5/11/2020 APPLICANT
Applicant returned to address corrections 5/15/2020 LARRY LEE
Applicant returned to address corrections 6/22/2020 LARRY LEE
Applicant returned to address corrections 12/16/2020 LARRY LEE
Green Plans Picked Up 1/4/2021 APPLICANT
Applicant returned to address corrections 1/29/2021 LARRY LEE
Applicant returned to address corrections 2/5/2021 LARRY LEE
Applicant returned to address corrections 4/23/2021 LARRY LEE
Applicant returned to address corrections 8/5/2021 LARRY LEE
Applicant returned to address corrections 8/25/2021 LARRY LEE
Applicant returned to address corrections 9/16/2021 LARRY LEE
Applicant returned to address corrections 10/5/2021 LARRY LEE
Applicant returned to address corrections 10/27/2021 LARRY LEE
Applicant returned to address corrections 2/24/2022 LARRY LEE
Plan Check Approved 4/26/2024 KEVIN MORALES
Issued 5/1/2024 APPLICANT
TCO Issued (Expire Date: 12-13-2026) 6/16/2026 RAFAEL ESPINOZA

Permit Application Clearance Information

Building over 3-story or 36-ft Cleared 12/14/2020 CALOSHA APPROVED
Permit Cleared 2/1/2021 THAN WIN
Redevelopment Project Area Cleared 4/16/2021 GRACIELA ACOSTA
Address approval Cleared 4/21/2021 ELAINE LEI
Community Plan Implem. Overlay Cleared 4/21/2021 EDUARDO HERMOSO
Community Plan Implem. Overlay Cleared 4/21/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 4/21/2021 ELAINE LEI
Highway dedication Cleared 4/21/2021 ELAINE LEI
Sewer availability Cleared 4/21/2021 ELAINE LEI
Community Plan Implem. Overlay Cleared 5/13/2021 HELEN JADALI
Community Plan Implem. Overlay Cleared 5/13/2021 JOHN KIM
Community Plan Implem. Overlay Cleared 5/13/2021 RIDWAN HARDY
Construction near power lines Cleared 5/13/2021 RIDWAN HARDY
Construction within easement Cleared 5/13/2021 RIDWAN HARDY
Miscellaneous Cleared 5/13/2021 HELEN JADALI
Miscellaneous Cleared 5/13/2021 JOE LUCKEY
Trees in Parkway Cleared 5/13/2021 JOHN KIM
Work Adjacent to Public Way Cleared 7/30/2021 ARMEN SARKISIAN
Fire Marshall Fire Life Safety Cleared 8/18/2021 OSCAR SALGADO JR
Hydrant and Access approval Cleared 9/19/2021 JOHN CONNEALLY
Public Housing Cleared 5/12/2022 GUS VINDELL
Low Impact Development Cleared 6/7/2022 ORVAL HERNANDEZ-MARCI
DAS Clearance Cleared 2/22/2024 LARRY LEE
Roof/Waste drainage to street Cleared 2/26/2024 DAVID LOPEZ
Green Code Cleared 4/2/2024 AARON COSTA
Miscellaneous Cleared 4/10/2024 DAVID URITA
Miscellaneous Cleared 4/10/2024 DAVID URITA
Density Bonus 12.22.A.31 Cleared 4/25/2024 DORIS KWOK

Contact Information

Architect Lehrer,, Michael Berryl; Lic. No.: C12115 LEHRER ARCHITECTS LA INC   2140 HYPERION AVE    LOS ANGELES, CA 90027
Contractor Alpha Construction Co Inc; Lic. No.: 241368-B 14601 AETNA STREET      VAN NUYS, CA 91411

