14924 W CAMAROSA DR 90272
Certificate Information: 14924 W CAMAROSA DR 90272
- Application / Permit
- 20010-10000-00881
- Plan Check / Job No.
- B20LA05169
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- NEW 1200SQ.FT ACCESSARY LIVING QUARTER
- Permit Issued
- Issued on 9/8/2020
- Issuing Office
- Current Status
- CofO Issued on 9/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/20/2020 | RACHEL BEYENE |
| Corrections Issued | 3/25/2020 | RACHEL BEYENE |
| Quality Review Completed | 4/2/2020 | STANLEY RAAP |
| Applicant returned to address corrections | 5/29/2020 | RACHEL BEYENE |
| Applicant returned to address corrections | 6/5/2020 | RACHEL BEYENE |
| Applicant returned to address corrections | 6/17/2020 | RACHEL BEYENE |
| Applicant returned to address corrections | 6/26/2020 | RACHEL BEYENE |
| Green Plans Picked Up | 7/21/2020 | APPLICANT |
| Applicant returned to address corrections | 8/19/2020 | RACHEL BEYENE |
| Plan Check Approved | 9/4/2020 | RAHEL BEYENE |
| Issued | 9/8/2020 | APPLICANT |
| Building Plans Picked Up | 9/9/2020 | APPLICANT |
| CofO in Progress | 9/11/2023 | EVAN COOPER |
| Permit Finaled | 9/21/2023 | DANIEL ORRANTE |
| CofO Issued | 9/21/2023 | DANIEL ORRANTE |
| Permit Finaled | 9/21/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| City Hist. Cultural Monument | Cleared | 5/15/2020 | LAMBERT GIESSINGER |
| HPOZ | Cleared | 5/15/2020 | LAMBERT GIESSINGER |
| Hist. Property Cntrct Mgr Appr | Cleared | 5/15/2020 | LAMBERT GIESSINGER |
| Sewer availability | Cleared | 5/22/2020 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 5/29/2020 | VASIL MIHALEV |
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2020 | DINAH GARIN |
| Coastal Zone | Cleared | 6/17/2020 | JOE LUCKEY |
| Disturb/Remove Protected Trees | Cleared | 6/17/2020 | STEPHEN DUPREY |
| Green Code | Cleared | 7/21/2020 | RAHEL BEYENE |
| Low Impact Development | Cleared | 8/6/2020 | MITESH PATEL |
| GPI Written Notices | Cleared | 8/19/2020 | RAHEL BEYENE |
| Roof/Waste drainage to street | Cleared | 8/26/2020 | DINAH GARIN |
Contact Information
| Architect | Rios,, Mark William; Lic. No.: C15744 | 3101 W EXPOSITION PLACE LOS ANGELES, CA 90018 |
| Contractor | G H B W; Lic. No.: 983577-B | 3209 LA CIENAGA AVE LOS ANGELES, CA 90034 |
| Engineer | Uhles,, Scott Delane; Lic. No.: C72391 | 2909 ARIZONA AVE 5 SANTA MONICA, CA 90404 |
| Engineer | Varela, Olivas, Benjamin; Lic. No.: S5714 | 12831 PANAMA STREET LOS ANGELES, CA 90066 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/29/2020 | Approved | ANDREW NAVE |
| Footing/Foundation/Slab | 10/21/2020 | Partial Approval | ANDREW NAVE |
| Deputy Steel/Welding | 11/13/2020 | Conditional Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 11/20/2020 | Corrections Issued | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 11/23/2020 | Partial Approval | ANDREW NAVE |
| Underground Mechanical | 12/1/2020 | Approved | ANDREW NAVE |
| Deputy Steel/Welding | 12/3/2020 | Conditional Approval | ANDREW NAVE |
| Reinforced Concrete Frame | 12/10/2020 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2021 | Partial Approval | ANDREW NAVE |
| PLUMBING-Rough | 1/8/2021 | Partial Approval | ANDREW NAVE |
| Sewer | 1/8/2021 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2021 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 8/6/2021 | Approved | ANDREW NAVE |
| Sewer | 8/26/2021 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 1/5/2022 | Partial Approval | ANDREW NAVE |
| Shower Pan | 1/5/2022 | Partial Approval | ANDREW NAVE |
| Shower Pan | 1/11/2022 | Approved | ANDREW NAVE |
| ELECTRICAL-Rough | 1/19/2022 | Corrections Issued | ANDREW NAVE |
| HVAC-Rough | 1/19/2022 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 5/19/2022 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 5/23/2022 | Corrections Issued | ANDREW NAVE |
| Green Building Rough | 5/23/2022 | Approved | ANDREW NAVE |
| Insulation | 5/23/2022 | Approved | ANDREW NAVE |
| Verify Sprinkler Sign Off | 5/23/2022 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 5/27/2022 | Approved | ANDREW NAVE |
| ELECTRICAL-Rough | 5/27/2022 | Approved | ANDREW NAVE |
| Insulation | 5/27/2022 | Approved | ANDREW NAVE |
| Special/Order Compliance | 5/27/2022 | Corrections Issued | ANDREW NAVE |
| Drywall Nailing | 6/29/2022 | Approved | ANDREW NAVE |
| PLUMBING-Final | 1/6/2023 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Final | 1/12/2023 | Corrections Issued | CLAYTON GRAHAM |
| PLUMBING-Final | 1/13/2023 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Final | 1/17/2023 | Partial Approval | BRENDAN LOONEY |
| HVAC-Final | 1/17/2023 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Final | 1/17/2023 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Final | 1/24/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Final | 2/23/2023 | Approved | STEPHANIE SWANSON |
| Final | 2/23/2023 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 2/23/2023 | Approved | STEPHANIE SWANSON |
| Green Building Final | 2/23/2023 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 2/23/2023 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 2/23/2023 | SGSOV Not Ready | STEPHANIE SWANSON |
| Service/Power Release | 2/23/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| Smoke Detectors | 2/23/2023 | Approved | STEPHANIE SWANSON |
| Final | 3/6/2023 | Corrections Issued | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 3/6/2023 | SGSOV Approved | BRENDAN LOONEY |
| Service/Power Release | 3/6/2023 | Not Required | BRENDAN LOONEY |
| Final | 6/27/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Final | 7/5/2023 | Corrections Issued | DAVID FEILER |
| Service/Power Release | 7/10/2023 | Approved | DAVID FEILER |
| Final | 9/11/2023 | OK to Issue CofO | EVAN COOPER |