14924 W CAMAROSA DR 90272

Certificate Information: 14924 W CAMAROSA DR 90272

Application / Permit
20010-10000-00881
Plan Check / Job No.
B20LA05169
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
NEW 1200SQ.FT ACCESSARY LIVING QUARTER
Permit Issued
Issued on 9/8/2020
Issuing Office
Current Status
CofO Issued on 9/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/13/2020 APPLICANT
Assigned to Plan Check Engineer 3/20/2020 RACHEL BEYENE
Corrections Issued 3/25/2020 RACHEL BEYENE
Quality Review Completed 4/2/2020 STANLEY RAAP
Applicant returned to address corrections 5/29/2020 RACHEL BEYENE
Applicant returned to address corrections 6/5/2020 RACHEL BEYENE
Applicant returned to address corrections 6/17/2020 RACHEL BEYENE
Applicant returned to address corrections 6/26/2020 RACHEL BEYENE
Green Plans Picked Up 7/21/2020 APPLICANT
Applicant returned to address corrections 8/19/2020 RACHEL BEYENE
Plan Check Approved 9/4/2020 RAHEL BEYENE
Issued 9/8/2020 APPLICANT
Building Plans Picked Up 9/9/2020 APPLICANT
CofO in Progress 9/11/2023 EVAN COOPER
Permit Finaled 9/21/2023 DANIEL ORRANTE
CofO Issued 9/21/2023 DANIEL ORRANTE
Permit Finaled 9/21/2023 DANIEL ORRANTE

Permit Application Clearance Information

City Hist. Cultural Monument Cleared 5/15/2020 LAMBERT GIESSINGER
HPOZ Cleared 5/15/2020 LAMBERT GIESSINGER
Hist. Property Cntrct Mgr Appr Cleared 5/15/2020 LAMBERT GIESSINGER
Sewer availability Cleared 5/22/2020 DINAH GARIN
Grading Pre-Inspection Cleared 5/29/2020 VASIL MIHALEV
Eng Process Fee Ord 176,300 Cleared 6/2/2020 DINAH GARIN
Coastal Zone Cleared 6/17/2020 JOE LUCKEY
Disturb/Remove Protected Trees Cleared 6/17/2020 STEPHEN DUPREY
Green Code Cleared 7/21/2020 RAHEL BEYENE
Low Impact Development Cleared 8/6/2020 MITESH PATEL
GPI Written Notices Cleared 8/19/2020 RAHEL BEYENE
Roof/Waste drainage to street Cleared 8/26/2020 DINAH GARIN

Contact Information

Architect Rios,, Mark William; Lic. No.: C15744 3101 W EXPOSITION PLACE      LOS ANGELES, CA 90018
Contractor G H B W; Lic. No.: 983577-B 3209 LA CIENAGA AVE      LOS ANGELES, CA 90034
Engineer Uhles,, Scott Delane; Lic. No.: C72391 2909 ARIZONA AVE 5      SANTA MONICA, CA 90404
Engineer Varela, Olivas, Benjamin; Lic. No.: S5714 12831 PANAMA STREET      LOS ANGELES, CA 90066

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/29/2020 Approved ANDREW NAVE
Footing/Foundation/Slab 10/21/2020 Partial Approval ANDREW NAVE
Deputy Steel/Welding 11/13/2020 Conditional Approval ANDREW NAVE
Footing/Foundation/Slab 11/20/2020 Corrections Issued ANDREW NAVE
Excavation/Setback/Form/Re-Bar 11/23/2020 Partial Approval ANDREW NAVE
Underground Mechanical 12/1/2020 Approved ANDREW NAVE
Deputy Steel/Welding 12/3/2020 Conditional Approval ANDREW NAVE
Reinforced Concrete Frame 12/10/2020 Approved ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 1/6/2021 Partial Approval ANDREW NAVE
PLUMBING-Rough 1/8/2021 Partial Approval ANDREW NAVE
Sewer 1/8/2021 Partial Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 1/21/2021 Approved ANDREW NAVE
PLUMBING-Rough 8/6/2021 Approved ANDREW NAVE
Sewer 8/26/2021 Approved ANDREW NAVE
Interior/Exterior Lathing 1/5/2022 Partial Approval ANDREW NAVE
Shower Pan 1/5/2022 Partial Approval ANDREW NAVE
Shower Pan 1/11/2022 Approved ANDREW NAVE
ELECTRICAL-Rough 1/19/2022 Corrections Issued ANDREW NAVE
HVAC-Rough 1/19/2022 Approved ANDREW NAVE
Interior/Exterior Lathing 5/19/2022 Approved ANDREW NAVE
BUILDING-Rough-Frame 5/23/2022 Corrections Issued ANDREW NAVE
Green Building Rough 5/23/2022 Approved ANDREW NAVE
Insulation 5/23/2022 Approved ANDREW NAVE
Verify Sprinkler Sign Off 5/23/2022 Approved ANDREW NAVE
BUILDING-Rough-Frame 5/27/2022 Approved ANDREW NAVE
ELECTRICAL-Rough 5/27/2022 Approved ANDREW NAVE
Insulation 5/27/2022 Approved ANDREW NAVE
Special/Order Compliance 5/27/2022 Corrections Issued ANDREW NAVE
Drywall Nailing 6/29/2022 Approved ANDREW NAVE
PLUMBING-Final 1/6/2023 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Final 1/12/2023 Corrections Issued CLAYTON GRAHAM
PLUMBING-Final 1/13/2023 Approved BRENDAN LOONEY
ELECTRICAL-Final 1/17/2023 Partial Approval BRENDAN LOONEY
HVAC-Final 1/17/2023 Corrections Issued BRENDAN LOONEY
PLUMBING-Final 1/17/2023 Approved BRENDAN LOONEY
ELECTRICAL-Final 1/24/2023 Not Ready for Inspection CLAYTON GRAHAM
ELECTRICAL-Final 2/23/2023 Approved STEPHANIE SWANSON
Final 2/23/2023 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 2/23/2023 Approved STEPHANIE SWANSON
Green Building Final 2/23/2023 Approved STEPHANIE SWANSON
HVAC-Final 2/23/2023 Approved STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 2/23/2023 SGSOV Not Ready STEPHANIE SWANSON
Service/Power Release 2/23/2023 Not Ready for Inspection STEPHANIE SWANSON
Smoke Detectors 2/23/2023 Approved STEPHANIE SWANSON
Final 3/6/2023 Corrections Issued BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 3/6/2023 SGSOV Approved BRENDAN LOONEY
Service/Power Release 3/6/2023 Not Required BRENDAN LOONEY
Final 6/27/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Final 7/5/2023 Corrections Issued DAVID FEILER
Service/Power Release 7/10/2023 Approved DAVID FEILER
Final 9/11/2023 OK to Issue CofO EVAN COOPER