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/26/2024 Partial Approval JAMES POWERS
Deputy Grading 8/23/2024 Approved JONATHAN HOM
Piling/Pier/Caisson 8/23/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/6/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/9/2024 Partial Approval JAMES POWERS
Footing/Foundation/Slab 9/9/2024 Not Ready for Inspection JAMES POWERS
Piling/Pier/Caisson 9/9/2024 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 9/10/2024 Partial Approval JAMES POWERS
Footing/Foundation/Slab 9/10/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/19/2024 Partial Approval JAMES POWERS
Footing/Foundation/Slab 9/19/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 10/8/2024 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 10/8/2024 No Access for Inspection RAFAEL ESPINOZA
Wood Frame 10/8/2024 Corrections Issued RAFAEL ESPINOZA
Deputy Wood Construction 10/15/2024 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 10/16/2024 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 10/25/2024 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 10/25/2024 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 11/7/2024 Partial Approval RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 11/25/2024 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 12/9/2024 Partial Approval RAFAEL CORTES
Footing/Foundation/Slab 12/9/2024 Partial Approval RAFAEL CORTES
Green Building Rough 12/19/2024 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 12/19/2024 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 12/19/2024 Partial Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 1/6/2025 Partial Approval JAMES POWERS
Deputy Wood Construction 1/13/2025 Conditional Approval RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 1/13/2025 Not Ready for Inspection RAFAEL CORTES
Structural Steel Frame 1/13/2025 Not Ready for Inspection RAFAEL CORTES
Deputy Wood Construction 1/21/2025 Conditional Approval JOEY BUCHANAN
Deputy Steel/Welding 1/22/2025 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 1/22/2025 Partial Approval RAFAEL ESPINOZA
Structural Steel Frame 1/22/2025 Approved RAFAEL ESPINOZA
Drywall Nailing 2/10/2025 Partial Approval RAFAEL ESPINOZA
Special/Order Compliance 2/21/2025 Partial Inspection RAFAEL ESPINOZA
Deputy Wood Construction 2/27/2025 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 2/27/2025 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 3/6/2025 Not Ready for Inspection RAFAEL CORTES
Insulation 3/11/2025 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 3/12/2025 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 3/13/2025 Partial Approval RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 3/13/2025 Partial Approval RAFAEL CORTES
Insulation 3/14/2025 Partial Approval RAFAEL CORTES
Pre-Inspection 3/20/2025 Partial Approval RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 3/25/2025 Partial Approval RAFAEL ESPINOZA
Insulation 3/25/2025 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 4/3/2025 Partial Approval RAFAEL ESPINOZA
Deputy Drilled-In Anchors 4/4/2025 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 4/4/2025 Partial Approval RAFAEL ESPINOZA
Wood Frame 4/4/2025 Partial Approval RAFAEL ESPINOZA
Deputy Drilled-In Anchors 4/7/2025 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 4/7/2025 Partial Approval RAFAEL ESPINOZA
Wood Frame 4/7/2025 Partial Approval RAFAEL ESPINOZA
Insulation 4/9/2025 Partial Approval RAFAEL ESPINOZA
Insulation 4/10/2025 Partial Approval RAFAEL CORTES
Insulation 4/11/2025 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 4/21/2025 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 4/22/2025 Partial Approval RAFAEL CORTES
Drywall Nailing 4/23/2025 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 5/2/2025 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 5/9/2025 Conditional Approval RAFAEL ESPINOZA
Light Gage Steel Frame 5/9/2025 Not Ready for Inspection RAFAEL ESPINOZA
Drywall Nailing 5/27/2025 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 5/27/2025 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 6/3/2025 Partial Approval RAFAEL ESPINOZA
Structural Steel Frame 6/16/2025 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 6/23/2025 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 6/25/2025 Conditional Approval RAFAEL ESPINOZA
Light Gage Steel Frame 6/25/2025 Not Ready for Inspection RAFAEL ESPINOZA
Light Gage Steel Frame 6/26/2025 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 6/30/2025 Approved JAMES POWERS
Light Gage Steel Frame 7/3/2025 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/9/2025 Partial Approval LARRY ARNICK
Drywall Nailing 8/8/2025 No Access for Inspection RAFAEL CORTES
Interior/Exterior Lathing 8/13/2025 Partial Approval LARRY ARNICK
Light Gage Steel Frame 8/13/2025 Partial Approval LARRY ARNICK
Light Gage Steel Frame 8/15/2025 Partial Approval RAFAEL CORTES
Interior/Exterior Lathing 8/18/2025 Partial Approval RAFAEL CORTES
Light Gage Steel Frame 8/18/2025 Not Ready for Inspection RAFAEL CORTES
Drywall Nailing 8/19/2025 Partial Approval RAFAEL CORTES
Special/Order Compliance 11/7/2025 Approved RAFAEL ESPINOZA
Special/Order Compliance 12/9/2025 Partial Approval RAFAEL CORTES
Structural Steel Frame 12/19/2025 Partial Approval RAFAEL CORTES
Special/Order Compliance 4/30/2026 Approved JOEY BUCHANAN
Final 5/26/2026 Partial Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 5/26/2026 Approved RAFAEL ESPINOZA
Green Building Final 5/26/2026 Approved RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 5/26/2026 SGSOV Not Ready RAFAEL ESPINOZA
Smoke Detectors 5/26/2026 Not Ready for Inspection RAFAEL ESPINOZA
Final 5/29/2026 Not Ready for Inspection RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 5/29/2026 SGSOV Not Ready RAFAEL CORTES
Smoke Detectors 5/29/2026 Not Ready for Inspection RAFAEL CORTES
Final 6/16/2026 Not Ready for Inspection RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 6/16/2026 SGSOV Approved RAFAEL CORTES
Smoke Detectors 6/16/2026 Approved RAFAEL CORTES