1165 W 13TH ST 90731
Certificate Information: 1165 W 13TH ST 90731
- Application / Permit
- 20010-10000-00991
- Plan Check / Job No.
- B20LA05698
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL OF (E) SFD W/ (6'-2" X 19'-6") ADDITION AT THE FRONT AND (10'-0"X11'-1") ADDITION AT THE REAR. ASPHALT COMPOSITION SHINGLES RE-ROOFING.
- Permit Issued
- Issued on 6/8/2020
- Issuing Office
- Current Status
- CofO Issued on 10/23/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/14/2020 | STARR CHEN |
| Corrections Issued | 4/14/2020 | STARR CHEN |
| Building Plans Picked Up | 4/14/2020 | APPLICANT |
| Plan Check Approved | 5/22/2020 | FARSHAD ALIMOHAMADI |
| Issued | 6/8/2020 | APPLICANT |
| CofO in Progress | 10/19/2021 | ANSON MAGLASANG |
| Permit Finaled | 10/23/2021 | DEROLD HAUFF |
| CofO Issued | 10/23/2021 | DEROLD HAUFF |
| Permit Finaled | 10/23/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/27/2020 | ELENA LOPEZ |
| Roof/Waste drainage to street | Cleared | 4/27/2020 | ELENA LOPEZ |
| Sewer availability | Cleared | 4/27/2020 | ELENA LOPEZ |
| Grading Pre-Inspection | Cleared | 5/8/2020 | PATRICK MISCHLICH |
| Green Code | Cleared | 5/22/2020 | STARR CHEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/15/2020 | Approved | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 7/16/2020 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 7/16/2020 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 8/19/2020 | Partial Inspection | JOHN KLARIN |
| Final | 8/19/2020 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Final | 8/19/2020 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Rough | 8/19/2020 | Not Ready for Inspection | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 8/19/2020 | SGSOV Not Required | JOHN KLARIN |
| Smoke Detectors | 8/19/2020 | Not Ready for Inspection | JOHN KLARIN |
| Insulation | 8/25/2020 | Partial Inspection | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2020 | Approved | JOHN KLARIN |
| Deputy Drilled-In Anchors | 9/1/2020 | Approved | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 9/3/2020 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 9/28/2020 | Corrections Issued | JOHN KLARIN |
| Final | 9/28/2020 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Final | 9/28/2020 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Rough | 9/28/2020 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 9/28/2020 | Not Ready for Inspection | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2020 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 10/21/2020 | Corrections Issued | JOHN KLARIN |
| HVAC-Rough | 10/21/2020 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 10/21/2020 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 10/23/2020 | Approved | JOHN KLARIN |
| HVAC-Rough | 10/23/2020 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 10/23/2020 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 10/23/2020 | Approved | JOHN KLARIN |
| Insulation | 11/2/2020 | Approved | JOHN KLARIN |
| Drywall Nailing | 11/4/2020 | Approved | JOHN KLARIN |
| Drywall Nailing | 11/4/2020 | Off-Hour Fees Due | |
| BUILDING-Rough-Frame | 9/24/2021 | Approved | ANSON MAGLASANG |
| Final | 9/24/2021 | Corrections Issued | ANSON MAGLASANG |
| Green Building Final | 9/24/2021 | Corrections Issued | ANSON MAGLASANG |
| Green Building Rough | 9/24/2021 | Approved | ANSON MAGLASANG |
| Smoke Detectors | 9/24/2021 | Approved | ANSON MAGLASANG |
| Final | 10/14/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| Green Building Final | 10/14/2021 | Approved | ANSON MAGLASANG |
| Final | 10/19/2021 | OK to Issue CofO | ANSON MAGLASANG |