15427 W MILLDALE DR 90077
Certificate Information: 15427 W MILLDALE DR 90077
- Application / Permit
- 20010-10000-00957
- Plan Check / Job No.
- B20LA05559
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW TWO-STORY SFD WITH ATTACHED 3-CAR GARAGE 1 OF 3
- Permit Issued
- Issued on 7/19/2021
- Issuing Office
- Current Status
- CofO Issued on 1/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/2/2020 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 4/10/2020 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 4/15/2020 | STANLEY RAAP |
| Green Plans Picked Up | 5/13/2020 | APPLICANT |
| Applicant returned to address corrections | 11/18/2020 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 5/4/2021 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 5/11/2021 | FARSHAD ALIMOHAMADI |
| Issued | 7/19/2021 | APPLICANT |
| Building Plans Picked Up | 7/27/2021 | APPLICANT |
| CofO in Progress | 1/16/2025 | CARLOS MATAMOROS |
| Permit Finaled | 1/27/2025 | RICHARD STEINBACH |
| CofO Issued | 1/27/2025 | RICHARD STEINBACH |
| Permit Finaled | 1/27/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 7/2/2020 | CATHERINE ADROVER |
| BHO/Hillside ordinance | Cleared | 7/6/2020 | CATHERINE ADROVER |
| BHO/Hillside ordinance | Cleared | 7/6/2020 | CATHERINE ADROVER |
| BHO/Hillside ordinance | Cleared | 7/6/2020 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2020 | CATHERINE ADROVER |
| Permit | Cleared | 7/6/2020 | CATHERINE ADROVER |
| Sewer availability | Cleared | 7/8/2020 | CATHERINE ADROVER |
| Hydrant and Access approval | Cleared | 8/12/2020 | MATTHEW CRAIG |
| Specific Plan | Cleared | 2/1/2021 | MARITZA PRZEKOP |
| Miscellaneous | Cleared | 3/2/2021 | DANIEL CORONADO |
| ZI | Cleared | 3/2/2021 | DANIEL CORONADO |
| Low Impact Development | Cleared | 3/17/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 3/24/2021 | DINAH GARIN |
| Trees in Parkway | Cleared | 4/7/2021 | JOHN KIM |
| GPI Written Notices | Cleared | 4/27/2021 | FARSHAD ALIMOHAMADI |
| Grading Pre-Inspection | Cleared | 4/27/2021 | FARSHAD ALIMOHAMADI |
| Green Code | Cleared | 4/27/2021 | DONALD CRICHLOW |
Contact Information
| Architect | Eckelberry,, Anthony Evans; Lic. No.: C17278 | 4535 GAINSBOROUGH AVE. LOS ANGELES, CA 90027 |
| Contractor | Triumph Construction Inc; Lic. No.: 688865-B | 1526 14TH STREET SUITE #108 SANTA MONICA, CA 90404 |
| Engineer | Onishi,, Robert K; Lic. No.: S3705 | 4438 LINDBLADE DRIVE LOS ANGELES, CA 90066 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/11/2022 | Corrections Issued | CARLOS MATAMOROS |
| Pre-Inspection | 1/12/2022 | Approved | CARLOS MATAMOROS |
| Underground Mechanical | 3/10/2022 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 3/14/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Reinf. Concrete | 3/16/2022 | Conditional Approval | CARLOS MATAMOROS |
| Underground Mechanical | 4/21/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Underground Mechanical | 4/22/2022 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 5/2/2022 | Partial Approval | CARLOS MATAMOROS |
| Deputy Steel/Welding | 5/13/2022 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Steel/Welding | 6/2/2022 | Approved | MICHAEL PELHAM |
| Deputy Steel/Welding | 6/8/2022 | Conditional Approval | MICHAEL PELHAM |
| Deputy Steel/Welding | 7/6/2022 | Conditional Approval | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 7/12/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Green Building Rough | 7/12/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Structural Steel Frame | 7/12/2022 | Partial Approval | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 7/12/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 7/14/2022 | Conditional Approval | CARLOS MATAMOROS |
| Special/Order Compliance | 7/22/2022 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 9/9/2022 | Approved | CARLOS MATAMOROS |
| Deputy Steel/Welding | 9/22/2022 | Conditional Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2023 | Corrections Issued | CARLOS MATAMOROS |
| HVAC-Rough | 3/3/2023 | Corrections Issued | CARLOS MATAMOROS |
| Deputy Steel/Welding | 5/12/2023 | Conditional Approval | MICHAEL PELHAM |
| HVAC-Rough | 6/23/2023 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Rough | 6/23/2023 | Partial Approval | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 6/26/2023 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Rough | 6/26/2023 | Conditional Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 7/21/2023 | Approved | CARLOS MATAMOROS |
| Insulation | 7/21/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 7/21/2023 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 8/25/2023 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 8/25/2023 | Approved | CARLOS MATAMOROS |
| Insulation | 8/25/2023 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 8/25/2023 | Approved | CARLOS MATAMOROS |
| Shower Pan | 8/25/2023 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 9/15/2023 | Partial Approval | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 9/27/2023 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 10/2/2024 | Corrections Issued | CARLOS MATAMOROS |
| HVAC-Final | 10/2/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Final | 10/2/2024 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Final | 10/18/2024 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Final | 10/18/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Final | 10/23/2024 | Approved | CARLOS MATAMOROS |
| Final | 10/23/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Gas Test | 10/23/2024 | Approved | CARLOS MATAMOROS |
| Green Building Final | 10/23/2024 | Corrections Issued | CARLOS MATAMOROS |
| HVAC-Final | 10/23/2024 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Final | 10/23/2024 | Approved | CARLOS MATAMOROS |
| Reinforced Masonry Frame | 10/23/2024 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 10/23/2024 | SGSOV Not Ready | CARLOS MATAMOROS |
| Service/Power Release | 10/23/2024 | Approved | CARLOS MATAMOROS |
| Smoke Detectors | 10/23/2024 | Approved | CARLOS MATAMOROS |
| Structural Steel Frame | 10/23/2024 | Approved | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 10/23/2024 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 11/20/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 11/20/2024 | SGSOV Not Ready | CARLOS MATAMOROS |
| Final | 1/15/2025 | OK to Issue CofO | CARLOS MATAMOROS |
| Green Building Final | 1/15/2025 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 1/15/2025 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 1/15/2025 | SGSOV Approved | CARLOS MATAMOROS |
| Special/Order Compliance | 1/17/2025 | Corrections Issued | CARLOS MATAMOROS |